HomeMy WebLinkAbout2021-116WORK ORDER 22
Rails to Trails 1.4 Mile Extension of the Historic Trans -Florida Rail Trail
This Work Order Number 22 is entered into as of this 17 1
day of August, 2021, pursuant to that
certain Continuing Consulting Engineering Services Agreement for Professional Services entered into as of this
17th day of April, 2018 (collectively referred to as the "Agreement"), by and between INDIAN RIVER COUNTY,
a political subdivision of the State of Florida ("COUNTY") and MBV Engineering, Inc. ("Consultant').
The COUNTY has selected the Consultant to perform the professional services set forth on
Exhibit A (Scope of Work), attached to this Work Order and made part hereof by this reference. The
professional services will be performed by the Consultant for the fee schedule set forth in Exhibit D
(Fee Schedule), attached to this Work Order and made a part hereof by this reference. The Consultant
will perform the professional services within the timeframe more particularly set forth in Exhibit B
(Time Schedule), attached to this Work Order and made a part hereof by this reference all in
accordance with the terms and provisions set forth in the Agreement. Pursuant to paragraph 1.4 of
the Agreement, nothing contained in any Work Order shall conflict with the terms of the Agreement
and the terms of the Agreement shall be deemed to be incorporated in each individual Work Order as
if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the date first
written above.
CONSULTANT:
MBV Engineering, Inc.
By: By:
Title: Vice President 1
BOARD OF COUNTY COMMISSIONERS
OF INDIAN RIVER COUNTY G..5M.SS���✓F>.
BCC Approved Date:
Q) - � *
Joseph E. F escher, Chairmipn`-,
August 17, 2021 SER COUP..
Attest: Jeffrey R. Smith, Clerk of Court and Comptroller
By: 2aOA,
De uty Clerk
Approved:
Approved as to form and legal sufficiency:
COUNTY Attorney
EXHIBIT A - SCOPE OF WORK
It is understood the COUNTY desires to construct Phase 2 of the Historic Trans Florida Rail Trail system
from the west side of the 1-95 Bridge approach to the City of Fellsmere city limits. The 1.4 -mile trail
extension will pass through the St. Sebastian River Preserve and will follow the Historic Trans -Florida
Railroad Route. We understand the upgraded trail will convert the trail to an asphalt paved surface
with several culvert crossing installations to re -connect and rehydrate existing wetlands. It is also
understood the multi -use trail will also provide for a safety upgrade for this area by acting as a fire
break for the St. Sebastian River Preserve and provide for safer egress movements for emergency
vehicles.
Through preliminary coordination with county staff and the St. Johns River Water Management District
(SJRWMD), it is understood the project will require environmental design and permitting and that the
COUNTY will contract these services separately with the selected environmental consultant. MBV will
coordinate, as necessary, with the selected consultant to provide all plans and documents necessary
for the jurisdictional permitting. All environmental design, studies, reports, and investigations will be
completed by the selected consultant and provided to MBV as needed for submissions to the
jurisdictional agencies.
It is understood, through meetings with SJRWMD, no stormwater design will be required other than
the development for the project's Erosion Control Plans. Therefore, drainage modeling and permitting
are not included in this Work Order. It was further understood, through coordination with SJRWMD,
the project environmental permitting must also -be reviewed and approved by Florida Department of
Environmental Protection (FDEP) under the new 404 Assumed Waters requirement. This permitting
will be conducted by the COUNTY's environmental consultant and MBV will assist with documents, as
necessary, in this coordination.
Project survey will be provided by the COUNTY. Survey shall be inclusive of topography, above -ground
infrastructure, any utility and underground infrastructure, wetland or preserve area(s) flagging, that
may be required for design in the influence area of the proposed project limits. All vertical and
horizontal locations shall be the responsibility of the COUNTY, or COUNTY's designated consultant, and
provided to MBV for use in the proposed design plans. MBV shall coordinate and work with COUNTY,
as, needed, on the necessary plan coordination for the existing conditions information. Furthermore, it
is understood that IRC will coordinate with the Florida Department of Transportation (FDOT) during
the project and that MBV will assist and provide all necessary design documentation, as needed, to
support the coordination.
The CONSULTANT proposes to provide the COUNTY with the necessary design plans and engineering
to complete the below detailed scope of work. associated with the roadway safety improvements
project and as further described below.
Task 1- Trail Route & Topographic Survey Review and Coordination
MBV will coordinate with the COUNTY, or COUNTY's survey consultant, as required, on the existing
conditions survey data and information. It is understood COUNTY will provide all necessary topographic
survey data in CAD format to MBV for utilization in the design plans. It is also understood all vertical
and horizontal locates will also be provided by the COUNTY or COUNTY's survey consultant. MBV shall
review provided survey data and shall provide in writing to the COUNTY comments for any areas
requiring further data collection needed to assist in the proper project design. MBV shall utilize final
existing conditions data for the base line information for the project.
Task 2 - Trail Construction Plans
The trail construction plans shall be developed to provide design for the 1.4 -mile length of the Historic
Trail from the west side of the 1-95 Bridge approach to the City of Fellsmere city limits. The plans will
reflect the design and details to include the construction of the 1.4 -mile section trail from the limits
stated above.
The construction plans shall include plan and profile views of the proposed trail and up to (45) cross-
sections at intervals along the 1.4 -mile corridor improvement area, or at more frequent intervals near
sensitive design areas. Trail plans shall include paving and grading design with applicable details, as
required. It is understood that minor drainage infrastructure is anticipated to re -connect and re -
hydrate existing wetlands and will, therefore, be detailed accordingly in the .trail improvement plans.
All plans will be prepared in accordance with the latest design standards and practices (MUTCD) and
the FDOT Standard Specifications and Indices. Trail plans shall depict existing rights-of-way, section
lines, property lines (as applicable), temporary construction easements (as applicable) and center line
of construction. Erosion control plans and applicable details sheets shall be developed, as applicable,
to support the roadway project.
All specifications shall be noted and contained on the trail construction plans and shall reference either
Indian River County and/or FDOT Specifications for Road and Bridge Construction. Any deviations from
County and/or FDOT Specifications for Road and Bridge Construction shall be noted and clarified on
the construction plans.
Task 3 - County Reviews
The CONSULTANT will attend two (2) progress review meetings with the COUNTY staff at the 50 and
100 percent levels of design completion. Design plans will be provided to the COUNTY at the 50% design
milestone for review. COUNTY will provide to CONSULTANT written comments at each review phase.
CONSULTANT will rely on COUNTY to coordinate with Florida Department of Transportation (FDOT) for
the proper reviews of said plans. MBV will incorporate any comments from FDOT into the plans as
provided and upon approval by COUNTY. This task includes revisions to plans from each COUNTY and
FDOT review within reasonable scope of the project.
Task 4 - Permitting
Through a coordination call with SJRWMD staff, it was acknowledged that the proposed improvements
will require an Individual Permit Modification to SJRWMD Permit No.: 141651-1. Stormwater Drainage
Modeling will not be required but all Erosion Control measures must be designed and accounted for.
A joint application will be required that will include all the necessary environmental applications,
reports, plans and documents to be submitted with the modification application. It is also understood
the project will require approval from the FDEP under the new 404 Assumed Waters policy. All
Environmental permitting design and coordination will be conducted by the COUNTY's selected
environmental consultant and provided to MBV as needed for the permit applications process.
COUNTY shall be responsible for the payment of permit application fees.
Task 5 - Cost Estimates and Pay Items
The consultant will produce an Opinion of Probable Cost (OPC) at the 100% design milestone of the
project. A summary of pay items sheet shall be prepared and incorporated into the 100% (Final) plans
submission. The final plans (signed and sealed) will be provided to COUNTY based upon English units
and provided in digital and PDF formats.
Task 6 - Bidding Phase
The COUNTY shall be responsible for providing the front-end bid documents, bid opening date,
advertisement of the bid, scheduling the pre-bid meeting, and scheduling the bid opening. The
Consultant will provide the following:
• Preparation of civil plan documents for bidding
• Attendance at pre-bid meeting
• Responses to requests for additional information (RAIs) from bidders
NOTE: All construction specifications will be on the applicable Civil plan sheets in lieu of a specifications
manual. The Consultant will prepare a pdf file of the final bid package for the COUNTY's use in
distribution to prospective bidders via DemandStar.
Task 7 - Construction Phase
The Consultant shall provide the below services during the Construction Phase. Should additional
Construction Services be desired, CONSULTANT can provide COUNTY Amendment to the Work Order
for the desired additional services.
• Shop drawings review of civil site components
• Attendance at one (1) pre -construction meeting
• Coordination with COUNTY Planning and Public Works inspection staff for RAIs during construction
• RAI coordination with selected contractor
• Review of project as-builts provided to CONSULTANT by COUNTY
• Certification by E.O.R. to COUNTY, SJRWMD and FDEP for Civil Portion
EXHIBIT B - SCHEDULE
Upon authorization to proceed by the COUNTY, the above described services will be provided based
on the following schedule:
• Interim Submittal (50% design drawings)
• Construction (100% design drawings)
90 days from the latter of the issuance of
Notice to Proceed or receipt of the project
survey
90 days from 50% Milestone Review*
*It should be noted, through coordination with the SJRWMD, permitting with the FDEP for the
Environmental portion of the project under the new 404 Assumed Waters Policy may take additional
time. Though the construction plans may be deemed complete by all parties, it is possible the FDEP
approval may not yet be available.
EXHIBIT C = DELIVERABLES
The CONSULTANT shall provide the COUNTY with the following at the designated milestones:
• Interim (50%) completion:
o Three (3) sets of plans in FDOT 11"x17" format
o One electronic version of plans set in PDF format
• Construction (100%) completion:
o Three (3) sets of plans in FDOT 11"x17" format (signed & sealed)
o One (1) Opinion of Probable Cost (OPC)
o One (1) electronic version of the plans in pdf and CAD format
EXHIBIT D - FEE SCHEDULE
The COUNTY agrees to pay and the Consultant agrees to accept for services rendered, pursuant to this
Agreement, fees inclusive of expenses in accordance with the following:
Task
Fee
Task 1: Trail Route & Topographic Survey Review and Coordination
$4,400
Task 2: Trail Construction Plans
$ 43,500
Task 3: County Reviews
$ 5,500
Task 4: Permitting
$ 9,200
Task 5: Construction Estimates & Pay Items
$ 1,250
Task 6: Bidding Phase
$ 3,400
LUMP SUM TOTAL
$67,250.
Task 7: Construction Phase (HRLY Not -To -Exceed)
$ 17,500
HRLY NOT -TO -EXCEED TOTAL
$17,500
Note: The above fee schedule represents a Lump Sum fee for Tasks 1-6. Task 7 will be
billed on an hourly rate bases as the services are required with a not -to -exceed fee
amount.
ADDITIONAL SERVICES
When required by the COUNTY or the Contract Documents, where circumstances exist beyond the
Consultant's control, Consultant shall provide or obtain from others, as circumstances required, those
additional services not listed as part of the Work Order, the Consultant shall notify the COUNTY
promptly prior to commencing said Additional Services, and if agreed upon, will be paid for by COUNTY
in accordance with the Master Agreement, Professionals and vendor intended to provide additional
services shall first be approved by the COUNTY, in writing, by the COUNTY's Project Manager.
The COUNTY has selected the Consultant to perform the professional services set forth on this Work
Order. The professional services will be performed by the Consultant for the fee schedule set forth in
this Work Order. The Consultant will perform the professional services within the timeframe more
particularly set forth in this Work Order in accordance with the terms and provisions set forth in the
Agreement. Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work Order shall
conflict with the terms of the Agreement and the terms of the Agreement shall be deemed to be
incorporated in each individual Work Order as if fully set forth herein.