HomeMy WebLinkAbout2021-159AWORK ORDER NUMBER 2018029-9
SECTOR 5 YEAR 1 POST CONSTRUCTION ENGINEERING REPORT
This Work Order Number 2018029-9 is entered into as of this 5th day of
October , 2021 pursuant to that certain Contract Agreement relating to Engineering
and Biological support services for Sector 5 (Vero Beach) Beach and Dune Renourishment
Project entered into as April 3, 2018 ("Agreement"), between Indian River County, a
political subdivision of the State of Florida ("COUNTY") and Aptim Environmental &
Infrastructure, LLC ("CONSULTANT").
The COUNTY has selected the CONSULTANT to perform the professional
services set forth on Exhibit 1, attached to this Work Order and made part hereof by this
reference. The professional services will be performed by the CONSULTANT for the fee
schedule set forth in Exhibit 1. The CONSULTANT will perform the professional services
within the timeframe more particularly set forth in Exhibit 1, all in accordance with the
terms and provisions set forth in the Agreement. Pursuant to paragraph 1.3 of the
Agreement, nothing contained in any Work Order shall conflict with the terms of the
Agreement and the terms of the Agreement shall be deemed to be incorporated in each
individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of
the date first written above.
CONSULTANT BOARD OF COUNTY COMMISSIONERS
Aptim Environmental & Infrastructure. LLC. -OF INDIAN RIVER COUNTY ...1114" •11
Title: Program Manager
Date: 1 V 1[2, ll
as
ME
Lo
�y kph ...... 9
B?st:Jeffrey
G v.
eph E. Flescher, Chairmah W'
A R. Smith, Clerk of Co,,�,,,�
Comp r
By:
Seal) Deputy Clerk
William K. DeBraal, Deputy County Attorney
)>iw
APTIM
September 22, 2021
Eric Charest
Coastal Division
Indian River County Public Works
1801 27th Street
Vero Beach, FL 32960
Aptim Environmental & Infrastructure, LLC
6401 Congress Avenue, Suite 140
Boca Raton, FL 33487
Tel: +1 561 391 8102
Fax: +1 561 391 9116
www.aptim.com
Subject: Indian River County, FL
Sector 5 — 2018029 — Work Order #9
Year 1 Post -Construction Engineering Monitoring Report
Dear Eric:
This proposal outlines a scope of work for Aptim Environmental & Infrastructure, LLC (APTIM) to provide
a Year 1 post -construction monitoring report for the Sector 5 Beach and Dune Restoration Project (R-70
to R-86) in Indian River County, which was completed in February 2020. This proposal was prepared to
fulfill the stipulations of the Joint Coastal Permit (JCP) No. 0363427 -001 -JC and modification 0363427-
002 -JN dated September 9, 2019 for the Sector 5 Beach and Dune Restoration Project. The scope and
fee were developed following the provisions of the Professional Services Agreement between Indian
River County and APTIM, dated April 3, 2018, to provide engineering and biological support services in
support of the Sector 5 Beach and Dune Restoration Project (RFQ#2018029).
Scope of Work
Volumetric and contour changes at the Sector 5 Beach will be calculated using surveys that were
collected at the FDEP R -monuments by the County's surveyor, Morgan & Eklund. APTIM will review the
County's routine Spring/Summer 2021 beach profile survey data to ensure that it conforms to the
standards required by the FDEP physical monitoring plan. APTIM will notify the County of any issues
with the survey data and will coordinate through the County or directly with the surveyors to resolve any
issues.
APTIM will develop an engineering report that discusses the performance of the beach fill project. Beach
contour changes will be evaluated to document changes at the shoreline and the dune. Volumetric
changes will be quantified above MHW (+0.6 ft NAVD) and above the depth of closure. All computations
and distinguished erosion and accretion patterns/trends will be summarized with tables and graphical
representations in addition to plots of the survey profiles.
Deliverable
A Year 1 post -construction monitoring assessment will be provided in report format for the Sector 5
project area. The report will summarize and discuss background information regarding the project, survey
datasets utilized, beach contour and volumetric changes, and overall project performance. The report
appendices will include the raw survey data and superimposed plots of the two most recent beach
profiles, the design template, and pre- and post -construction profiles.
-4A PT I M September 22, 2021
Page 2 of 3
In accordance with the JCP requirements, the report will specifically include the following:
1. A record of the volume and location of all beach fill material placed within the project area
2. The volume and percentage of advance nourishment lost since the last beach nourishment project
as measured landward of the MHW line of the most recent survey
3. The most recent MHW shoreline positions (feet) in comparison to the design profile at each
individual monument location
4. The MHW shoreline position changes (feet) relative to the pre -construction survey at each
individual monument location for all the monitoring periods
5. The total measured remaining volume (cubic yards) in comparison with the total predicted
remaining volume (cubic yards) above the MHW line and above the Depth of Closure for the entire
project area over the successive monitoring periods
6. Any other shoreline position and/or volumetric analysis the Engineer deem useful in assessing,
with quantitative measurements, the performance of the project.
Schedule & Assumptions
APTIM will provide the deliverable within 90 calendar days of receipt of the Sector 5 Beach and Dune
Restoration Project survey data. It is assumed that the survey data provided by the County has been
processed and is considered final.
Cost
The cost to complete this task is a fixed price of $28,068. The scope and fee were developed following
the provisions of the Professional Services Agreement between Indian River County and APTIM, dated
April 3, 2018, to provide engineering and biological support services in support of the Sector 5 Beach
and Dune Restoration Project (RFQ#2018029).
Thank you for the opportunity to serve Indian River County. Please do not hesitate to call if you have any
questions.
Sincerely,
Nicole S. Sharp, P.E.
Coastal Restoration Modeling Program Manager
Aptim Environmental & Infrastructure, LLC
,`APTIM
EXHIBIT A
At
APTIM Sector 5 - 2018029 - Work Order #9
Year 1 Post -Construction Engineering Monitoring Report
Indian River County, FL
Summary of Cost by Task
September 22, 2021
Page 3 of 3
REV 20.1
Task Number Task Name Labor Sub- I rattractors Mobilaation/Trave Totals
Task 1
Year 1 Post -Construction
$ 28,068.00
$
$
$ 28,068.00
Engineering Report
$
Program Manager
Totals =
$ 28,068.00
$
$
$ 28,068.00
Submitted Ely: Nicole Sharp
Submitted To: Indian River County, FL
A2020 - REV 20.1
APTIM Sector 5 - 2018029 - Work Order #9
Year 1 Post -Construction Engineering Monitoring Report
Indian River County. FL
Summary of Labor Hours and Cost
Labor Title
Labor Bill
Rate
Design, Plans, and
Specifications
Task 1
Labor
Hours Cost
Totals
Labor
Hours Cost
Principal Engineer/Sr Pro' Kftr
$ 250.00
$
$
Program Manager
$ 190.00
32
$
6,080.00
32
$ 6,080.001
Sr Coastal E ineer/Pr ' MVr
$ 165.00
$
$
Coastal Engineer NI
$ 150.00
$
$
Coastal Engineer N
$ 125.00
20
$
2,500.00
20
$ 2,500.00
Coastal Engineer 1
$ 105.0092
$
9,660.00
92
$ 9,660.00
Coastal Modeler N
$ 130.00
— —
$
$
Geologist 11
$ 95.00
$
$
Geo st 1
$ 80.00
$
$
Marine Biologist 11
$ 110.00
8
$
880.00
8
$ 880.00
Professional Surveyor & Mapper
$ 160.00
6
$
960.00
6
$ 960.00
Senior CAD Operator
$ 140.00
8
$
1,120.00
8
$ 1.120.00
CAD Operator
$ 105.00
40
$
4,200.00
40
$ 4.200.00
GIS Operator
$ 105.00
20
$
2,100.00
20
$ 2,100.00
Bookkeeper
$ 80.00
$
$
Cleencal
$ 71.00 1
8
$
568.00
8
$ 568.00
Technician
1 $ 60.00
$
$
NbbikzatioNrravel
1$
$
Sub -Contractors
-
$
TOTAL
234
$
28 068.00
234
$ 28 068.00
submnnd By: Nicole Sharp
submmed To: Indian River County, FL