Loading...
HomeMy WebLinkAbout2022-050CHANGE ORDER No. 1 PROJECT: North County Water Treatment Plant Well N7 Formation Water Disposal Measures and Gopher Tortoise Management DATE OF ISSUANCE March 2022 EFFECTIVE DATE March 2022 OWNER Indian River County OWNER's Contract No. Agreement Dated July 13, 2021 Project No. 044572103 CONTRACTOR All Webbs Enterprises, Inc. ENGINEER Kimley-Horn and Associates You are directed to make the following changes in the Contract Documents: Description: Install 800 linear feet of silt fence and pipe ramps for gopher tortoise management; add turbidity controls to formation water disposal to meet 0 NTU above background in G7 canal (in accordance with IRFWCD Discharge permit No. 22-07). Modify configuration to blend discharge with raw water, add settling tanks, add floc logs, furnish dissipation structure in canal (install by owner). Change Order 1 includes an increase in contract price for Well N7 ($92,435) and a net reduction of the total Contract Price for work not performed on Well S1 ($211,465). Reason for change order: Meet discharge permit requirements for IRFWCD and FWC permit requirements for gopher tortoise relocation. Attachments: (List documents supporting change) CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME Original Contract Price Original Contract Times $ 992,100.00 Substantial Completion: 270 (April 9, 2022) Ready for final payment: 300 (May 9, 2022) Days or dates Net changes from previous Change Orders Net change from previous Change Orders $ N/A N/A days Contract Price prior to this Change Order Contract Time prior to this Change Order Substantial Completion: 270 $ 992,100 Ready for final payment: 300 Days or dates Net Increase (decrease) in this Change Order Net Increase in this Change Order $ (211,465) 118 days Contract Price with all approved Change Orders Contract Time with all approved Change Orders Substantial Completion: 388 $ 780,635 Ready for final payment: 418 Days or dates,.••", RECOMME ED: APPR D: ACCEPTED: �� �M!SS%p^✓F 9s �i By: By: Engineer ( uthorize4i Signature) Owner (Authorized Signature)Contractor (Authorized S�griature Jill Grimaldi, Kimley-Horn and Associates Dave Webb, Jr. All Webbs, Inc. ; p� Date: 2/24/2022 Date: April 5 , 2022 Date EJCDC No. C-700 (2002 Edition) PP -"1K'- ED- AS TO FORM Prepared by the Engineers Joint Contract Documents Committeebri1 erdorjp4( U;hd so(i)i(ed G44il!Pr nlrAmerica COUNTY A17ORNEY R C�����f Attest: Jeffrey R. Smit11;'Clerk of Circuit Court and Comptroller Deputy CW* (Ak) All WEBBS February 25, 2022 Jon Friedrichs Principal Hydrogeologist ILA Geosciences, Inc. CELL: (561) 459-9355 Dear Jon, RE: IRC N7 Request for Change Order Discharge Requirements and Tortise Impact Reason The recently issued IRFWCD discharge permit #22-07 and the special conditions in that permit as the reason for the additional costs and time. The Special Conditions for Permit No. 22-07 for temporary discharge of formation water associated with deepening IRCDUS existing production well N7 from the UFA to the APPZ/Lower Floridan Aquifer, into Sublateral G-7 (815' Street) Canal Located in NW '/< of SE % of Section 32-31-39 include: (1) Off-site discharge of formation water associated with proposed well deepening shall not exceed 1,250 PPM total dissolved solids (TDS), and turbidity shall not exceed existing background Nephelometric Turbidity Units (NTU) of receiving wasters within canal system. (2) TDS and turbidity of said off-site discharge water shall be monitored several times daily. If/when above limits of TDS and turbidity are exceeded, Permittee is to notify David E. Gunter, Superintendent of Indian River Farms Water Control District, of remedial action taken to bring operation within permit limits. (3) Permittee shall advise the District (Phone: 772-562-2141) in advance of commencement and upon completion of proposed well deepening operations. The discharge requirements in the permit are extremely high, the system proposed below is an attempt to meet the requirements. Additional work may be required depending on the water quality encountered during deepening and David Gunter's remedial actions. Pricing Description Quantity Units Unit Cost Extended Cost Silt Fence 1 LS $ 4,000.00 $ 4,000.00 Frac Tanks 4 LS $ 5,778.75 $ 23,115.00 Freight Tanks 4 LS $ 2,673.75 $ 10,695.00 Cleanout Tanks 4 LS $ 2,673.75 $ 10,695.00 Settling Tank 1 LS $ 7,935.00 $ 7,935.00 Filter Sand 1 LS $ 5,520.00 $ 5,520.00 Pumps 1 LS $ 13,340.00 $ 13,340.00 Pipe Ramps 50 LS $ 144.90 $ 7,245.00 Box 1 LS $ 4,830.00 $ 4,830.00 Floc Logs 10 LS $ 506.00 $ 5,060.00 subtotal $ 92,435.00 Additional Contract Time: 118 days for tortoise impact and discharge requirements. Please contact me with any questions or concerns Sincerely, David Webb, Jr. Vice President Kimley»>Horn February 24, 2022 Mr. Terry Southard Operations Manager Indian River County, Department of Utility Services 4350 4151 Street Vero Beach, Florida 32960 RE: Wellfield Feasibility Expansion - Change Order No. 1 All Webbs Enterprises Dear Mr. Southard: In July 2021, All Webbs Enterprises, Inc. (AWE) was contracted to assist with a Wellfield Feasibility Expansion Study that included deepening two of the County's existing production wells from the Upper Floridan Aquifer (UFA) to the Avon Park Production Zone (APPZ)/Lower Floridan Aquifer (LFA). The goal of the project was to deepen production wells S1 (south wellfield) and N7 (north wellfield) to obtain representative water quality and production data from the lower aquifer, to facilitate long-term water supply planning efforts. AWE began the process of deepening S1 in October 2021; however, it was quickly discovered that the well was producing high volumes of sand during the drilling process and the well was determined to be unsuitable for further use. Given the condition of the well during drilling activities and the overall age of the well (constructed in 1982), the decision was made to halt the deepening activities and to plug and abandon the well. Well S1 has now been plugged and the County is making arrangements to drill a replacement well (S1 R) under a separate contract. As a result, the work completed to date, through restoration for the abandoned well site, totals $273,900 less than the originally budgeted amount. Plans were made in December 2021 to mobilize to Well N7 to complete the scope of work associated with deepening the well. It was discovered that three gopher tortoise burrows were located within 25 feet of the planned work area limits, and therefore required relocation of the tortoises. The permitting and relocation activities were performed by others under separate authorization; however, AWE agreed to set the silt fence required to exclude the tortoises from returning to the work area. The additional work associated with the silt fence installation is $4,000. In the course of permitting the discharge for the N7 deepening, the Indian River Farms Water Control District indicated that the permit would be contingent upon meeting two strict water quality parameters. Total dissolved solids (TDS) would not be permitted to exceed 1,250 ppm, and turbidity of the discharge would not be permitted to exceed the background turbidity of the receiving canal at the end of pipe (0 NTU above background). Complying with these conditions will require that discharge water be blended with raw water from the surrounding wells (via the raw water main) and require the installation of additional turbidity measures that were not accounted for in the original kimley horn.com 445 24111 Street, Suite 200, Vero Beach, Florida 32960 772 794 4100 Kimley>»Horn Page 2 AWE bid for this project. The summary of additional measures and resulting costs are presented in Table 1. Table 1 - Summary of Additional Services Description Quantity Units Incurred to Date Unit Cost Work Change Directive No. 1 Extended Cost Silt Fence Installation 800 LF $ 5.00 $ 4,000 Frac Tanks 4 LS $ 5,778.75 $ 23,115 Freight Tanks 4 LS $ 2,673.75 $ 10,695 Cleanout Tanks 4 LS $ 2,673.75 $ 10,695 Settling Tank 1 LS $ 7,935.00 $ 7,935 Filter Sand 1 LS $ 5,520.00 $ 5,520 Pumps 1 LS $ 13,340.00 $ 13,340 Pipe Ramps 50 LS $ 144.90 $ 7,245 Box 1 LS $ 4,830.00 $ 4,830 Floc Logs 10 LS $ 506.00 $ 5,060 Total $ 92,435 As noted above, approximately $273,900 of the previously approved budget for S1 was unused and will not be invoiced to the County. Additionally, the $50,000 allowance (see Table 2, Item 2) was only partially used. The remaining $30,000 will not be invoiced to the County, for a total of $303,900 in funds that will not be incurred on S1. Table 1 identifies $92,435 in additional measures required to address the gopher tortoises and discharge limitations. Kimley-Horn recommends increasing the contract value for N7 from $474,800 to $567,235 (a net increase of $92,435) to address the additional permit requirements. Adjusting for the unused balance on the Well S1 work, the total contract value shall also be reduced from $992,100 to $780,635. Table 2 - Summary of Funds Item Description Original Authorization Incurred to Date Unused Balance Work Change Directive No. 1 Updated Total 1 Bonds/Insurance/General Conditions $ 25,000 $ 25,000 $ - $ - $ 25,000 2 Unidentified Conditions Allowance (S1 Drill Bit) $ 50,000 $ 20,000 $ 30,000 $ (30,000) $ 20,000 3 Well S1 Deepening $ 442,300 $ 168,400 $ 273,900 $ (273,900) $ 168,400 4 Well N7 Deepening $ 474,800 $ - $ 474,800 $ 92,435 $ 567,235 Total $ 992,100 $ 213,400 $ 778,700 $ (211,465) $ 780,635 *Full budget for Well N7 is anticipated to be incurred completing original scope of work. Kimley>»Horn Page 3 Change Order No. 1, executed by the contractor and Kimley-Horn, is attached for County approval. AWE is also requesting an additional 118 days to complete the work (beyond the original completion date, due to delays in permitting and coordinating these efforts). Please contact me at (772) 794-4146 or jill.grimaldi(a)kimley-horn.com should you have any questions or require additional information. Sincerely, Jil Grimal , BCES Project Manager cc: Harrison Youngblood, Indian River County Mark Miller, Kimley-Horn and Associates Jon Friedrichs, JLA Geosciences