HomeMy WebLinkAbout2022-050CHANGE ORDER
No. 1
PROJECT: North County Water Treatment Plant Well N7 Formation Water Disposal Measures and
Gopher Tortoise Management
DATE OF ISSUANCE March 2022 EFFECTIVE DATE March 2022
OWNER Indian River County
OWNER's Contract No. Agreement Dated July 13, 2021 Project No. 044572103
CONTRACTOR All Webbs Enterprises, Inc. ENGINEER Kimley-Horn and Associates
You are directed to make the following changes in the Contract Documents:
Description: Install 800 linear feet of silt fence and pipe ramps for gopher tortoise management; add
turbidity controls to formation water disposal to meet 0 NTU above background in G7 canal (in
accordance with IRFWCD Discharge permit No. 22-07). Modify configuration to blend discharge with raw
water, add settling tanks, add floc logs, furnish dissipation structure in canal (install by owner). Change
Order 1 includes an increase in contract price for Well N7 ($92,435) and a net reduction of the total
Contract Price for work not performed on Well S1 ($211,465).
Reason for change order: Meet discharge permit requirements for IRFWCD and FWC permit
requirements for gopher tortoise relocation.
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIME
Original Contract Price
Original Contract Times
$ 992,100.00
Substantial Completion: 270 (April 9, 2022)
Ready for final payment: 300 (May 9, 2022)
Days or dates
Net changes from previous Change Orders
Net change from previous Change Orders
$ N/A
N/A days
Contract Price prior to this Change Order
Contract Time prior to this Change Order
Substantial Completion: 270
$ 992,100
Ready for final payment: 300
Days or dates
Net Increase (decrease) in this Change Order
Net Increase in this Change Order
$ (211,465)
118
days
Contract Price with all approved Change Orders
Contract Time with all approved Change Orders
Substantial Completion: 388
$ 780,635
Ready for final payment: 418
Days or dates,.••",
RECOMME ED: APPR D: ACCEPTED: �� �M!SS%p^✓F
9s �i
By: By:
Engineer ( uthorize4i Signature) Owner (Authorized Signature)Contractor (Authorized S�griature
Jill Grimaldi, Kimley-Horn and Associates Dave Webb, Jr. All Webbs, Inc. ; p�
Date: 2/24/2022 Date: April 5 , 2022 Date
EJCDC No. C-700 (2002 Edition)
PP -"1K'- ED- AS TO FORM
Prepared by the Engineers Joint Contract Documents Committeebri1 erdorjp4( U;hd so(i)i(ed G44il!Pr nlrAmerica
COUNTY A17ORNEY
R C�����f
Attest: Jeffrey R. Smit11;'Clerk of
Circuit Court and Comptroller
Deputy CW*
(Ak)
All WEBBS
February 25, 2022
Jon Friedrichs
Principal Hydrogeologist
ILA Geosciences, Inc.
CELL: (561) 459-9355
Dear Jon,
RE: IRC N7 Request for Change Order Discharge Requirements and Tortise Impact
Reason
The recently issued IRFWCD discharge permit #22-07 and the special conditions in that permit as
the reason for the additional costs and time. The Special Conditions for Permit No. 22-07 for
temporary discharge of formation water associated with deepening IRCDUS existing production
well N7 from the UFA to the APPZ/Lower Floridan Aquifer, into Sublateral G-7 (815' Street) Canal
Located in NW '/< of SE % of Section 32-31-39 include:
(1) Off-site discharge of formation water associated with proposed well deepening shall not
exceed 1,250 PPM total dissolved solids (TDS), and turbidity shall not exceed existing
background Nephelometric Turbidity Units (NTU) of receiving wasters within canal system.
(2) TDS and turbidity of said off-site discharge water shall be monitored several times daily.
If/when above limits of TDS and turbidity are exceeded, Permittee is to notify David E. Gunter,
Superintendent of Indian River Farms Water Control District, of remedial action taken to bring
operation within permit limits.
(3) Permittee shall advise the District (Phone: 772-562-2141) in advance of commencement
and upon completion of proposed well deepening operations.
The discharge requirements in the permit are extremely high, the system proposed below is an
attempt to meet the requirements. Additional work may be required depending on the water
quality encountered during deepening and David Gunter's remedial actions.
Pricing
Description
Quantity
Units
Unit Cost
Extended Cost
Silt Fence
1
LS
$ 4,000.00
$ 4,000.00
Frac Tanks
4
LS
$ 5,778.75
$ 23,115.00
Freight Tanks
4
LS
$ 2,673.75
$ 10,695.00
Cleanout
Tanks
4
LS
$ 2,673.75
$ 10,695.00
Settling Tank
1
LS
$ 7,935.00
$ 7,935.00
Filter Sand
1
LS
$ 5,520.00
$ 5,520.00
Pumps
1
LS
$ 13,340.00
$ 13,340.00
Pipe Ramps
50
LS
$ 144.90
$ 7,245.00
Box
1
LS
$ 4,830.00
$ 4,830.00
Floc Logs
10
LS
$ 506.00
$ 5,060.00
subtotal
$ 92,435.00
Additional Contract Time: 118 days for tortoise impact and discharge requirements.
Please contact me with any questions or concerns
Sincerely,
David Webb, Jr.
Vice President
Kimley»>Horn
February 24, 2022
Mr. Terry Southard
Operations Manager
Indian River County, Department of Utility Services
4350 4151 Street
Vero Beach, Florida 32960
RE: Wellfield Feasibility Expansion - Change Order No. 1
All Webbs Enterprises
Dear Mr. Southard:
In July 2021, All Webbs Enterprises, Inc. (AWE) was contracted to assist with a Wellfield Feasibility
Expansion Study that included deepening two of the County's existing production wells from the
Upper Floridan Aquifer (UFA) to the Avon Park Production Zone (APPZ)/Lower Floridan Aquifer
(LFA). The goal of the project was to deepen production wells S1 (south wellfield) and N7 (north
wellfield) to obtain representative water quality and production data from the lower aquifer, to facilitate
long-term water supply planning efforts.
AWE began the process of deepening S1 in October 2021; however, it was quickly discovered that
the well was producing high volumes of sand during the drilling process and the well was determined
to be unsuitable for further use. Given the condition of the well during drilling activities and the overall
age of the well (constructed in 1982), the decision was made to halt the deepening activities and to
plug and abandon the well. Well S1 has now been plugged and the County is making arrangements
to drill a replacement well (S1 R) under a separate contract. As a result, the work completed to date,
through restoration for the abandoned well site, totals $273,900 less than the originally budgeted
amount.
Plans were made in December 2021 to mobilize to Well N7 to complete the scope of work associated
with deepening the well. It was discovered that three gopher tortoise burrows were located within 25
feet of the planned work area limits, and therefore required relocation of the tortoises. The permitting
and relocation activities were performed by others under separate authorization; however, AWE
agreed to set the silt fence required to exclude the tortoises from returning to the work area. The
additional work associated with the silt fence installation is $4,000.
In the course of permitting the discharge for the N7 deepening, the Indian River Farms Water Control
District indicated that the permit would be contingent upon meeting two strict water quality
parameters. Total dissolved solids (TDS) would not be permitted to exceed 1,250 ppm, and turbidity
of the discharge would not be permitted to exceed the background turbidity of the receiving canal at
the end of pipe (0 NTU above background). Complying with these conditions will require that
discharge water be blended with raw water from the surrounding wells (via the raw water main) and
require the installation of additional turbidity measures that were not accounted for in the original
kimley horn.com 445 24111 Street, Suite 200, Vero Beach, Florida 32960 772 794 4100
Kimley>»Horn
Page 2
AWE bid for this project. The summary of additional measures and resulting costs are presented in
Table 1.
Table 1 - Summary of Additional Services
Description
Quantity
Units
Incurred to
Date
Unit Cost
Work Change
Directive No. 1
Extended Cost
Silt Fence Installation
800
LF
$
5.00
$
4,000
Frac Tanks
4
LS
$
5,778.75
$
23,115
Freight Tanks
4
LS
$
2,673.75
$
10,695
Cleanout Tanks
4
LS
$
2,673.75
$
10,695
Settling Tank
1
LS
$
7,935.00
$
7,935
Filter Sand
1
LS
$
5,520.00
$
5,520
Pumps
1
LS
$
13,340.00
$
13,340
Pipe Ramps
50
LS
$
144.90
$
7,245
Box
1
LS
$
4,830.00
$
4,830
Floc Logs
10
LS
$
506.00
$
5,060
Total
$
92,435
As noted above, approximately $273,900 of the previously approved budget for S1 was unused and
will not be invoiced to the County. Additionally, the $50,000 allowance (see Table 2, Item 2) was only
partially used. The remaining $30,000 will not be invoiced to the County, for a total of $303,900 in
funds that will not be incurred on S1. Table 1 identifies $92,435 in additional measures required to
address the gopher tortoises and discharge limitations.
Kimley-Horn recommends increasing the contract value for N7 from $474,800 to $567,235 (a net
increase of $92,435) to address the additional permit requirements. Adjusting for the unused balance
on the Well S1 work, the total contract value shall also be reduced from $992,100 to $780,635.
Table 2 - Summary of Funds
Item
Description
Original
Authorization
Incurred to
Date
Unused
Balance
Work Change
Directive No. 1
Updated
Total
1
Bonds/Insurance/General
Conditions
$
25,000
$
25,000
$ -
$
-
$
25,000
2
Unidentified Conditions
Allowance (S1 Drill Bit)
$
50,000
$
20,000
$ 30,000
$
(30,000)
$
20,000
3
Well S1 Deepening
$
442,300
$
168,400
$ 273,900
$
(273,900)
$
168,400
4
Well N7 Deepening
$
474,800
$
-
$ 474,800
$
92,435
$
567,235
Total
$
992,100
$
213,400
$ 778,700
$
(211,465)
$
780,635
*Full budget for Well N7 is anticipated to be incurred completing original scope of work.
Kimley>»Horn
Page 3
Change Order No. 1, executed by the contractor and Kimley-Horn, is attached for County approval.
AWE is also requesting an additional 118 days to complete the work (beyond the original completion
date, due to delays in permitting and coordinating these efforts).
Please contact me at (772) 794-4146 or jill.grimaldi(a)kimley-horn.com should you have any questions
or require additional information.
Sincerely,
Jil Grimal , BCES
Project Manager
cc: Harrison Youngblood, Indian River County
Mark Miller, Kimley-Horn and Associates
Jon Friedrichs, JLA Geosciences