HomeMy WebLinkAbout2022-055AMENDMENT NUMBER 2 TO WORK ORDER NUMBER 18
Hallstrom House (FTC No.: 01-055-FF1)
This Amendment 2 to Work Order Number 18 is entered into as of this 15 day of March
2023 pursuant to that certain Continuing Consulting Engineering Services Agreement for Professional Services
entered into as of this 17th day of April, 2018 (collectively referred to as the "Agreement"), by and between
INDIAN RIVER COUNTY, a political subdivision of the State of Florida ("COUNTY") and MBV Engineering,
Inc. ("Consultant").
The COUNTY has selected the Consultant to perform the professional services set forth on
Exhibit A (Scope of Work), attached to this Work Order and made part hereof by this reference. The
professional services will be performed by the Consultant for the fee schedule set forth in Exhibit B
(Fee Schedule), attached to this Work Order and made a part hereof by this reference. Pursuant to
paragraph 1.4 of the Agreement, nothing contained in any Work Order shall conflict with the terms of
the Agreement and the terms of the Agreement shall be deemed to be incorporated in each individual
Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the date first
written above.
CONSULTANT: BOARD OF COUNTY COMMISSIONERS .••••••••••..
. y r, 011 M/S3
MBV Engineering, Inc. OF INDIAN RIVER COUNTY J�:�.• •" •.%,�
By: ,.� �.. By: i
Peter D. O'Bryan, Chairman
Title: Vice President
BCC Approved Date: March 15, 2022 RCOUc1�.`
Attest: Jeffre Smith, Clerk of Court and Comptroller
t
By:
t�eputy Clerk
Approved:
Jason Ef. Br wn, County Administrator
;t
Approved as to form and legal sufficiency:,,----
Dylan
ufficiency:%
Dylan T. Reingold, County Attorney
EXHIBIT A - SCOPE OF WORK
It is our understanding that the COUNTY intends to construct approximately 2,750 LF of 5 -foot -wide
concrete sidewalk along the east side of Old Dixie Highway, for the frontage along the County -owned
parcels 33-40-30-00000-5000-00009.1 and 33-40-31-00000-1000-00003.3. A description of these
services is provided in further detail, below.
TASK 1: SURVEY COORDINATION
The CONSULTANT will coordinate with the Land Surveyor chosen by the COUNTY to perform the
work. Consultant will provide scope of work to the Surveyor and coordinate on receiving the survey in
formats necessary for design and permitting. Land Surveyor will contract directly with the COUNTY.
TASK 2: CIVIL DESIGN AND PERMITTING
The CONSULTANT will prepare 24"x36" design drawings of the required sidewalk and permit them
through the Indian River County's Right -of -Way Use Permit application. This project should be exempt
from SJRWMD permitting. However, if a SIRWMD ERP is determined to be a requirement, a scope for
these services can be provided.
TASK 3: COST ESTIMATE
The CONSULTANT will prepare an Engineer's Opinion of Probable Cost at design completion.
TASK 4: CONSTRUCTION SERVICES
The CONSULTANT will provide the following scope of services during the construction phase:
• Two (2) inspection during subbase construction
• Two (2) inspection during sidewalk formboards
• One (1) final inspection of sidewalk construction
• Two (2) additional inspections, if required
• Review of testing reports and as-builts, provided by others
• Coordination with County Parks Division and Public Works inspection staff
• Coordination with the Contractor
• Certification by E.O.R. to County
DELIVERABLES
The Consultant shall provide the COUNTY with the following:
• Initial (60%) completion:
o One (1) set of drawings in pdf format for COUNTRY review
• Final (100%) completion
o Two (2) sets of plans in 24"x 36" format
o One (1) set of drawings in pdf format
o One (1) Opinion of Probable Cost (OPC) in pdf format
EXHIBIT B - FEE SCHEDULE
The COUNTY agrees to pay and the Consultant agrees to accept for services rendered, pursuant to this
Agreement, fees inclusive of expenses in accordance with the following:
Task
Fee
Task 1: Survey Coordination
$
1,000
Task 2: Civil Design and Permitting
$
11,650
Task 3: Cost Estimates
$
650
Task 4: Construction Services
$
3,000
Work Authorization Total 1
$
16,300
ADDITIONAL SERVICES
When required by the COUNTY or the Contract Documents, where circumstances exist beyond the
Consultant's control, Consultant shall provide or obtain from others, as circumstances required, those
additional services not listed as part of the Work Order, the Consultant shall notify the COUNTY
promptly prior to commencing said Additional Services, and if agreed upon, will be paid for by County
in accordance with the Master Agreement, Professionals and vendor intended to provide additional
services shall first be approved by the COUNTY, in writing, by the COUNTY's Project Manager.
The COUNTY has selected the Consultant to perform the professional services set forth on this Work
Order. The professional services will be performed by the Consultant for the fee schedule set forth in
this Work Order. The Consultant will perform the professional services within the timeframe more
particularly set forth in this Work Order in accordance with the terms and provisions set forth in the
Agreement. Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work Order shall
conflict with the terms of the Agreement and the terms of the Agreement shall be deemed to be
incorporated in each individual Work Order as if fully set forth herein.
20-0240 Hallstrom House-ADD2
$ -
04-SUBCOORD
ADMIN
$90
INSPECTOR TECH ENG
$115 $115 $150
SUB -CONSULTANT COORDINATION
PM
$175
TOTAL
COSTS
Geotechnical Coordination
Coordination/ Meetings
1 1
$
1
Traffic Coordination
$
440.00
Sidewalk Plans
$
-
Environmental Coordination
3
43
$
$
QC by Admin
Survey Coordination
3.3333
$
4
7.3333 $
1,000.00
Landscape Coordination
Forcemain Extension Plans
3
$
$
-
Architectural Coordination
$
-
Watermain Plans
$
-
Misc Sub Coordination
1
$
$
-
425.00
Miscellaneous
$
$
-
MOT Plans
3.3333
-
4
7.3333 $
1,000.00
09-MISC-OFF
MISCELLANEOUS/ OFF-SITE PLANS
$
-
Coordination/ Meetings
1 1
1
1
3
$
440.00
Sidewalk Plans
6
32 8
8
3
43
$
5,405.00
QC by Admin
1
2
$
350.00
1
$
90.00
Forcemain Extension Plans
3
$
500.00
Site Changes
$
-
Watermain Plans
$
-
Final Certifications 1.1111
1
$
-
Off -Site Force Main
425.00
Miscellaneous
$
-
MOT Plans
$
-
Revisions per Agency Comments
8 2
10
$
1,220.00
Progress meetings
30
2 i 2
19.1111
$
4
$
530.00
61
$
7,685.00
1 43 13 4
10 -PERMIT
PERMITTING
Client Coordination
1
1
2
$
265.00
Sub -Consultant Coord
$
Permit Packages
2.7223
2
4.7223
$
595.01
Municipal Coordination
t
1
2
$
265.00
Attend Public Hearing(s)
$
-
Agency Responses
1
4
5
$
790.00
5.7223
8
13.7223
$
1,915.01
11 -PM
PROJECT MANAGEMENT
Client Coordination
3.3333
6
9.3333
$
1,350.00
Municipal Coordination
1
1
$
175.00
Team Meetings
$
-
Opinion of Probable Cost
3.16666
1
4.16666
$
650.00
Schedules
1
1
$
175.00
QC of Plans
2
2
$
350.00
11
SUMMARY
DEVELOPMENT HOURS AND COSTS
ADMIN INSPECTOR TECH ENG PM TOTAL COSTS
Total 13.4 Hr 43.0 Hr 16.2 Hr 27.0 Hr 99.6 Hr $ 13,300.00
AVERAGE HOURLY COST
$134
ADMIN INSPECTOR TECH ENG PM jl TOTAL COSTS
Pre -Construction Meeting
$
-
Shop Drawings
2
1
3
$
475.00
Inspections
6
2
8
$
1,250.00
Site Visit
2
2
$
350.00
Contractor / owner coord
1
2
3
$
500.00
Site Changes
$
-
Final Certifications 1.1111
1
1
3.1111
$
425.00
Miscellaneous
$
-
$
1.1111
30
8
19.1111
$
3,000.00
SUMMARY
DEVELOPMENT HOURS AND COSTS (WITH CONSTRUCTION)
ADMIN INSPECTOR TECH ENG PM TOTAL COSTS
Total 14.5 Hr 43.0 Hr 26.2 Hr 35.0 Hr 118.7 Hr $ 16,300.00
Comparative numbers
Estimated construction cost: (construction costs of discipline)
% design fees (ASCE comp curve) 5.50%
Calculated Design fee $ -
Rev Date: 2020-11-05