HomeMy WebLinkAbout2023-117WORK ORDER 3
West Wabasso Park Improvements
This Work Order Number 3 is entered into as of this 20 day of June , 2023,
pursuant to that certain Continuing Contract Agreement, dated May 2, 2023 (referred to as the
"Agreement"), by and between INDIAN RIVER COUNTY, a political subdivision of the State of Florida
("COUNTY") and MASTELLER & MOLER, INC. ("Consultant").
The COUNTY has selected the Consultant to perform the professional services set forth on
Exhibit A (Scope of Work), attached to this Work Order and made part hereof by this reference. The
professional services will be performed by the Consultant for the mutually agreed upon lump sum or
maximum amount not -to -exceed professional fee. Any additional costs must be approved in writing,
and at a rate not to exceed the prices set forth in Exhibit B (Rate Schedule) of the Agreement, made a
part hereof by this reference. The Consultant will perform the professional services within the
timeframe more particularly set forth in Exhibit A (Time Schedule), attached to this Work Order and
made a part hereof by this reference all in accordance with the terms and provisions set forth in the
Agreement. Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work Order shall
conflict with the terms of the Agreement and the terms of the Agreement shall be deemed to be
incorporated in each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the date first
written above.
CONSULTANT: BOARD OF COUNTY COMMISSIONERS ; yGOb1M1SS/0,�•.
OF INDIAN RIVER COUNTY
By:
By:
Jos . Earman, C firman
Print Name: Sean C. Green, PE
BCC Approval Date: June 20, 2023 '•R��f+�C��N.� "
Title: Executive Vice President
Attest: Jeffrey R. Smith, Clerk of Court and Comptroller
By:
De
pu Clerk a
n A. Tit anich, Jr., County Administrator
Approved as to form and legal sufficiency:
Reingold, County Attorney
M J MASTELLER & MOLER, INC.
M1 — CIVIL ENGINEERS —
EXHIBIT A
1655 27" St
Ste. 2, Vero Beach, FL 32960
(772) 567-5300
The Indian River County Parks and Recreation Division (IRCPRD) plans to modify and improve the existing
crushed shell walking path within and around the West Wabasso Park. Under Work Order 5 of the 2018
Agreement, Masteller & Moler, Inc. (MM) performed conceptual planning and submitted for, and attended,
an IRCCD Pre -Application Conference
This Work Order proposes to provide for the engineering design and preparation of construction plans, site
planning and project permitting, bidding services, and construction administration and observation services
for the West Wabasso Park Improvements.
Scope of Work:
Task A — Surveying Services
Masteller & Moler, Inc. shall use the services of our survey sub -consultant Masteller, Moler, & Taylor, Inc.
to provide a Site Survey for Engineering Utility & Site Design purposes for this project. The proposed
serpentine patterned stabilized walking path internal to the park connecting to the proposed stabilized
looped walking path around the exterior of the park. A proposed stabilized parking area in the south east
quadrant of the park is to be created to better service park users.
Masteller & Moler, Inc. shall locate all specimen hardwoods greater than 4" in caliper and all Cabbage
palms with 10' or greater of clear trunk within the proposed clearing limits.
The Site Survey will include location of all visible improvements within the proposed project limits.
Elevations will be based on NAVD 1988 and cross sections will be obtained on an as -needed basis. Base
Plans will be generated showing the Site Survey information for use in preparing the Engineering Design
Construction Plans.
Task B — Engineering Design & Preparation of Construction Plans
Masteller & Moler, Inc. shall use the aforementioned Base Plans for design and preparation of
Construction Plans for the location and requirements for the new proposed serpentine patterned
stabilized walking path internal to the park connecting to the proposed looped stabilized walking
path around the exterior of the park. A proposed stabilized parking area in the south east
quadrant of the park is intended to be created to better serve park users.
Task C — Minor Site Plan Approval
A Pre -Application Conference with the Technical Review Committee (TRC) was held on February 27th, 2023
to discuss the Project requirements based on a Conceptual Site Plan that was submitted along with the
Conference request. Masteller & Moler, Inc. shall utilize the aforementioned design and construction
plans for submittal to the County Planning Department to secure Minor Site Plan Approval based on
comments provided by TRC Staff at the pre -application conference. The Plans shall include improvements
necessary to facilitate Minor Site Plan Approval generally including but not limited to:
• Location of the proposed stabilized walking path;
Page 1 of 4
M J MASTELLER & MOLER, INC.
165527 1h Stre
, Ste. 2, Vero Beach
FL 32960
M ~ CIVIL ENGINEERS ~ (772) 567-5300
• Location of stormwater management dry retention area;
• Location of the existing Trees.
The permit review fee yet to be determined is excluded from this Work Order. Following the submittal,
we shall complete any required additional rounds of responses following the first round based on hours
expended multiplied by the appropriate job classification rate set forth in Exhibit 1 attached to the
Agreement for a fee not to exceed $2,710.00.
Task D — Soils Engineering Services
Masteller & Moler, Inc. shall use the services of our soils engineering sub -consultant KSM Engineering &
Testing to provide soil engineering services for the project as follows:
• Perform one (1) soil boring to a depth of 20' below grade within the limits of the proposed dry
retention area;
• Perform one (1) "Usual Open Hole" constant head permeability test up to a depth of 5' below
grade within the limits of the proposed dry retention area;
o Obtain (1) soil sample for each strata encountered;
o Perform laboratory testing and engineering calculations to determine the saturated
permeability coefficient "Ksat" value for each sampled stratum;
• Obtain (1) sample for each encountered stratum from a depth range of 6' to 20' below grade;
o Perform laboratory testing and engineering calculations to determine the saturated
permeability coefficient "Ksat" value for each sampled stratum.
o Perform (1) Sieve Analysis (includes Fines Content Test) for each sampled stratum
(includes sampled stratum from the first 5 feet below grade).
o Perform laboratory testing and engineering calculations to determine the Coefficient of
Uniformity "Cu", Coefficient of Curvature "Cc" for each stratum, and, if applicable, the
fineness module for the soil profile.
• Provide a report detailing all findings and conclusions as to the suitability of the subsurface soils
per IRC requirements for the project.
Task E — Supporting Permits
Masteller & Moler, Inc. shall secure the supporting permits for the proposed work from the following
agencies:
• Indian River County Public Works —Type A SWMS Permit (Review fee of $ 850.00)
• SJRWMD 10-2 Self -Certification (Review fee TBD)
• Tree Removal Permit (Review fee of $200.00) (If Required)
• Land Clearing Permit (Review fee of $120.00) (If Required)
Permit application fees are included for reference only and are excluded from this Work Order.
Page 2 of 4
M J MASTELLER & MOLER, INC.
M1 — CIVIL ENGINEERS
Task F — Bidding Services and Specifications
165527 1h Stre
Ste. 2, Vero Beach, FL 32960
(772) 567-5300
Using IRC standard bid documents, Masteller & Moler Inc. shall prepare Contract Plans and Specifications
with Bid Documents to allow the Indian River County Purchasing Department to advertise and bid the
proposed Site Improvements Project. Additionally, we will provide engineering services during the
project's bidding process generally including but not limited to the following:
1. Preparation for and attendance at a mandatory pre-bid meeting and preparation of a letter
of response to include in an addendum.
2. Revise and/or amend Contract Plans and Specifications and prepare written addendum /
addenda during bidding to reflect any comments and/ or requirements by permitting
agencies.
3. Research and responses to bidders' questions to be incorporated into written addenda during
the bidding process.
4. Review submitted bids, evaluate for correctness and completion, compile bid comparison by
line item for each bidder, contact references (if applicable), and provide Letter of Findings and
Recommendation of Contract Award.
Task G — Construction Administration and Observation
Masteller & Moler, Inc. shall provide engineering services as needed during the construction of the project
generally including but not limited to the following:
1. Preparation for and attendance of a mandatory pre -construction meeting;
2. Periodic construction observations as needed;
3. Perform the walkthrough at the end of the construction;
4. Provide a punch list to the Contractor;
5. Review the As -built drawings;
6. Prepare Project Close-out/Certification documents.
Deliverables — The ENGINEER shall provide the COUNTY:
a. 60% Construction Plans and Preliminary Specifications — 1 Hard Copy + PDF
b. Final Construction Plans - 2 Sets + PDF
C. Bid Documents and Final Specifications necessary for Advertisement and Bidding of the work
d. Related digital AutoCAD, DOC, and PDF files
TIME SCHEDULE
Project shall be completed as follows:
Engineering Design & Preparation of Construction Plans (after NTP Receipt) 60 Working Days
Submittal of Permit Applications (after NTP Receipt) 80 Working Days
Page 3 of 4
M
ry
M
MASTELLER & MOLER, INC.
CIVIL ENGINEERS —
FEE SCHEDULE
165527 1h Street, Ste. 2, Vero
FL 32960
(772) 567-5300
The COUNTY agrees to pay, and the ENGINEER agrees to accept a maximum not -to -exceed amount of
$47,120.00 for the above-described services rendered based on the following:
Task A
— Surveying Services
$
7,700.00
Task B
— Engineering Design & Preparation of Construction Plans
$
10,760.00
Task C
— Minor Site Plan Approval*
$
4,160.00
Additional rounds of responses, hourly NTE (if necessary)
$
2,710.00
Task D — Soils Engineering Services
$
2,300.00
Task E —
Permitting*
$
6,700.00
Task F —
Bidding Services and Specifications
$
7,110.00
Task G
— Construction Administration Services
$
5,680.00
Project Total
$
47,120.00
* Permit review fees are excluded from this Work Order.
File#2303
(2303_W W a basso Pa rkl m p_Exh ib itA_23-0525. docx)
Page 4 of 4
ENGINEERING DESIGN, PERMITTING, BIDDING, & CONSTRUCTION SERVICES
West Wabasso Park Improvements
ESTIMATED FEE BREAKDOWN
File # 2303
2303 W03 Fee Breakdown 23-0525.x1sx
Page 1 of 1
Does Not
Include
Survey (MMT) $ 7,700.00
Geotech (KSM) $ 2,300.00
Total $ 47,120.00
Princi al / PE / PSM
Project Manager
CAD Draftsmen
Ins ector
Administrative
Totals
$ 205.00
$ 145.00
$ 115.00
$ 105.00
$ 85.00
Hours
Amount
Hours
Amount
Hours
Amount
Hours
Amount
Hours
Amount
Task B - Design & Construction Plan Services
12
$ 2,460.00
16
$ 2,320.00
52
$ 5,980.00
$
$ -
$ 10,760.00
Task C - Minor Site Plan Approval
4
$ 820.00
16
$ 2,320.00
$ -
$
12
$ 1,020.00
$ 4,160.00
Task C - *Response to Comments*
2
$ 410.00
6
$ 870.00
8
$ 920.00
$ -
6
$ 510.00
$ 2,710.00
Task E - Supporting Permits
10
$ 2,050.00
18
$ 2,610.00
$ -
$
24
$ 2,040.00
$ 6,700.00
Task F - Bidding Services
12
$ 2,460.00
18
$ 2,610.00
$
$ -
24
$ 2,040.00
$ 7,110.00
Task G - Construction Admin. & Obs. Services
4
$ 820.00
8
$ 1,160.00
$ -
32
$ 3,360.00
4
$ 340.00
$ 5,680.00
Total (hrs/cost)
44
$ 9,020.00
82
$ 11,890.00
60
$ 6,900.00
32
$ 3,360.00
70
$ 5,950.00
$ 37,120.00
File # 2303
2303 W03 Fee Breakdown 23-0525.x1sx
Page 1 of 1
Does Not
Include
Survey (MMT) $ 7,700.00
Geotech (KSM) $ 2,300.00
Total $ 47,120.00