HomeMy WebLinkAbout2023-140ASECTION 00942 - Change Order Form
No. 1
DATE OF ISSUANCE: 06/21/2023 EFFECTIVE DATE: 7/11/2023
OWNER: Indian River County
CONTRACTOR Allen Concrete & Masonry, Inc.
Project:MOORHEN MARSH LOW ENERGY AQUATIC PLANT SYSTEM
OWNER's Project No. IRC -2107 OWNER'S Bid No. 2021038
You are directed to make the following changes in the Contract Documents:
Description:
Change Order 1 for Part A of the Contract
Reason for Change Order:
The project is complete. This change order is to make final adjustment to bid line items, to
address plan omissions, and design changes for the construction of the Moorhen Marsh LEAPS
facility. This change order is to finalize Part A of the contract and release retainage to the
Contractor. Part B of the contract, that contains the one-year landscape maintenance and
warranty line items, will remain open as outlined in the bid documents. The following is a list of
plan errors, omissions and design changes for the construction of the Moorhen Marsh LEAPS
facility. This includes the following:
1. Front entrance modification needed as a result of the 53rd street widening (IRC -1505) —
$28,936.22
2. Landscaping pay item discrepancies between the bill of materials and landscaping plans
- $26,654.25
3. Construction of a sediment wall at the headworks structure that was omitted in the
structural plans — $16,015.71
4. Installation of electrical service pull box required at the headworks structure for the 3-
phase service - $6,778.08
5. Removal of a berm on the east side of the side of the property that was constructed after
the project survey was completed - $2,417.94
6. Relocation of electrical conduit for the pole barn due to FPL service work — $1,857.37
Attachments:
Description of Itemized Changes and Backup
CHANGE IN
CONTRACT PRICE:
Time
Description
Amount
Original Contract Price
$$10,987,684.90
Net deeFeaee-of this
$$82,659.57
Change Order:
(days)
Contract Price with all
$$11,070,344.47
approved Change
(days)
Orders:
J I KAt- I UK pignature)
CHANGE IN CONTRACT TIMES
Description
Time
Original Contract Time:
(days)
Final Completion:
300
Net increase this Change Order:
(days)
Final Completion:
317
Contract Time with all approved
(days)
Change Orders:
Final Completion:
617
Richard Reichenbach
Richard B. Szpyrka, P.E.
Public Works Director
Richard B. :aK^,roas=o,�PE.ma„
Szpyrka
2ar,071213�31a.�
IRC -2107 CO#1 20230621 REDUCED
00942-1
F:\Public Works\ENGINEERING DIVISION PROJECTS\2107 Moorhen Marsh LEAPS\1-Admin\Agenda Items\Change Orders\CO1 (PART A)\IRC-2107_CO#1_20230621
REDUCED.doc Rev. 05/01
CHANGE ORDER NO. 1
DESCRIPTION OF ITEMIZED CHANGES
PROJECT NAME: Moorhen Marsh Low Energy Aqatic Plant System (LEAPS)
PROJECT NO. IRC- 2107 BID NO. 2021038
Item No.
Description
Unit
Quantity_Unit
Price
Price Increase
Price Decrease
CO # 1
FRONT ENTRANCE MOD, LANDSCAPING, SEDIMENT WALL,
ELECTRICAL SERVICE PULL BOX, ELECTRICAL CONDUIT
LS
82,659.57
SUBTOTALS
82,659.57
0.00
PROJECT NAME TOTAL
$ 82,659.57
1