HomeMy WebLinkAbout2023-143AF
CHANGE ORDER
No. 1
PROJECT: West Wabasso Septic to Sewer Phase 3
DATE OF ISSUANCE
OWNER Indian River County
OWNER's Contract No. 2022050
EFFECTIVE DATE
Project No. UCP 4155
CONTRACTOR Centerline. Inc. ENGINEER Bowman Consultina Group: Ltd
You are directed to make the following changes in the Contract Documents:
Description: Increase unit quantities as described in the attached OPC.
Reason for change order: Add Phase 3A (61St Drive) to the contract.
Attarhmants• Phaca '�A nPr'
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIME
Original Contract Price
Original Contract Times
$ 1.403.350.48
Substantial Completion: April 22, 2023
Final Payment: June 21; 2023
Days or dates
Net changes from previous Change Orders
Net change from previous Change Orders
No, to No.
No. to No.
$ 0 (zero)
0 (zero) days
Contract Price prior to this Change Order
Contract Time prior to this Change Order
$ 0
Substantial Completion: April 22, 2023
Final Payment: June 21. 2023
Days or dates
Net Increase (decrease) in this Change Order
Net Increase in this Change Order
$1,368,176.77
Substantial: 390 days / Final: 360 days
days
Contract Price with all approved Change Orders
Contract Time with all approved Change Orders
$ 2,771,527.25
Substantial Completion: May 16, 2024
Final Payment: June 15, 2024
Days or dates
ECOMMENDED: APPROVED: ACCEPTED:
By:
Engineer: John M. Boyer, P.E.
Bowman Consulting Grp, Ltd
Date:
By/Dept.
On Lieske
IRof UtiliLZ;
vices
Date: 2
Cont actor: Spencer Weiner
Centerline, Inc.
Date: t> f ; c
EJCDC No. C-700 (2002 Edition)
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America.
OPINION OF PROBABLE COST
Change Order Ni - West Wabasso Septic to Sewer
Phase 3A - 61st Drive
BOWMAN PROJECT No: OlOS14-01-013
June 29, 2023
SUBMITTED TO: Indian River County Department of Utility Services
Vero Beach, Florida 32960
BY: BOWMAN CONSULTING GROUP, .LTD
4450 West Eau Gallie Blvd, Suite 144
Melbourne, Florida 32964
(321) 255.5434 Cert. of Authorization 30462
Item No.
Description
Quantity
Unit
Unit Price
Total Item Cost
1
Construct County Lift Station, Complete and Operable. Furnish
Pumps Package and Dataflow System, Pump package will
include pumps, cables, guide rails and assemblies, float
assembly, anchor bolts and washers and nuts, lifting bails, 55
nipples and elbows, float switches, hatch covers, duplex
control panel, SS base plates and spare parts, concrete
driveway and housekeeping pad The price to include
Dataflow equipment with the spare Telemetry Control Unit
(TCU) Supply spare parts per IRCOUS Construction Standards
Section 10.
1
LS
5355,650,00
$355,650.00
2
Gravity Sewer - B" PVC 6'-8' Cut
712
LF
$83.30
$59,309.60
3
Gravity Sewer -8"PVC 8'-10'Cut
3S5
LF
$92.58
$32,865.90
4
Gravity Sewer - B" PVC 10'-12' Cut
67
LF
$98.72
$6,614.24
5
Sewer Lateral - 6" Single with Clean Out
19
EA
$2,650.00
$50,35000
6
Sewer Lateral - 6" Double with Clean Out
5
EA
$3,650.00
$18,25000
7
Standard Manholes 6'- 8' (4' Dia )
2
EA
$6,668.28
$13,336.56
B
Standard Manholes 6' • 10'(4' Dia,)
1
EA
$11,10215
$11,102.15
9
Standard Manholes 10' • 12' (5' Dia.)
2
EA
$11,146.10
$22,292.20
30
Sanitary Force Main 4" OR 18 PVC
1,260
LF
$58,32
$73,483.20
11
Wastewater MJ Pipe Fittings, Ductile Iron, All Sizes
0.25
Ton
$14,759 77
$3,689.94
12
Gate Valve, 4" dia. w/ Box and Conc, Pad
1
EA
$2,001.08
$2,001.08
13
12N 4" Tapping Sleeve & Gate Valve w/ Box & Conc Pad
i
EA
$9,06566
$9,06566
14
Asphaltic Concrete, Superpave (Traffic C) Per FOOT Spec 334
370
Tons
$464.82
$171,983.40
15
Optional Base Group 6 (8 -inches) -FOOT Spec 285
2,800
SY
$25.48
$71,344.00
16
Type 8 Stabilized Subgrade (12 -inches)- Per FOOT Spec 160
fLBR 40)
2,900
SY
$23.50
$68,150.00
17
5" Double Yellow Per FOOT Spec 711-8
50
LF
$4.08
$204 00
18
24" White Per FOOT Spec 711-8
12
LF
$11.63
$139.56
19
Raised Pavement Markers (RPM'S) - Class B, All Types & Colors
per FOOT Spec 706
10
EA
$5.00
$5000
20
Sign - Object Marker, Type 4 (0M4.3) with Round Aluminum
Post per FOOT Spec. 705
3
EA
$250.00
$750.00
21
Import Fill oer FDOTSoec 120
1,300
CY
S15.00
$19,SDOD0
22
Restoration (Sod)
6,650
SY
$31.21
$207,546.50
23
TestlnR of Gravity Mains (TV & Exfiltration)
1,134
LF
$15.34
$17,395.56
24
Construction stake -Out Survey
1
LS
$10,881.99
$10,881.99
25
As -built Survey
1
LS
$1,360.25
$1,360.25
26
Erosion & Sediment Control
1
LS
$62,409.21
$62,409,21
Sub Total Construction:
$1,289,725.00
27
Mobilization, Demobilization, MOT (See Section 01025)
1
LS
$60,000.00
$6Q000.00
28
Public Construction Bond:
1
L5
$18,451.77
$18,451.77
Estimated Project Total Cost:$1,368,176.77
The opinion of cost, above, is based on West Wabasso Phase 3B contract prices provided by
Centerline Construction. It is true and accurate to the best of my knowledge; however,
actual construction cost may vary. Dlgitally signed by John M.
Boyer
Reason; Engineer's Seal /
Contact Info: �
jboyer@bowman cam
Date: 2023.06,29
16:13:44-04'00'
s\ttr,,.,,,rrrr
�. No- 57970 :�12
3 -0 Z_
� pIV Z
0 STATE OF Ar
FLORtO�:• +
6.
'�
1"01NALtt� ..