HomeMy WebLinkAbout1999-216P
•
August 11, 1999
Mr. Ronald R. Brooks, Manager
Indian River County
Solid Waste Disposal District
1325 74th Avenue SW
Vero Beach, FL 32968
Subject: Proposal - Indian River County SWDD Landfill
Class I Operation Permit and Stormwater Permit Renewal
Dear Mr. Brooks:
(�._:.4-99
yR-art.
Camp Dresser & McKee Inc. (CDM) is pleased to provide this proposal for engineering
services for renewal of the Class I Operations Permit and the Stormwater Permit for the
Landfill.
Our proposal includes the following sections:
Attachment A - Engineering Work Authorization
Attachment B - Scope of Services and Schedule
Attachment C - Project Budget Services by Task
Attachment D Cost Estimate
A task summary of hours by labor category is included in Attachment C. The engineering
fee for these permitting services is $51,492.
If you have any questions or need additional information, please feel free to call me at
(407)660-2552 or Marty Lewis at 231-4301.
Very truly yours,
CAMP DRESSER & McKEE INC.
john G. Ladner, P.E.
JGL:jee/rb
Attachments
APPROVED
E. Lawrence Adams, Jr., P.E., DEE
Vice President
�iININ
Camp Dresser & McKee Inc.
cwwffing
Maitland Center Parkway, Suite 300
eng0601ing
12301
Maitland, Florida 32751
L"'"'G
Tel: 407 660.2552 Fax:407 875-1161
operations
August 11, 1999
Mr. Ronald R. Brooks, Manager
Indian River County
Solid Waste Disposal District
1325 74th Avenue SW
Vero Beach, FL 32968
Subject: Proposal - Indian River County SWDD Landfill
Class I Operation Permit and Stormwater Permit Renewal
Dear Mr. Brooks:
(�._:.4-99
yR-art.
Camp Dresser & McKee Inc. (CDM) is pleased to provide this proposal for engineering
services for renewal of the Class I Operations Permit and the Stormwater Permit for the
Landfill.
Our proposal includes the following sections:
Attachment A - Engineering Work Authorization
Attachment B - Scope of Services and Schedule
Attachment C - Project Budget Services by Task
Attachment D Cost Estimate
A task summary of hours by labor category is included in Attachment C. The engineering
fee for these permitting services is $51,492.
If you have any questions or need additional information, please feel free to call me at
(407)660-2552 or Marty Lewis at 231-4301.
Very truly yours,
CAMP DRESSER & McKEE INC.
john G. Ladner, P.E.
JGL:jee/rb
Attachments
APPROVED
E. Lawrence Adams, Jr., P.E., DEE
Vice President
•
0
CDM Camp Dresser & McKee Inc.
Mr. Ronald R. Brooks
August 11, 1999
Page 2
cc: Donald R. Hubbs, P.E., Director, Indian River County Solid Waste Disposal
District
E. Lawrence Adams Jr., P.E., DEE, CDMNRB
File No.: 0000-ELANB-MT.ELAIC
,eosoe »Fa
C]
ATTACHMENT A
ENGINEERING WORK AUTHORIZATION
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
Date: Work Authorization No. 09 __ For Consulting Services
County No.%&I- b�Camp Dresser & McKee Inc. (Consultant) CDM Project No.
I. PROJECT DESCRIPTION
Consulting Engineering Services as related to permitting services: Renewal of the Landfill Class
I Operation Permit and the Stormwater Permit for the Indian River County Landfill.
II. SCOPE OF SERVICES
Reference is made to Attachment B, the attached Scope of Services, and the "Professional
Engineering Services Master Agreement for Solid Waste."
III. CONSULTING ENGINEER INSURANCE REOUIREMENTS
The following insurance requirements will be provided in accordance with the Master Services
Agreement:
A. Worker's Compensation Insurance in accordance with Florida Statutes.
B. Automotive Liability with a coverage of $1,000,000 for a combined single limit.
C. General Liability with a limit of $2,000,000 for general aggregate coverage.
D. Professional Liability with an aggregate limit of $3,000,000.
UTIF1. 2
A -I
IV. COMPENSATION FOR SERVICES
Engineer Services:
Task 1.0 - Landfill Operation Permit Renewal (Lump Sum) $25,464
Task 2.0 - Landfill Stormwater Permit Renewal (Lump Sum) $13,839
Task 3.0 - FDEP RAI Responses (Lump Sum) $12,189
TOTAL $51,492
Lump Sum Cost Elements
For the basic services performed for each task for a lump sum fee, Indian River County Solid
Waste Disposal District agrees to pay Camp Dresser & McKee Inc. (CDM) partial payments to
be made on a monthly basis in proportion to the percentage of work completed in accordance
with the referenced contract.
SUBMITTED BY: APPROVED BY:
- — CAMP DRESSER & McKEE INC. INDIAN RIVER COUNTY SOLID
(Consultant) WASTE DISPOSAL DISTRICT
E. Lawrence Adams, Jr., P.E., DEE C mmjssionerKenneth R. Macht, Chairman
Vice President Board of Commissioners
UF11 b:
T) I I I I " DATE: August 24, 1999
7� 171
A-2
Je309A.
A-2
Je309A.
40
•
ATTACHMENT B
SCOPE OF SERVICES AND SCHEDULE
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
ENGINEERING SERVICES FOR
RENEWAL OF LANDFILL OPERATION PERMIT AND STORMWATER PERMIT
Project Understanding
The Indian River County Solid Waste Disposal District (SWDD) operates a Class I Landfill and
other solid waste management facilities for Indian River County residents. The Florida Department
of Environmental Protection (FDEP) issues operation permits which must be renewed every 5 years
for the operation of solid waste disposal facilities. The SWDD permit needs to be renewed and
updated for the next 5 years. This FDEP Operations Permit also includes the closure of Segment 1,
the partial closure of Segment 2 and the Waste Tire Processing Operation.
Task 1.0 - PREPARATION OF PERMIT RENEWAL APPLICATION FOR THE LANDFILL
The solid waste renewal application consists of the 41 page Chapter 62-701.900 FAC checklist and
all other supporting information, The major information for the permit application is the updating of
all information since the last permit modification. The applicant must complete Parts A, B, D, E, F,
H, I, K through R, and T of the application. The anticipated effort required for each of the parts is
described in the following paragraphs.
Parts A, B, D, E, and F consist of data forms and general facility information (location of airports,
floodplain, zoning/land use, solid waste projections, airspace volume, etc.). Most of the information
developed for the December 1995 operations permit modification is usable for the permit renewal,
with some revisions for changes in facility operations since January 1996, and for required updates.
Part H of the permit application reflects the results of the hydrogeological investigation for the site.
Much of the hydrogeological information for the site can be taken from the hydrogeological report
submitted with the February 1994 operations permit renewal.
"-1 w*ll i 6iei unuc and summarize the geotechnical investigation performed for the lateral and
vertical expansions of Segment 2 and the Infill.
Part K information is an operations plan which describes in detail the operations, safety, and training
procedures which are used on a daily basis to minimize the risk of environmental degradation. Most
of the operations manual prepared for the Infill operation permit modification will be used for this
renewal submittal.
Part L describes the water quality and leachate monitoring plan for the site. A comprehensive report
describing hydrogeology, the groundwater and surface water monitoring system, and leachate
sampling has been prepared and will be submitted prior to this renewal being submitted. This report
is the Indian River County Landfill Biennial Water Quality Report for the 1997 and 1998 water
quality data.
03W•Wo
August 11, 1999 B—I
40
Parts N, O, and P relate to landfill closures. These parts will be updated as needed for both
Segment 1 and the partial closure already taken place on Segment 2. Information submitted
previously to FDEP will be referenced as much as possible.
Part Q is a requirement to provide financial assurance for closure and for 30 years of long-term
care. A detailed closure cost estimate for the Segment 2/Infill Segment Closure and a sinking
fund financial analysis to determine annual deposits to a landfill closure escrow account, based
on the remaining airspace has been performed and will be included in the submittal. This will
include the most recent detailed cost estimate for operation and maintenance of Segment 1,
Segment 2, and the Infill segment.
The Tire Processing Operation will also be renewed as part of this permit application.
Task 2.0 - FDEP STORMWATER PERMIT RENEWAL
CDM has contacted FDEP regarding the renewal of the stormwater permit. The stormwater
permit was issued to construct and operate a stormwater system at the site and now must be
renewed.
An Environmental Resource Permit (ERP) is now required for stormwater permitting. FDEP
staff has indicated that the conversion of this permit will require submittal of an ERP application.
The ERP application form will be completed, however, some information which has already
been submitted will be referenced in the form and not resubmitted. Some information will have
to be updated with the submittal of this ERP application.
The Environmental Resource Permit (ERP) application form consists of Sections A — F and
attachments 1-6. For the renewal of the current MSSW permit Sections A, C and E will be
completed. Information previously submitted which is still applicable will be referenced to the
submittal in which it was included.
Section A of the ERP is a general information section consisting of 8 parts. Information
regarding the proposed activities, type of permit, ownership, general description of activities and
signature pages are part of this section.
Section C will be completed and information which includes additional nrnnprt%r .4,.,.h c ><.,,1:.._
_ r 'r• J ......... u.auuu
River County has recently acquired will be shown.
Section E requires detailed information regarding any site improvements or stormwater
improvements which affect wetlands or surface waters. Since construction of additional
stormwater facilities was recently completed, some limited information will be supplied
regarding the landfill area and stormwater facilities. A map showing the entire property
boundary of the landfill on a recent aerial will be included as part of the submittal. Aerial
photography will be performed by a subconsultant to CDM to show the existing and additional
property owned by the SWDD at the landfill. The aerial photography will include a rectified
color aerial, an infra -red aerial and a digital file of the aerial photograph.
jeM.wpa
August 11, 1999 D-2
do
s
Task 3.0 - RESPONSES TO FDEP REQUESTS FOR ADDITIONAL INFORMATION
Due to the complexity of the construction process for Class I lined disposal areas, it is
anticipated that FDEP may request additional information regarding the permit renewal. It is
anticipated that each round of responses will require from 45 to 60 days depending on the
number and complexity of FDEP comments. Responses to FDEP comments will be in the form
of letter reports with attached supplemental information.
",rwv.wpa B-3
August 11, 1999
40
i
ATTACHMENT C-1
PROJECT BUDGET
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
ENGINEERING SERVICES FOR RENEWAL OF LANDFILL
OPERATION PERMIT AND STORMWATER PERMIT
TASK/PROJECT: Renewal of Landfill Operation Permit and Stormwater Permit
DESCRIPTION: Task 1.0 - Renewal of Landfill Operation Permit
CONTRACT Agreement between the Indian River County Board of County
REFERENCE: Commissioners and Camp Dresser & McKee Inc.
Labor Cateeory Hours
J Officer/Senior Engineer
8
Associate/Principal (ENEV-7/8)
22
Engineer (ENEV-5/6)
26
Engineer (ENEV 3/4)
116
Drafter
60
Support
60
TOTAL HOURS
292
Direct Salary Cost
$7,270.00
Indirect Salary Cost (0.393)
$2,857.11
TOTAL SALARY COST $10,127.11
SALARY COST TIMES MULTIPLIER (2.35) $23,798.71
OTHER DIRECT COSTS:
Printing, Copies, Communication, Computer $1,665.91
TOTAL ESTIMATED COSTS $25,464.62
For the basic services under this Agreement, the County agrees to pay the Consultant a Lump Sum
fee of $25,464 for Task 1.0 services, partial payments to be made on a monthly basis in accordance
with the referenced contract.
je0309.wpd C— 1
August 11, 1999
40
•
[:
ATTACHMENT C-2
PROJECT BUDGET
l INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
ENGINEERING SERVICES FOR RENEWAL OF LANDFILL
1 OPERATION PERMIT AND STORMWATER PERMIT
TASK/PROJECT: Renewal of Landfill Operation Permit and Stormwater Permit
DESCRIPTION: Task 2.0 - Renewal of Landfill Stormwater Permit
CONTRACT Agreement between the Indian River County Board of County
REFERENCE: Commissioners and Camp Dresser & McKee Inc.
Labor Cateeory Hours $
Officer/Senior Engineer 4
Associate/Principal (ENEV-7/8) 16
Engineer (ENEV-3/4) 64
Drafter (DFGN-4) 24
Support 28
TOTAL HOURS 136
Direct Salary Cost $3,380.00
Indirect Salary Cost (0.393) $1,328.34
TOTAL SALARY COST $4,708.34
SALARY COST TIMES MULTIPLIER (2.35) $11,064.60
OTHER DIRECT COSTS:
Printing, Copies, Communication, Computer $774.52
vvTSIDE, P-mOCESSiGNAL SERVICES
Aerial Photography $2,000.00
TOTAL ESTIMATED COSTS $13,839,12
For the basic services under this Agreement, the County agrees to pay the Consultant a Lump Sum
fee of $13,839 for Task 2.0 services, partial payments to be made on a monthly basis in accordance
with the referenced contract.
je0309.wpa C-2
August 11, 1999
40
bik:; c
ATTACHMENT C-3
PROJECT BUDGET
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL
ENGINEERING SERVICES FOR RENEWAL OF LANDFILL
OPERATION PERMIT AND STORMWATER PERMIT
TASK/PROJECT: Renewal of Landfill Operation Permit and Stormwater Permit
DESCRIPTION: Task 3.0 - FDEP RAI Responses
CONTRACT Agreement between the Indian River County Board of County
REFERENCE: Commissioners and Camp Dresser & McKee Inc.
Labor Cateeory
Hours $
Officer/Senior Engineer
2
Associate/Principal (ENEV-7/8)
16
Engineer (ENEV 5/6)
8
Engineer (ENEV-3/4)
64
Drafter (DFGN-4)
24
Support
24
TOTAL HOURS 138
Direct Salary Cost $3,480.00
Indirect Salary Cost (0.393) $1,367.64
TOTAL SALARY COST $4,847.64
SALARY COST TIMES MULTIPLIER (2.35) $11,391.95
OTHER DIRECT COSTS:
Printing, Copies, Communication, Computer $797.44
TOTAL ESTIMATED COSTS $12,189.39
For the basic services under this Agreement, the County agrees to pay the Consultant a Lump Sum
fee of $12,189 for Task 3.0 services, partial payments to be made on a monthly basis in accordance
with the referenced contract.
;0309.
August 11, 1999
C-3