INDIAN RIVER COUNTY, FLORIDA
CHANGE ORDER NO.3
PROJECT NO. 9723
ACCOUNT NO: 101-156-541-067.75
PROJECT: INTERSECTION IMPROVEMENTS TO OSLO ROAD & 27"' AVENUE
AND FIVE LANE WIDENING OF OSLO ROAD
CONTRACTOR NAME/ADDRESS: DICKERSON FLORIDA, INC.
POST OFFICE BOX 719
STUART, FLORIDA 33495
DATE OF ISSUANCE: SEPTEMBER 10, 1999
ITEM
NO.
DESCRIPTION OF CHANGE
QUANTITY
UNIT
UNIT
PRICE I
PRICE
INCREASE
PRICE
DECREASE
1
Additional asphalt course/Leveling
1,439
TON
$33.89
$48,767.71
2
Adjust Structure S -6A & S-18 plus
Dickerson's 10% mark-up
2
EA
$275.00
$550.00
$55.00
3
Additional Grading around Cason
Pond
l
LS
$3,542.00
$3,542.00
4
Adjustment of Structure due to
utility conflict
1
LS
$900.00
$900.00
5
Pavement Marking Arrows
plus Dickerson's 10% mark-up
36
EA
$40.00
$1,440.00
$144.00
630-1-12
Conduit, underground (loo)
520
LF
$3.38
$1,757.60
635-1-1
Pull Boxes
4
EA
$301.78
$1,207.12
62U-2-102
6' Advanced Loo
a
AS
$592.51
430-11-325
Concrete Pipe Culvert, 18"
37
LF
$39.22
$1,451.14
430-11-329
Concrete Culvert, 24"
2
LF
$59.89
$119.78
430-11-333
-Pipe
Concrete Pipe Culvert, 30"
4
LF
$106.00
$424.00
430-11-340
Concrete Pipe Culvert, 54"
10
LF
$98.58
$985.80
430-141-111
Concrete Pipe Culvert, 43" x 68"
24
LF
$116.07
$2,785.68
430-141-102
Concrete Pipe Culvert 14" x 23"
1 45
LF
$68.90
$3100.50
PAGE 1 OF 3 PAGES
40
i
itered End Section, 18" RCP -CD
1
EA
$779.10
$779.10
I
itered End Section, 24" RCP -CD
I
EA
$816.20
$816.20
Mitered Section, 18" RCP -SD
2
EA
$943.40
$1,986.80
itered End Section, 18" ACCMP-
RTOTAL
4
EA
$954.00
$3,816.00
---
rench Drain A re ate
30
CY
$24.38
$731.41
OTAL INCREASE/DECREASE IN CONTRACT AMOUNT
$69,160.60
$8,569.40
II NFT CHANGE IN CONTRACT AMOUNT
$60,591.20
ORIGINAL CONTRACT PRICE/TIME $1,212,255.30 150 DAYS
CHANGE ORDER NO. 1 $ 2,123.00
CHANGE ORDER NO. 2 $ ( 9,489.00)
CURRENT CONTRACT PRICE/TIME $1,204,889.30 150 DAYS
AS ADJUSTED BY PREVIOUS CHANGE
ORDERS
NET CHANGE IN CONTRACT PRICE/TIME $ 60,591.20 0 DAYS
THIS CHANGE ORDER
NEW CONTRACT PRICE./TIME $1,254,480.50 150 DAYS
INCLUDING THIS CHANGE ORDER
PAGE 2 OF 3 PAGES
E:
•
INDIAN RIVER COUNTY, FLORIDA
CHANGE ORDER NO. 3
PROJECT NO. 9723
APPROVAL
ENGINEERS RECOMMENDATION:
I have examined the above changes. They are necessary to satisfactorily complete the Contract. The
price changes are reasonable and 1 reconinlend ihat the changes be made.
,- "J,0" p-. 9- 5
Eng(p6er Date
CONTRACTORS APPROVAL:
I agree that the above changes in said Contract, in accordance with Specifications for the price
changes shown, are satisfactory.
6h
Con ctor Date
ACCEPTED BY: INDIANAIVER COUNTY, FLORIDA
NNETH R. MRCHT;, CHAIRMA
BOARD OF COUNTY COMMISSIONERS
BCC ADDr'ovpd 1-1—her 2n 1999
October 12, 1999
DATE
9723 ")3-mag.wpd
PAGE 3 OF 3 PAGES