Task 02 — Vero Lake Estates Stormwater Improvements, Phase I
WORK ORDER NO.6 TO THE PROFESSIONAL
CIVIL SERVICES MASTER AGREEMENT
BETWEEN CARTER ASSOCIATES, INC.,
DATED AUGUST 4,1998 AND
INDIAN RIVER COUNTY, FLORIDA
Pursuant to the Professional Services Agreement dated August 4, 1998, by and between Indian River
® County, a political subdivision of the State of Florida, hereinafter referred to as the COUNTY, and CARTER
ASSOCIATES, INC., (C.A.I.) VERO BEACH, FLORIDA, hereinafter referred to as the ENGINEER, this
Work Order No. 6 is an extension of and hereby becomes a part of the MASTER AGREEMENT as follows:
SECTION I - PROJECT LIMITS AND DESCRIPTION
These services will include updating the Vero Lake Estates conceptual master drainage plan
(permitted March '97 — July '98) to include the following additional items in a construction package of plans
and specifications to be provided to the County for use in constructing the work. The additional items include a
conveyance canal and pipe structure improvements to route stormwater runoff to the stormwater lake
(Lake 20). The drainage area served by Lake 20 following the Phase I work will be significantly increased with
the inclusion of these improvements. The work will be installed by a combination of County forces and a
Contractor selected through a bid process.
The work items noted below will be incorporated into one (I) construction package with the Work
Order Number 3 construction work items.
Work Order No. 6 (Task 02, Vero Lake Estates Stonnwater Improvements, Phase I)
Project work items include:
A. 98'h Avenue cross section improvements from 80'" Street to 86a' Street
B. Construct new pipe structures or retrofit existing structures at the 980' Avenue/83'' Street
intersection to route runoff through Lake 20.
SECTION II - COUNTY OBLIGATIONS
The COUNTY agrees to provide the ENGINEER with the following material, data or services as
required in connection with the work to be performed under this Agreement:
A. Currently available drainage studies, survey drawings, plans, calculations and other data
pertinent to the project.
B. 'Title information and title opinion relating to land necessary for the project.
C. Landowner authorizations to inspect and enter onto the site(s).
D. Landowner negotiations to acquire permission, easements and/or right-of-way necessary for the
project.
E. Provide coordination with the Planning Department to determine any project construction
requirements including tb: length of time that may be allowed for the excavation section of the
project. This project is exempted from the normal site plan review process due to its public
works status.
F. Stockpile location for lake excavation material.
1:\CYN\ENGPROJ\IRCStonnwtrMgnttlmprove\VeroLi:Eslales\IRC-WRKORDERNO6-TASK2.doc Page Iof4
SECTION III - SCOPE OF SERVICES
A. The ENGINEER will perform all necessary engineering design for construction plans and
specifications as described in Section I. No additional permits are required. Detailed Plans,
Specifications and Estimated Bid Quantities shall be prepared so that the work itemized in
Section I (B) above can be properly bid by the County. The work to be performed by County
® forces (Section I A), above will be constructed using the typical cross sections, as noted on the
permit plans.
• B. After issuance of a work order and written authorization to proceed, the ENGINEER shall
consult with the COUNTY to confirm the COUNTY'S requirements and objective for the
project, and review all available data.
C. The ENGINEER will strive to complete his work on the PROJECT within the time allowed by
maintaining an adequate staff of registered engineers, biologists, draftsmen, and other
employees on the work at all times.
D. The ENGINEER shall report the status of this project to the Director of Public Works
Department upon request and hold all drawings, calculations and revised work open to the
inspection of the Director or his authorized agent at any time, upon reasonable request.
E. TASK 02 — PROJECT DEFINITION (Vero Lake Estates Stormwater Improvements Phase 1)
The ENGINEER will perform and provide topographic and land surveying information
required of all areas of work. Detail of existing structures such as mail boxes, above and below
ground utilities, driveways, trees, etc. shall be provided. The ENGINEER will coordinate with
the COUNTY to assure access to the property after the limits of the project have been
established.
The ENGINEER will have the following required meetings with the County staff.
Program meeting to outline survey work and scope as defined.
30% drawings
60% drawings and specifications
90% construction plans and specifications
County will supply their STANDARD BID documents.
The Engineer will review the project with SJRWMD staff for their comments and
approval.
A. Prepare Base Sheet
• Perforin and assemble survey data for use in construction plans.
B. Engineering final design and specifications
• Prepare plans and specifications for structures, piping, and excavation.
Specifications shall include summary of estimated quantities.
C. One (1) additional review meeting of design and specifications with County staff.
D. Reimbursables - mileage, postage, printing, telephone
SECTION IV - TIME FOR COMPLETION
A. All survey and design work will occur between October 1, 1999 and July 1, 2000 in accordance
with the FDEP Grant requirements. CAI will deliver the plans, specifications and summary of
quantities to the County for bidding purposes on or before May 1, 2000 so that bids may be
received and actual construction started on July 1, 2000.
SECTION V - COMPENSATION
The COUNTY agrees to pay, and the ENGINEER agrees to accept fee for services rendered according
to the Scope of Services, Task 02, identified in Section III of this work order with a maximum charge under this
work order of $ 6,955.00. This fee is itemized as follows:
1:1CYN\ENGPROJ\IRCSIonnwlrMgnttlmprovc\VeroUEslmesllRC-WRKORDERNO6-TASK2.doc Page 2of4
SECTION VII - PARTIAL PAYMENTS
The COUNTY shall make monthly partial payments to the ENGINEER for all authorized work
pertaining directly to this project performed during the previous calendar month. Invoices will be submitted on
forms furnished for that purpose by the ENGINEER to the COUNTY monthly for services performed and
expenses incurred pursuant to this Agreement during the prior month.
The ENGINEER shall submit duly certified invoices in duplicate to the Director of the Publin Works
Department. The amount of the invoices submitted shall be the prorated amount due for all work performed to
date under this phase, determined by applying the percentage of the work completed its certified by the
ENGINEER to the total due for this phase of the work.
l:\CYN\ENGPROAIRCStomtwtrMgmttmprove\VeroLkEstates\IRC-W RK ORDER NO 6 - TASK 2.doc Page 3 of 4
A. Boundary and Topographic Survey
$ 3,750
B. Engineering - Final Design, Plans, Specifications,
$ 2,850
Summary of Quantities including Fill
Calculations
C. Review Meetings with County - 1 Required
$ 255
•
F. Reimhursables
100 (Estimated)
Total
$ 6,955
SECTION VI - ADDITIONAL WORK
In the event changes are requested by the COUNTY or extra work is imposed to the COUNTY by the
demands of certain regulatory agencies after the approval by the COUNTY of this AGREEMENT, and upon the
issuance of a subsequent work order by the Director of Public Works
Department, said extra work may
commence in accordance with the following fee schedule:
ENGINEER I ............................................................
$ 115.00/hr
ENGINEER II ...........................................................
$ 85.00/hr
ENGINEER III .........................................................
$ 60.00/hr
ENGINEERTECHNICIAN..........................................
$ 50.00/hr
SURVEYOR I (Principal) ............................................
$ 115.00/hr
SURVEYOR II (Registered) ..........................................
$ 65.00/hr
SURVEYOR III .........................................................
$ 55.00/hr
SURVEY CREW (3 -MAN) ...........................................
$ 90.00/hr
CAD TECHNICIAN ..................................................
$ 50.00/hr
DRAFTING..............................................................
$ 45.00/hr
SECRETARY/WORD PROCESSOR ..............................
$ 30.00/hr
RESIDENT PROJECT REP ...........................................
$ 35.00/hr
GRAPHICS ASSISTANT .............................................
$ 25.00/hr
RECORDING AND PERMIT FEES ................................
Cost + 10%
MATERIALS............................................................
Cost + 10%
TRAVEL.................................................................
$ 0.29/Mile or Cost
SUB -CONSULTANTS ................................................
Cost + 10%
REIMBURSABLE EXPENSES:
Postage, Long Distance Calls
Federal express, mail, etc ....................................
Cost + 10%
Blueprints......................................................
$ 0.20/sf
Mylars..........................................................
$ 1.75/sf
Pltotocopy......................................................
$ .15
SECTION VII - PARTIAL PAYMENTS
The COUNTY shall make monthly partial payments to the ENGINEER for all authorized work
pertaining directly to this project performed during the previous calendar month. Invoices will be submitted on
forms furnished for that purpose by the ENGINEER to the COUNTY monthly for services performed and
expenses incurred pursuant to this Agreement during the prior month.
The ENGINEER shall submit duly certified invoices in duplicate to the Director of the Publin Works
Department. The amount of the invoices submitted shall be the prorated amount due for all work performed to
date under this phase, determined by applying the percentage of the work completed its certified by the
ENGINEER to the total due for this phase of the work.
l:\CYN\ENGPROAIRCStomtwtrMgmttmprove\VeroLkEstates\IRC-W RK ORDER NO 6 - TASK 2.doc Page 3 of 4
40
•
•
The amount of the partial payment due for the work performed to date under these phases shall be an
amount calculated in accordance with the percentage of work complete, less ten percent (10%) of the amount
thus determined which shall be withheld by the COUNTY, as retainage, and less previous payments.
The ten percent (10%n) retainage withheld with respect to the Task I phase shall be paid in full to the
ENGINEER upon completion of the items.
Fees are payable monthly based upon a percent complete of the lump sum elements. Billings will be
payable within 25 days. The contract is broken into deliverable units. No payment shall be made unless the
Public Works Director has received and approved work products required under the Scope of Services.
SECTION VIII - RELATIONSHIP TO MASTER AGREEMENT AND LAWS OF FLORIDA
All conditions set forth in the MASTER AGREEMENT shall control unless otherwise specified in this
WORK ORDER.
This WORK ORDER, regardless of where executed, shall be governed by and construed according to
the laws of the State of Florida.
IN WITNESS WHEREOF the parties hereto have executed these presents this 18th day of
April , 2000.
CARTER ASSOCIATES, INC.
1708 21" STREET
VERO ACH, OR DA 32960
BY: tCa.� U; _
Deanhje, 're e
t e r t
Attest.- wt�
INDIAN RIVER COUNTY, FLORIDA
BOARD OF COUNTY COMMISSIONERS
n
�-Fran B. Adams,,,Chai
Attest✓�ih tt�.r .4-41
PA'i MCIA W RIDGECy CERK
I Indian River Countyl Approved' Date I
Administration I Ite0h 11 1,7A
Legal
Public Works ' U
=n�,,j�cii•+� C 'j-3 -off
1:\CYN\ENGPROJ\IRCStormwtrMgmthnprove\VeroUEstates\IRC-W RK ORDER NO 6 - TASK 2.doe Page 4 of 4
•
•
L�]
EXHIBIT A
ITEMIZED MAN-HOUR ESTIMATE
TASK 2, VERO LAKE ESTATES
STORMWATER IMPROVEMENTS, PHASE 1
WORK ORDER NO.6
INDIAN RIVER COUNTY PROJECT NO. 9219
March 22, 2000
A. Topographic Survey of Project Area (98h Avenue)
Surveyor II
10 hrs. x $ 65
= $ 650.00
Crew (3 -man)
20 hrs. x $ 90
= $ 1,800.00
Cad Tech
26 hrs x $ 50
= ".300.
$ 3,750.00
B. Prepare Construction Plans,
Specifications and Summary of Quantities
Engineer I
2 hrs. x $115
= $ 230.00
Engineer lI
16 hrs. x $ 85
= $ 1,360.00
Engineer III
8 hrs. x $ 60
= $ 480.00
Cad Technician
12 hrs. x $ 50
= $ 600.00
Word Processor
6 hrs. x $ 30
= 180.00
$ 2,850.00
C. Review Meetings with County (I Meeting)
Engineer II 3 hrs. x $ 85 = $ 255.00
$ 2,910.00
D. Reimbursables not to exceed = $ 100.00
TOTAL $ 6,955.00