HomeMy WebLinkAbout2024-094ACHANGE ORDER
PROJECT: South Oslo Road WTP Improvements No. 4
DATE OF ISSUANCE: March 26, 2024 EFFECTIVE DATE:
OWNER: Indian River County
OWNER's Contract No.: 2021026 Project No.: 044572102
CONTRACTOR: TLC Diversified, Inc ENGINEER: Kimley-Horn & Associates, Inc.
You are directed to make the following changes in the Contract Documents:
1. Deductive change order of line item 345 in the schedule of values to IRCDUS. This credit is
provided to cover costs associated with schedule delay shown in TLC latest schedule.
Deductive change order includes time extension request of additional 77 days to final
completion.
Attachments: Updated vroiect schedule. Contractor request for time extension letter
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIME
Original Contract Price
Original Contract Times:
$ 10,665,515.65
Substantial Completion: 760
Ready for final payment: 820
Net changes from previous Change Orders
Net change from previous Work Directives:
No. 1, 2, 3 $1,020,621.72
No. 1 to No. 2 197
Contract Price prior to this Change Order
Contract Time prior to this Change Order
$ 11,686,137.37
Substantial Completion: 954
Ready for final payment: 1017
Days or dates
Net Increase (decrease) in this Change Order
Net Increase in this Change Order
$ ( 54,928.65)
77 days
Contract Price with all approved Change
Contract Time with all approved Change
Orders
Orders
$ 11,631,208.72
Substantial Completion: 1,046 (6/15/2024)
Ready for final payment: 1,094 (8/2/2024)
Davs or d`516s
REC MMENDED:
&M AACte
By: iy mY -Wpt,✓
Engineer (Authorized Signature)
Date: 3 2-L _Zo ZI
APPROVED: ACCEPTED
Harrison
B'gounohloY�d p «�""u By: TLC Div. PM
Owner (Authorized Signature) Contractor (Authorized Signature)
Date:
Date: 27 -March -2024
EJCDC No. C-700 (2002 Edition)