HomeMy WebLinkAbout2024-210SECTION 00942 — Change Order Form
DATE OF ISSUANCE: September 10, 2024
No. 1
EFFECTIVE DATE: September 10, 2024
OWNER: Indian River County
CONTRACTOR Close Construction
Project: RENOVATION OF THE JONES' PIER CONSERVATION AREA BUNGALOW
OWNER'S Bid No. 2024009
You are directed to make the following changes in the Contract Documents:
Description:
Addition of 23 days to contract time and formally incorporate work change directives 1, 2, and 3
Reason for ChanRe Order:
Prepare for final completion
Attachments: (List documents supporting change)
Work change directives 1, 2 and 3.
CHANGE IN CONTRACT PRICE:
Description
Amount
Original Contract Price
$
Net Increase (Decrease) from
$
previous Change Orders No.
180
to
Contract Price prior to this Change
$
Order:
0
Net increase (decrease) of this
$
Change Order:
Contract Price with all approved
$
Change Orders:
150
ACCEPTED:
By: iieyna� yy (�az
CONTRACTOR ( ignature)
Date: 8/27/2024
CHANGE IN CONTRACT TIMES
Description
Time
Original Contract Time:
(days or dates)
Substantial Completion:
150
Final Completion:
180
Net change from previous Change
Orders No. to
(days)
Substantial Completion:
0
Final Completion:
0
Contract Time prior to this Change
Order:
(days or dates)
Substantial Completion:
150
Final Completion:
180
Net increase (decrease) this Change
Order:
(days or dates)
Substantial Completion:
23
Final Completion:
23
Contract Time with all approved
Change Orders:
(days or dates)
Substantial Completion:
173 9/10/2024
Final Completion:
1 203 10/1 w S ",,J
RECOMMENDED:
By: 44ff " �,-rmaclia
ARCHITECT (Signature)
Date: 10/22/2024
r.�
APP
By:
0 NER( gnature)-` ' u
.OigT%R • E�R(C� c;
Date: 09/10/2024
APPROVED AS TO FORM Attest: Ryan L. Butler, Clerk of
AND L 4GALSUFFICIENCY Change Order Form — 00942
��_dl/ Circuit Court and Comptroller
BYlos ons c - re 4 - ones' Pier Bungalow\Change Order Requests\JP_Bunga w Renovation_DIV 0 4FormsTemplate_20220330.docx
J NHULER By:�1L!�_�3j
UNTY ATTORNEY Clerk