Loading...
HomeMy WebLinkAbout2025-059CHANGE ORDER No. 1 PROJECT: South Oslo WTP Well S-1 Replacement (S-1 R) DATE OF ISSUANCE: 2/20/2025 EFFECTIVE DATE: OWNER: Indian River County OWNER's Contract No.: 2024024 Project No.: 044572106 CONTRACTOR: Florida Design Drilling Corp. ENGINEER: Kimley-Horn & Associates, Inc. You are directed to make the following changes in the Contract Documents: Description: Drilling and construction is complete on the above referenced project. This change order serves to deduct the remaining unused $314,175 from the contract value. Reason for change order: Project closeout. Attachments: Final Pavment Application CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME Original Contract Price Original Contract Times: $ 1,931,250 Substantial Completion: 0 Ready for final payment: 0 Net changes from previous Change Orders Net change from previous Change Orders: No. to No. No. to No. Contract Price prior to this Change Order Contract Time prior to this Change Order $ 1,931,250 Substantial Completion: 300 Ready for final payment: 330 Das or dates Net Increase (decrease) in this Change Order Net Increase in this Change Order $ (314,175) 0 days Contract Price with all approved Change Contract Time with all approved Change Orders Orders $ 1,617,075 Substantial Completion: 300 Ready for final payment: 330 Days or a es RECO END D: By: � ngineer (Authorized Signatufe) ," &AC"A, A.E. APPROVED: By: Owner (Authorized Signature) ACCEPTED: Contractor (Authorized Signature) Date: Z- ZO -2 �5' Date: Date: 2/20/2025 Brandon K. Holst, Vice President EJCDC No. C-700 (2002 Edition) Florida Design Drilling LLC Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America. 00800-24