HomeMy WebLinkAbout2025-059CHANGE ORDER
No. 1
PROJECT: South Oslo WTP Well S-1 Replacement (S-1 R)
DATE OF ISSUANCE: 2/20/2025 EFFECTIVE DATE:
OWNER: Indian River County
OWNER's Contract No.: 2024024 Project No.: 044572106
CONTRACTOR: Florida Design Drilling Corp. ENGINEER: Kimley-Horn & Associates, Inc.
You are directed to make the following changes in the Contract Documents:
Description: Drilling and construction is complete on the above referenced project. This change order serves to
deduct the remaining unused $314,175 from the contract value.
Reason for change order: Project closeout.
Attachments: Final Pavment Application
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIME
Original Contract Price
Original Contract Times:
$ 1,931,250
Substantial Completion: 0
Ready for final payment: 0
Net changes from previous Change Orders
Net change from previous Change Orders:
No. to No.
No. to No.
Contract Price prior to this Change Order
Contract Time prior to this Change Order
$ 1,931,250
Substantial Completion: 300
Ready for final payment: 330
Das or dates
Net Increase (decrease) in this Change Order
Net Increase in this Change Order
$ (314,175)
0 days
Contract Price with all approved Change
Contract Time with all approved Change
Orders
Orders
$ 1,617,075
Substantial Completion: 300
Ready for final payment: 330
Days or a es
RECO END D:
By:
�
ngineer (Authorized Signatufe)
," &AC"A, A.E.
APPROVED:
By:
Owner (Authorized Signature)
ACCEPTED:
Contractor (Authorized Signature)
Date: Z- ZO -2 �5' Date: Date: 2/20/2025
Brandon K. Holst, Vice President
EJCDC No. C-700 (2002 Edition) Florida Design Drilling LLC