Aviation Boulevard Extension Alternative Alignment Study
ENGINEERING SERVICES WORK ORDER 19
This Work Order Number 19 is entered into as of this8th day of April , 2025 ,
pursuant to that certain Continuing Contract Agreement, dated May 2, 2023, ("Agreement"), by and
between INDIAN RIVER COUNTY, a political subdivision of the State of Florida ("COUNTY") and
Kimley-Horn & Associates, Inc. ("Consultant").
The COUNTY has selected the Consultant to perform the professional services set forth on
Exhibit A (Scope of Work), attached to this Work Order and made part hereof by this reference. The
professional services will be performed by the Consultant for the mutually agreed upon lump sum or
maximum amount not -to -exceed professional fee. Any additional costs must be approved in writing,
and at a rate not to exceed the prices set forth in Exhibit B of the Agreement (Rate Schedule) for RFQ
2023015, made a part hereof by this reference. The Consultant will perform the professional services
within the timeframe more particularly set forth in Exhibit A (Time Schedule), attached to this Work
Order and made a part hereof by this reference all in accordance with the terms and provisions set
forth in the Agreement. Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work
Order shall conflict with the terms of the Agreement and the terms of the Agreement shall be deemed
to be incorporated in each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the date first
�, •Cp�,IMtS3%p '•a
;OCIATES, INC. BOARD OF COUNTY COMMISSON#�AF 9s°;
INDIAN RIVER COUNTY:
By.
seph E. flescher, Chairman q .. Cj'
vRi`-...VER COIN
BCC App oval Date: April 8, 2025 •.•r
By:
ohn A. Titkanich, Jr., County Administrator
Approved as to Form and Legal Sufficiency:
By:
nnifer I. Shuler, County Attorney
Ryan L. Butler, Clerk of Court and Comptroller
Attest: ��YYI.Q/JJ
Deput Jerk
(SEAL)
Aviation Boulevard Extension
Alternative Alignment Study —
EXHIBIT A — SCOPE OF WORK
The COUNTY desires to revise the Aviation Boulevard Extension Alternative Alignment
Study to incorporate the following changes:
• Incorporate the SR S/ US 1 at Aviation Boulevard PD&E Study alignment between US
1 and 33rd Street. This will now serve as the western alignment terminus associated
with the Aviation Boulevard Extension.
• Incorporate the 13th Avenue re -alignment connecting into the proposed Aviation
Boulevard Extension, as negotiated with the City of Vero Beach
All eight (8) contemplated alignments will be updated based upon incorporating the changes
identified above. The Alternative Alignment Study will consider five (S) key factors:
• long-range planning
• public safety
• environmental impacts
• alternative alignments
• cost
The alternative alignments considered will be those that maximize the utilization of existing
roadway right-of-way, minimized impacts to the environment and resulted in minimized
impacts to private property.
A. Alignment Study:
The Alignment Study prepared to support evaluating the Aviation Boulevard Extension
between 33rd Street and 36th Street, approximately 2,400 linear feet to document the
alternative alignments developed and evaluation performed to identify a preferred
alignment which addresses the project needs. The scope of improvements will consist of
identifying alternative alignments and evaluating their unique characteristics between the
limits identified above to meet current County roadway standards relative to lane width, 7 -
foot bike lane facilities, drainage requirements and Florida Department of Transportation
Manual of Uniform Minimum Standards for Design, Construction and Maintenance for
Street and Highways.
The Alignment Study shall summarize the project need, discuss the corridors evaluated, and
provide a recommendation for the preferred corridor.
ALTERNATIVEALIGNMENT EVALUATION
The Consultant will identify up to three (3) alternative alignments to assist in identifying
a Preferred Corridor. The corridor(s) will be studied to assist in identifying a preferred
alternative to serve the identified purpose and community needs. The corridor(s) will
be examined for increase mobility, safety improvements and operational benefits.
Page 2 of 5
Aviation Boulevard Extension
Alternative Alignment Study —
COST EVALUATION
The Consultant will evaluate cost factors, based upon current market conditions, that
will be associated with each alternative corridor evaluated. These cost factors will
consist of the following:
• Construction
• Right -of -Way Acquisition
• Environmental Impact Mitigation
• Franchise Utility Relocations
Page 3 of 5
Aviation Boulevard Extension
Alternative Alignment Study—
EXHIBIT B — FEE SCHEDULE
The COUNTY agrees to pay and the Consultant agrees to accept for services rendered
pursuant to this Agreement fees inclusive of expenses in accordance with the following:
A. Professional Services Fee
The basic compensation mutually agreed upon by the Consultant and the
COUNTY is as follows:
Lump Sum Components
Task
Alignment Study Amendment
(THE REMAINDER OF THIS PAGE IS INTENTIONALLY BLANK)
Page 4 of 5
Labor Fee
$ 46,720
Aviation Boulevard Extension
Alternative Alignment Study—
EXHIBIT C — TIME SCHEDULE
Upon authorization to proceed by the COUNTY, final design documents are expected
to take approximately four (4) months from the Notice to Proceed (NTP).
contingent upon approval
Alignment Study Amendment 4 months following NTP
(THE REMAINDER OF THIS PAGE IS INTENTIONALLY BLANK)
Page 5 of 5
Summary
Project Name Aviation Blvd Extension Alternative Alignment Study - 33rd Street to 35th Lane Manhours for project
Task Summary completion
Task
Principle
Senior
Registered
Professional
Designer
Support Remarks
Professional
Professional
1
Staff
$300
$270
$210
$130
$165
$75
Alternative Alignment Study 1
201
461
401
401
801
20
Total Hours =
20
46
40
40
80
20
Labor Fee =
$6,000
$12,420
$8,400
$5,200
$13,200
$1,500
Sub -Total Fee =
$46,720
Corridor Survey Fee =
$0
Cultural Resource Assessment Study =
$0
Geotechnical Fee =
$0
Total Labor Fee =
$46,720
Aviation Blvd Ext. Scale Report - Amendmet No 2 Workplan.xls Page 1
Activity: Alternative Alignment Study
Task
Principle
Senior
Professional
Registered
Professional
Professional
1
Designer
Support Remarks
Staff
Comparative Analysis and Evaluation
Alternative Alignments
8
20
20
40
4 3 alignments
Safety Considerations
Long Range Planning
Environmental Impacts
4
8
8
8
Costs
2
12
12
40
3 alignments
Public Involvement Meeting
BOCC Presentation
12
24
8
QC/QA
8
Project Management
8
Subtotal
20
46
40
40
80
20