HomeMy WebLinkAbout2025-116AWORK ORDER 8
This Work Order Number 8 is entered into as of this 20 day of May 2025
pursuant to that certain Continuing Contract Agreement, dated May 2, 2023 (referred to as the
"Agreement"), by and between INDIAN RIVER COUNTY, a political subdivision of the State of Florida
("COUNTY") and Geosyntec Consultants, Inc. ("Consultant").
The COUNTY has selected the Consultant to perform the professional services set forth on
Exhibit A (Scope of Work), attached to this Work Order and made part hereof by this reference. The
professional services will be performed by the Consultant for the mutually agreed upon lump sum or
maximum amount not -to -exceed professional fee. Any additional costs must be approved in writing,
and at a rate not to exceed the prices set forth in Exhibit B (Rate Schedule) of the Agreement, made a
part hereof by this reference. The Consultant will perform the professional services within the
timeframe more particularly set forth in Exhibit A (Time Schedule), attached to this Work Order and
made a part hereof by this reference all in accordance with the terms and provisions set forth in the
Agreement. Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work Order shall
conflict with the terms of the Agreement and the terms of the Agreement shall be deemed to be
incorporated in each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the date first
written above.
CONSULTANT:
BOARD OF
COMMISSIONERS
OF RIVER +."�>�yGp�`M!SS/off✓F'9s
IVER
.
By:
By•:
VO seph E. Flescher, Chairman
'o¢�
Print Name: Todd Kafk
'o�NAiVEFiCo�N�•
BCC Approval Date: May 20, 2025
Title: Vice President
Attest: Ryan L. Butler, Clerk of Court and Comptroller
By: �1N
Dep ty Clerk
By: Q C;
+--T§h'�. Titkanich, Jr., County Administrator
Approved as to form and legal sufficiency:
County Attorney
EXHIBIT A
PROFESSIONAL SERVICES
777 Yamato Road
Geosyntec °
Suite
Boca Raton, 33431 FL 33431
PH 561-995-0900
consult311ts www.geosyntec.com
8 May 2025
Mr. Himanshu Mehta, P.E., Managing Director
Solid Waste Disposal District
Indian River County
132574 th Avenue SW
Vero Beach, Florida 32968
Subject: Proposal for Engineering Services
Preparation of the Title V Air Operation Permit Including Visible Emission
Testing
Indian River County Landfill Facility
Vero Beach, Indian River County, Florida
Dear Mr. Mehta:
Per your request, Geosyntec Consultants, Inc. (Geosyntec) is pleased to submit this proposal to
Indian River County (IRC), Solid Waste Disposal District (SWDD) to provide engineering
services related to revision to the Title V Air Operation Permit for the IRC Landfill (IRCL)
facility. Air Construction Permit No. 0610015 -011 -AC was issued on 31 October 2024 for the
construction of a 3,000 SCFM Landfill Gas Utility Flare (EU 009). Per Section 2, Condition #9
of the permit, IRCL must apply for a Title V Air Operation Permit no later than 180 days of the
initial operation of the Landfill Gas Utility Flare; therefore, pursuant to the requirements of
Chapter 403 of the Florida Statue (F.S.), Chapters 62-4, 62-210 and 62-213 of the Florida
Administrative Code (F.A.C.), the operation of the Landfill Gas Utility Flare has to be added to
the Title V Air Operation Permit for the Class I Landfill. The permit also requires that SWDD
conduct an initial visible emissions compliance test within 60 days after achieving the permitted
capacity, but not later than 180 days after initial operation of the unit.
The current 5 -year permit (Permit No. 0610015 -008 -AV) was issued on 24 January 2023 with an
expiration date of 24 January 2028 by the Florida Department of Environmental Protection
(FDEP), Division of Air Resource Management (DARM). This proposal presents the scope of
work, schedule, and budget estimate for the preparation and submittal to the FDEP an application
for the permit revision to include the Landfill Gas Utility Flare to the Title V Air Operation
Permit and coordination of the initial visible emission test.
Geosyntec has prepared this proposal (professional services as Exhibit A of Work Order Number
8, pursuant to that certain Continuing Contract Agreement, dated May 2, 2023 ("Agreement"),
by and between INDIAN RIVER COUNTY, a political subdivision of the State of Florida
("COUNTY") and Geosyntec ("Consultant").
The remainder of this proposal presents: (i) project background; (ii) proposed scope of work; (iii)
schedule; and (iv) budget estimate.
NCP2323263/JL23037 Title V Air Operation Permit Revision Proposal.doc
engineers I scientists I innovators
Mr. Himanshu Mehta
8 May 2025
Page 3
PROJECT BACKGROUND
The IRCL facility is located in southern Indian River County, east of Interstate 95, south of Oslo
Road, and west of Rangeline Road in Vero Beach, Florida. The landfill serves the unincorporated
Indian River County and municipalities of Vero Beach, Orchid, Fellsmere, Sebastian, and Indian
River Shores. The SWDD administers the management and operation of the Class I Landfill at the
IRCL facility, and as such, it is the permit holder of the IRCL facility. This landfill facility is
currently operating under Title V Air Operation Permit No. 0610015 -008 -AV, effective 24 January
2023. The permit covers the following EUs: (i) EU 003 — Municipal Solid Waste (MSW) Landfill;
(ii) EU 004 — Emergency Standby Generator (805 HP) for the on-site bio -solids dewatering facility;
(iii) EU 005 — Landfill Gas Utility Flare; (iv) EU 006 — Emergency Standby Generator (268 HP) at
administrative building; (v) EU 007 — Emergency Standby Generator (26.8 HP) for new leachate lift
station at the landfill; and EU 008 — 30,000 GPD Leachate Evaporator.
As previously mentioned, the IRCL facility was issued a Title V Air Construction Permit No.
0610015 -009 -AC for the Landfill Gas Utility Flare as Emission Unit (EU) 009 on 31 October 2024
with an expiration date of 31 May 2027. This permit authorizes construction of the flare and initial
operation to determine compliance with FDEP rules. The permit requires that SWDD apply for the
permit at least 90 days prior to expiration of the air construction permit, but no later than 180 days
after commencing operation. It also requires that SWDD conduct an initial visible emissions
compliance test within 60 days after achieving the permitted capacity, but not later than 180 days
after initial operation of the unit. The flare went into commercial operation in April 2025 after the
start of commissioning and testing. Therefore, the permit application to include EU 009 to the Title
V Air Operation Permit and the initial visible emissions test are due in July 2025. This proposal
presents the scope of work, schedule and budget estimate to prepare a Title V Air Operation Permit
revision application to include the Landfill Gas Utility Flare and to oversee the required testing.
PROPOSED SCOPE OF WORK
This project includes professional engineering services required to revise the Title V Air
Operation Permit for the IRCL facility to include the Landfill Gas Utility Flare and to comply
with the testing requirements of Permit No. 0610015 -009 -AC. The scope of work is based on
the requirements of F.S. Chapter 403, Chapters 62-4, 62-210, 62-213 F.A.C., and Geosyntec's
understanding of the project based on information provided by SWDD and the Title V permitting
requirements. Geosyntec will provide the engineering services necessary to prepare the permit
modification application and request for additional information (RAI) from FDEP.
For budgeting purposes, the scope of work will be performed in three phases as follows:
• Phase 1 — General Consulting/Meeting Support/Project Management;
• Phase 2 — Visible Emission Testing;
NCP2323263/JL23037 Title V Air Operation Permit Revision Pronosal.doc
engineers I scientists I innovators
Mr. Himanshu Mehta
8 May 2025
Page 4
• Phase 3 — Title V Permit Revision Application; and
• Phase 4 — Response to Regulatory Comments.
Each of these phases is briefly described below.
Phase 1— General Consulting/Meeting Support/Project Management
Phase 1 consists of three components: general consulting, meeting support, and project
management. Geosyntec will provide SWDD with consulting services necessary to initiate the
Project. Geosyntec will prepare presentation graphics, and other documents required to support
the Project's meetings and coordination activities.
A kickoff meeting with SWDD and IRSC, is proposed before the start of project activities so that
the specific project requirements can be discussed. If required by SWDD, Geosyntec will
prepare for and attend a meeting with the SWDD Board to explain the project scope and budget
requirements (Note that this meeting is not included in the budget estimate presented below).
Geosyntec will also schedule and attend, with SWDD staff, meetings with DARM office in
Tallahassee to discuss specific permitting issues. In addition, review meetings will be held with
SWDD as necessary during the project implementation schedule. Following each meeting,
Geosyntec will prepare meeting minutes that document decisions reached in the meetings.
For the purpose of this budget estimate, Geosyntec has included four (4) meetings: (i) one (1)
kickoff meeting with SWDD; (ii) one (1) in -progress design review meeting with SWDD; and
(iii) two (2) meetings with FDEP and SWDD staff. The FDEP meetings will consist of: (i) one
(1) pre -application meeting; and (ii) review meeting following submittal of the Title V permit
revision application. These meetings will be held via teleconference to reduce overall costs of
the project.
Project management activities will include budget and schedule tracking, invoice review, and
project communications, including the preparation of a monthly progress report. The project
report will include a description of the activities completed during the month and planned
activities for the following month. In addition, the progress report will identify technical or
administrative issues that require SWDD's attention and the current status of the budget and
schedule.
Phase 2 — Visible Emission Testing
Under this phase, Geosyntec will oversee the visible emission per Permit Condition 9. This
includes retaining the subcontractor to perform the emission testing, review the test procedures
and report prior to submittal to FDEP, and providing the communication to FDEP that is required
under Permit Condition 9. Additionally, the visible emission test will be included as an
attachment in the Title V Air Operation Permit application.
NCP2323263/JL23037 Title V Air Operation Permit Revision Pronosal.doc
engineers I scientists I innovators
Mr. Himanshu Mehta
8 May 2025
Page 5
Phase 3— Title V Permit Revision Applications
Under this phase, Geosyntec will prepare the FDEP Title V Air Operation Permit revision
application for the IRCL facility. Geosyntec will complete FDEP, DARM Form No. 62-
210.900(1) titled "Application for Air Permit - Long Form" and address the additional
information items required by the form. The following items will be prepared as part of the
permit revision application:
• Facility plot plan;
• Process flow diagram;
• Precautions to prevent emissions of unconfined particulate matter;
• List of insignificant activities;
• Identification of applicable requirements;
• Compliance report and plan;
• Description of proposed revisions to the current Title V Air Operation Permit;
• Fuel analysis or specification;
• Detailed description of control equipment;
• Procedures for startup and shutdown;
• Operation and maintenance plan;
• Previously submitted information; and
• Identification of applicable requirements.
Geosyntec will describe the additional emission unit (i.e., the flare) for the IRCL facility, and
calculate the emissions of air pollutants expected to be released into the environment by its
operation. Geosyntec will complete the required FDEP Form 62-210.900(1) and prepare a
transmittal letter to FDEP that summarizes the permit revision application package.
Phase 4 — Response to Regulatory Comments
Following submittal of the permit revision application, Geosyntec will meet with the FDEP-
DARM Tallahassee office to present and discuss the application package. This meeting will be
held via teleconference in order to reduce overall costs of the project. Geosyntec will provide
FDEP-DARM with written responses to requests for additional information (RAIs) throughout
the course of the permit application review process. For the purpose of the budget estimate,
Geosyntec has estimated one response to FDEP-DARM RAI will be required.
Geosyntec will also review and provide comments on the draft Title V Revised Permit issued by
FDEP to ensure that it is consistent with the facility requirements and does not contain
unexpected compliance and monitoring requirements.
NCP2323263/JL23037 Title V Air Operation Permit Revision Proposal.doc
engineers I scientists I innovators
Mr. Himanshu Mehta
8 May 2025
Page 6
SCHEDULE
Geosyntec will initiate work immediately upon receipt of Notice to Proceed (NTP) from SWDD.
Geosyntec has assumed that this NTP would be issued no later than 21 May 2025 in order for us
to complete the work and submit the Title V Air Operation Permit Revision Application to FDEP
before the due date.
BUDGET ESTIMATE
The budget estimate for the scope of work outlined in this proposal is summarized in the
following table, and a detailed budget estimate is provided as Attachment A. The budget
estimate does not include permit fees that may be required at the time the permit application is
submitted to FDEP.
Phase 1—Project Management/Meetings $8,064.90
Phase 2 — Visible Emission Testing $17,650.40
Phase 3 — Title V Permit Revision Application $13,115.25
Phase 4 — Response to Regulatory Comments $5,467.50
Total Budget Estimate $44,298.05
Geosyntec will not exceed the cost estimate without prior approval and written authorization
from SWDD.
CLOSURE
Geosyntec appreciates this opportunity to offer our services. If this proposal is acceptable,
please indicate your agreement by signing the attached work authorization, which references this
proposal. Please return one signed work authorization to Dr. Badu-Tweneboah's attention.
Please call the undersigned with questions you may have as you review this proposal.
Sincerely,
Cristina Graver, P.E.
Senior Engineer
Copies: Tim Copland and Nichole Walko — Geosyntec Consultants
Attachments
NCP2323263/JL23037 Title V Air Operation Permit Revision Proposal.doc
engineers I scientists I innovators
ATTACHMENT A
DETAILED BUDGET ESTIMATE
TABLE 1
BUDGET ESTIMATE
Preparation of the Title V Air Operation Permit Including Visible Emission Testing
INDIAN RIVER COUNTY LANDFILL
INDIAN RIVER COUNTY, FLORIDA
PHASE 1: General Consulting/Meeting Support/Proiect Manaqement
ITEM
BASIS
RATE
QUANTITY
ESTIMATED
COST
A.
Professional Services
a. Senior Principal
Hr
$310.00
2
$620.00
b. Principal
Hr
$287.00
0
$0.00
c. Senior Professional
Hr
$265.00
8
$2,120.00
d. Project Professional
Hr
$235.00
10
$2,350.00
e. Professional
Hr
$207.00
0
$0.00
f. Senior Staff Professional
Hr
$184.00
10
$1,840.00
g. Staff Professional
Hr
$160.00
0
$0.00
Subtotal Professional Services
$6,930.00
B.
Technical/Administrative Services
a. Senior Designer
Hr
$195.00
0
$0.00
b. Designer
Hr
$165.00
0
$0.00
c. Senior Drafter/Senior CADD Operator
Hr
$150.00
0
$0.00
d. Project Administrator
Hr
$90.00
10
$900.00
e. Clerical
Hr
$68.00
0
$0.00
Subtotal Technical/Administrative Services
$900.00
C.
Indirect Expenses
a. Subcontractor Services
Each
$0.00 1
1.00
$0.00
Subcontractor Services
$0.00
D.
Direct Expenses
a. Lodging
Da
$150.00
0
$0.00
b. Per Diem
Da
$55.00
0
$0.00
c. Communications Fee
3% Labor
3%
$7,830
$234.90
d. CADD Computer System
Hr
$15.00
0
$0.00
e. Vehicle Rental & Fuel
Da
$150.00
0
$0.00
Subtotal Reimbursables
$234.90
TOTAL ESTIMATED BUDGET: PHASE 1
8 064.90
TABLE 2
BUDGET ESTIMATE
Preparation of the Title V Air Operation Permit Including Visible Emission Testing
INDIAN RIVER COUNTY LANDFILL
INDIAN RIVER COUNTY, FLORIDA
PHASE 2: Visiable Emission Testing
IF
-
ITEM
BASIS
RATE
QUANTITY
ESTIMATED
COST
A.
Professional Services
a. Senior Principal
Hr
$310.00
0
$0.0011
b. Principal
Hr
$287.00
0
$0.00
c. Senior Professional
Hr
$265.00
4
$1,060.00
d. Project Professional
Hr
$235.00
4
$940.00
e. Professional
Hr
$207.00
0
$0.00
f. Senior Staff Professional
Hr
$184.00
20
$3,680.00
g. Staff Professional
Hr
$160.00
0
$0.00
Subtotal Professional Services
$5,680.00
B.
Technical/Administrative Services
a. Senior Designer
Hr
$195.00
0
$0.00
b. Designer
Hr
$165.00
0
$0.00
c. Senior Drafter/Senior CADD Operator
Hr
$150.00
0
$0.00
d. Project Administrator
Hr
$90.00
0
$0.00
e. Clerical
Hr
$68.00
0
$0.00
Subtotal Technical/Administrative Services
$0.00
C.
Indirect Expenses
a. Subcontractor Services
Each
$11,500.00 1
1.00
$11,500.00
Subcontractor Services
$11,500.00
D.
Direct Expenses
a. Lodging
Da
$150.00
0
$0.00
b. Per Diem
Da
$55.00
0
$0.00
c. Communications Fee
3% Labor
3%
$5,680
$170.40
d. CADD Computer System
Hr
$15.00
0
$0.00
e. Vehicle Rental & Fuel
Da
$150.00
2
$300.00
f. 8"x11"Photocopies
Each
$0.12
0
$0.00
g. CADD Drawings
Each
$3.00
0
$0.00
Subtotal Reimbursables
$470.40
TOTAL ESTIMATED BUDGET: PHASE 2
$17,650.40
TABLE 3
BUDGET ESTIMATE
Preparation of the Title V Air Operation Permit Including Visible Emission Testing
INDIAN RIVER COUNTY LANDFILL
INDIAN RIVER COUNTY, FLORIDA
PHASE 3: Title V Permit Revision Application
IF
-
ITEM
BASIS
RATE
QUANTITY
ESTIMATED
COST
A.
Professional Services
a. Senior Principal
Hr
$310.00
2
$620.00
b. Principal
Hr
$287.00
0
$0.00
c. Senior Professional
Hr
$265.00
10
$2,650.00
d. Project Professional
Hr
$235.00
0
$0.00
e. Professional
Hr
$207.00
15
$3,105.00
f. Senior Staff Professional
Hr
$184.00
30
$5,520.00
g. Staff Professional
Hr
$160.00
0
$0.00
Subtotal Professional Services
$11,895.00
B.
Technical/Administrative Services
a. Senior Designer
Hr
$195.00
4
$780.00
b. Designer
Hr
$165.00
0
$0.00
c. Senior Drafter/Senior CADD Operator
Hr
$150.00
0
$0.00
d. Project Administrator
Hr
$90.00
0
$0.00
e. Clerical
Hr
$68.00
0
$0.00
Subtotal Technical/Administrative Services
$780.00
C.
Indirect Expenses
a. Subcontractor Services
Each
$0.00 1
1.00
$0.00
Subcontractor Services
$0.00
D.
Direct Expenses
a. Lodging
Da
$150.00
0
$0.00
b. Per Diem
Da
$55.00
0
$0.00
c. Communications Fee
3% Labor
3%
$12,675
$380.25
d. CADD Computer System
Hr
$15.00
4
$60.00
e. Vehicle Rental & Fuel
Da
$150.00
0
$0.00
f. 8"x11" Photocopies
Each
$0.12
0
$0.00
g. CADD Drawings
Each
$3.00
0
$0.00
Subtotal Reimbursables
$440.25
TOTAL ESTIMATED BUDGET: PHASE 3
$13,115.25,
TABLE 4
BUDGET ESTIMATE
Preparation of the Title V Air Operation Permit Including Visible Emission Testing
INDIAN RIVER COUNTY LANDFILL
INDIAN RIVER COUNTY, FLORIDA
PHASE 4: Response to Regulatory Comments
ITEM
BASIS
RATE
QUANTITY
ESTIMATED
COST
A.
Professional Services
a.
Senior Principal
Hr
$310.00
0
$0.00
b.
Principal
Hr
$287.00
0
$0.00
c.
Senior Professional
Hr
$265.00
8
$2,120.00
d.
Project Professional
Hr
$235.00
10
$2,350.00
e.
Professional
Hr
$207.00
0
$0.00
f.
Senior Staff Professional
Hr
$184.00
0
$0.00
g.
Staff Professional
Hr
$160.00
0
$0.00
Subtotal Professional Services
$4,470.00
B.
Technical/Administrative Services
a.
Senior Designer
Hr
$195.00
4
$780.00
b.
Designer
Hr
$165.00
0
$0.00
c.
Senior Drafter/Senior CADD Operator
Hr
$150.00
0
$0.00
d.
Project Administrator
Hr
$90.00
$0.00
e. Clerical
Hr
$68.00
0
$0.00
Subtotal Technical/Administrative Services
$780.00
C.
Indirect Expenses
a.
Subcontractor Services
Each
$0.00 1
1.00
$0.00
Subcontractor Services
$0.00
D.
Direct Expenses
a.
Lodging
Da
$150.00
0
$0.00
b.
Per Diem
Da
$55.00
0
$0.00
c.
Communications Fee
3% Labor
3%
$5,250
$157.50
d.
CADD Computer System
Hr
$15.00
4
$60.00
e.
Vehicle Rental & Fuel
Da
$150.00
0
$0.00
f.
8"x11"Photocopies
Each
$0.12
0
$0.00
g.
CADD Drawings
Each
$3.00
0
$0.00
Subtotal Reimbursables
$217.50
TOTAL ESTIMATED BUDGET: PHASE 4
5 467.50