SECTION 00942 — Change Order Form
No. 1
DATE OF ISSUANCE: 3/20/2026
EFFECTIVE DATE: 3/20/2026
OWNER: Indian River County
CONTRACTOR NEW TECH CONSTRUCTION CORP.
Project: IT INTERCONNECTIVITY BLDG B TO EOC
OWNER's Project No. CP -2513
OWNER'S Bid No. 2025046
You are directed to make the following changes in the Contract Documents:
Description: INCREASE CONTRACT PRICE BY $14,650 FOR A TOTAL CONTRACT PRICE OF $505,847.
Reason for Change Order: ADDITION OF SLACK BOX
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE:
Description
Amount
Original Contract Price
$491,197
Net Increase (Decrease) from
$
previous Change Orders No.
to
Contract Price prior to this Change
$491,197
Order:
Net increase (decrease) of this
$14,650
Change Order:
Contract Price with all approved
$505,847
Change Orders:
ACCEPTED:
1QrR Mark Snyder
Date: 2026.03.20
By: nyder 12:41:23-04'00'
F
CONTRACTOR (Signature)
Date:
CHANGE IN CONTRACT TIMES
Description
Time
Original Contract Time:
(days or dates)
Substantial Completion:
Final Completion:
Net change from previous Change
Orders No. to
(days)
Substantial Completion:
Final Completion:
Contract Time prior to this Change
Order:
(days or dates)
Substantial Completion:
Final Completion:
Net increase (decrease) this Change
Order:
(days or dates)
Substantial Completion:
Final Completion:
Contract Time with all approved
Change Orders:
(days or dates)
Substantial Completion:
Final Completion:
RECOMMENDED:
Rob Skok a `®�
= Buiq -ery��
By:
ENGINEER (Signature)
Date:
Attest: Ryan L. Butler, Clerk of
Circuit Court and Comptroller
f
APPROVED
By: k-6-25-
OWNER
-62OWNER (Signature)
Date: April 7
Change Order Form — 00942
R C OUN �' �s•
Change Order Form — 00942
New -Tech Construction, Corp.
1579 Barber Rd.
Sarasota, FL 34240
Name / Address
Indian River County
Ship To
Sales Order
Date
S.O. No.
2/27/2026
33235
P.O. No.
Rep
Project
NOTES
CP -2513
Item
Description
Rate
Ouanity
U/M
Invoiced
Amount
Other Customer
Labor
14,650.00
1
0
14,650.00
-Set 48"x60" HD HH/pull box
oMachine set required
-Bridge 2 conduits between existing/new
boxes
-Remove existing damaged apron
-Frame-set rebar for Double apron
oTo encompass both HHs
Supplied Materials
•48"x60" HD HH/pull box
-Conduit for connection
-Apron materials: rebar, chairs, concrete
Total $14,650.00