HomeMy WebLinkAbout2026-077SECTION 00942 - Change Order Form DATE OF ISSUANCE: 4/1/26 No. 1 EFFECTIVE DATER/1/26 OWNER: Indian River County CONTRACTOR W & J Construction Corporation Project: Fire Station No. 7 OWNER's Project No. IRC -1911 OWNER'S Bid No. 2024041 You are directed to make the following changes in the Contract Documents: Description: Reason for Change Order: The project is complete. This change order is intended to make final adjustments to the bid line and items and time to finalize the contract. Attachments: (List documents supporting change) Description of Itemized Changes CHANGE IN CONTRACT PRICE: Time Description Amount Original Contract Price $7,130,185.74 Net Increase (Decrease) from $0 previous Change Orders No. to (days) Contract Price prior to this $7.130,185.74 Change Order: Net increase (decrease) of $j261,284.37) this Change Order: (days or dates) Contract Price with all $6,868,901.37 approved Change Orders: ACCEPTED: By: I :::�L CONTRACTOR (Signature) Date: 04/07/2026 CHANGE IN CONTRACT TIMES Description Time Original Contract Time: (days or dates) Substantial Completion: Final Completion: Net change from previous Change Orders No. to (days) Substantial Completion.- ompletion:Final FinalCompletion: Contract Time prior to this Change Order: (days or dates) Substantial Completion: Final Completion: Net increase (decrease) this Change Order: (days or dates) Substantial Completion: Final Completion: Contract Time with all approved Change Orders: (days or dates) Substantial Completion: Final Completion: RECOMMENDED: Rob By Project Manager (Signature) Date: APPROVED: By: OWNER (Signature) Date: Change Order 1 00942-1 F:\Building&FacilitiesDept\Projects\IRC - 1911 Fire Station 7\1-Admin\Agenda Items\Project Closeout\Change Order 1.doc Rev. 05/01 CHANGE ORDER NO. 1 DESCRIPTION OF ITEMIZED CHANGES PROJECT NAME: Fire Station 7 PROJECT NO. IRC -1911 BID NO. 2024041 Item No. Description Unit Ouantl Unit Price Price Increase Price Decrease 1 Timber Crossing 1 1 50,715.00 50,715.00 2 Window Chane 1 1 6,615.89 6,615.89 3 iTree Prunning for FPL 1 1 1 12,075.00 12,075.00 4 Drawing sheet changes, 22 sheets 1 1 17,170.77 17,170.77 5 Main Breaker for MPD to 100% rated 1 1 19,002.43 19,002.43 6 Flooring Changes per Fire Department 1 1 10,715.86 10,715.86 7 Fans, Utility valves 1 1 46,006.91 46,006.91 8 Pipe in Retention area Fill grading for FPL transformer pad 1 1 6,450.00 6,450.00 9 Kitchen - switch out counters to SS cabinets 1 1 20 346.73 20 346.73 10 Irrigation/Sod 1 1 24 316.95 (24,31&95) 11 Stucco Band per Architect 1 1 4,725.00 4,725.00 12 Fire Lid Issue/Dampers 1 1 85 344.50 85 344.50 13 Additional Data Lines 1 1 3 811.50 3,811.50 14 Lockers 1 1 18 221.70 18 221.70 15 Mini Splits 1 1 13,096.26 13,096.26 16 Exterior Signage 1 1 1,919.17 1,919.17 17 Gates at Gas Easement 1 1 3,335.46 3,335.46 18 Tile Base 1 1 1,406.92 1,406.92 19 Access Control for 3 Doors 1 1 12,810.00 12,810.00 20 Fire Sprinkler Heads 1 1 3,260.20 3,280.20 21 Moisture Mitigation 1 1 14 631.75 14,631.75 22 Corner guards 1 1 306.24 306.24 23 Material Testing,ARVs Fire Extin ushers 1 1 49 039.63 49 039.63 24 Exit Signs, Lights 1 1 11165.50 1 165.50 25 Reconcile Balances 1 1 30 979.96 30 979.96 FA FORCEACCOUNT LS 1 570000.00 SUBTOTALS I 1 1 383,102.48 1 -644,386.85 PROJECT NAME: Fire Station 7 TOTAL 1 $ (261,284.37) F.\BuM,N&Fzi—Dept\Rgmt,VRC-1911 Fre 91—Tt-PdminVgerNa Items\PrgM CbsealUte .i Chxlges Indian River County Indian River Q L Administration Complex County, Florida 1801 27th Street Vero Beach. Florida 32960 Indian River County Website \0 RIVI Memorandum File ID: Type: Meeting Date: 2026-589 Consent Agenda April 21, 2026 To: Board of County Commissioners Through: John Titkanich Jr., County Administrator Anthony Warren, Building & Facilities Director From: Rob Skok, Manager, Capital Projects Date: 04/0712026 Subject: Fire Station 7 (IRC -1911) — Change Order No. 1, Final Pay Application/Release of Retainage – Project Closeout Background: On May 26, 2024, the project was advertised for bid and all sealed bids were opened on July 10, 2024. W&J Construction Corporation was considered the lowest, responsive, responsible bidder for the project with a bid total of 57,130,185.74 and was subsequently awarded the project on 8/120/2024. Analysis: Change Order No. 1 is to snake final adjustments to contract bid items for a (decrease) to the total contract by (5261,284.37) resulting in a final contract price of $6,868,901.37. W&J Construction Corporation has completed the project and has been paid 56,525,456.30 to date. Contractor is due Pay Application #16 for $343,445.07 held in retainage for a total payout of $343,445.07. Budgetary Impact: Funding for this project is available in Optional Sales Tax/Fire Services/Fire Station No.7 Construction. Contractor retainage for $343,445.07 is held in account 315-206000-19020. Previous Board Actions: The Board awarded Bid No. 2024041 to W&J Construction Corporation on August 20, 2024, for Fire Station 7 Construction. Potential Future Board Actions: N/A Strategic Plan Alignment: NIA Other Plan Alignment: N/A Staff Recommendation: Staff recommend approval of Change Order No. 1 and payment of Contractor's Final Application of Payment to W&J Construction Corporation in the amount of $343,445.07. Attachments: 1. Change Order 1 2. IRC- 1911_PA16_2026-04-01 - Retainage