HomeMy WebLinkAbout2026-170A TRUE COPY
CERTIFICATION ON LAST PAGE
RYAN L. BUTLER, CLERK
ENGINEERING SERVICES WORK ORDER 14
This Work Order Number 14 is entered into as of this /5 day of U 'C/ ,
pursuant to that certain Continuing Contract Agreement, dated May 2, 2023, ("Agreement"), by and
between INDIAN RIVER COUNTY, a political subdivision of the State of Florida ("COUNTY") and
MBV Engineering, Inc.
("Consultant")
The COUNTY has selected the Consultant to perform the professional services set forth on
Exhibit A (Scope of Work), attached to this Work Order and made part hereof by this reference. The
professional services will be performed by the Consultant for the mutually agreed upon lump sum or
maximum amount not -to -exceed professional fee. Any additional costs must be approved in writing,
and at a rate not to exceed the prices set forth in Exhibit B of the Agreement (Rate Schedule) for RFQ
2023015, made a part hereof by this reference. The Consultant will perform the professional services
within the timeframe more particularly set forth in Exhibit A (Time Schedule), attached to this Work
Order and made a part hereof by this reference all in accordance with the terms and provisions set
forth in the Agreement. Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work
Order shall conflict with the terms of the Agreement and the terms of the Agreement shall be deemed
to be incorporated in each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the date first
written above.
CONSULTANT:
By:
Name: Aaron Bowles, P.E.
Title: Senior Vice President
BOARD OF COUNTY COMMISSQISS'1 -. 5%,`•
INDIAN dh
By:
Deryl Loar, Chairman ;y.
BCC Appr'v, l qaJ SEPt TiXr ;�' i`.
By: ,/L 7V/C' *
hn A. Titkanich, Jr., Countymin
Approved as to Form and Legal Sufficiency:
By:
nnife . Shuler, County Attorney
Ryan L. Butler, Clerk of Court and Comptroller
Attest:
Deputy Clerk
(SEAL)
A TRUE COPY
CERTIFICATION ON LAST PAGE
RYAN L. BUTLER, CLERK
EXHIBIT A - SCOPE OF WORK
It is our understanding that the COUNTY intends to construct a neighborhood park in Vero Lake Estates
on an approximately 8.27 -ac COUNTY owned tract of land zoned RS -3 and bordered by 78th Street to
79th Street and 98th Avenue to 99th Avenue. We understand the park will consist of amenities such as a
picnic pavilion, stabilized walking trails, open lawn areas, sidewalks, a basketball court, fitness station
and playground area. We further understand that the COUNTY has previously coordinated with the VLE
Homeowner's Association and that the "Alternative2: Field and Forest" Conceptual Plan is the favored
plan for the park depicting the aforementioned amenities and is what this Work Order shall be based
on. As such, MBV Engineering Inc. will provide the following scope of services in support of the project:
Existing Conditions Survey, Civil design, Structural design permitting services, bidding assistance and
construction administration services as related to the above activities and as further described below.
TASK 1- EXISTING CONDITIONS SURVEY
This task includes the services listed below associated with the Existing Conditions Survey services
required for the project.
A. Existing Conditions Survey Services
• Boundary survey with improvements.
• Recover and verify or, set permanent markers at perimeter boundary corners.
• Locate and depict permanent, fixed above -ground improvements on site and within 2 -feet
either side of perimeter boundary lines.
• Depict easements/ right of ways shown on Record Plat or known to surveyor.
• Depict current flood zone lines, if applicable.
• Topographic survey, minimum 50 -foot grid within project scope area.
• Topographic survey to extend 25' beyond perimeter boundary lines.
• Topographic survey to include full width of paved/dirt roadways adjacent to parcel.
• LiDAR scanning for enhanced elevation saturation and mapping.
• Locate desirable trees 8" dbh and above.
• Locate visible above ground utilities with elevations, where applicable.
• Locate existing drainage structures including rim elevation, pipe invert, size, type and
direction within project scope area.
• Provide sufficient elevations on site to determine existing drainage patterns.
• Provide 6 certified copies of the completed survey, including all the above.
• Provide a PDF copy of the survey, upon request.
B. Gopher Tortoise Hole Locations — (If Applicable)
• Locate and depict gopher tortoise holes as flagged in the field by others.
A TRUE COPY
CERTIFICATION ON LAST PAGE
RYAN L. BUTLER, CLERK
TASK 2— CONCEPTUAL SITE PLAN AND PRELIMINARY AGENCY COORDINATION
This task includes the services below associated with the development of a Conceptual Site Plan and
coordination with the below jurisdictional agencies in preparation for design and permitting phase.
1. Conduct (1) site inspection at the site location prior to Conceptual Plan Development.
2. Development of the Conceptual Site Plan in preparation for coordination with the jurisdictional
agency. This task includes coordination with IRC staff and revisions to (2) two rounds of
comments. Should additional layouts be desired, those services shall be billed under Task 9
below.
3. Preparation of the following pre -application form and package and attendance at the meeting:
• IRC pre -application meeting form
TASK 3 - CIVIL DESIGN & PERMITTING
This task includes the below services associated with design and permitting portion of the project once
Task 1 has been completed and a Site Layout has been agreed upon.
1. Project coordination with the following regulatory agencies:
• Indian River County (IRC)
• St. Johns River Water Management District (SJRWMD)
• Florida Department of Environmental Protection (FDEP)
2. Review of the Existing Conditions Survey. It is understood that the existing conditions survey
will be provided by others to MBV in both CAD and hard copy formats to be utilized in the design
of the project. The cost of survey work has been included in this proposal and is noted above
under Task 1.
3. Review of the subsurface soils investigation. No cost of geotech work is included in this
proposal. MBV will assist in identifying approximate soil boring locations needed for the civil
portion of the site development. The geotechnical firm shall contract directly with the COUNTY.
4. Attendance at three (3) design development meetings with IRC and project team during the
civil design phase.
5. Finalization of the Civil site plan layout upon completion of IRC/development team reviews.
6. Development of the stormwater adlCPR drainage model and calculations for the development's
stormwater containment system sizing and runoff analysis.
7. Design of the paving, grading, and drainage system.
8. Coordination with the RCP Shelters, Inc. in the proposed pavilion design layout. It is understood
the IRC Park's Department would like to RCP Shelters, Inc. for the pavilion design plans and that
all plans required or Civil permitting shall be provided by this company to MBV for use in the
Civil design documents.
9. Project coordination with the landscape architect. MBV shall coordinate with the Landscape
Architect during the design process and provide CAD base plans as required for the
development of the Landscape Plans and details. Landscape architect shall provide all landscape
design plans and responses to comments as needed for project permitting. The cost of
landscape design and permitting services has been included in this proposal. See Task 5 for
Landscape Design scope.
10. Project coordination with the IRC for the Environmental items. It is understood that IRC will
provide all Environmental items, inspections, reports, documents, etc. as needed for the
project. Therefore, the cost of Environmental services has not been included in this proposal.
A TRUE COPY
CERTIFICATION ON LAST PAGE
RYAN L. BUTLER. CLERK
11. Development of civil construction plans consisting of, or a combination thereof:
• Cover Page
• General Notes Plan
• Existing Conditions Plan
• Demolition Plan
• Erosion Control Plan and Details
• Summary of Quantities Plan
• Site Plan
• Paving, Grading and Drainage Plan
• Cross Sections Plan
• Site Details Plan
• Paving, Grading and Drainage Details Plans
12. Preparation of the following design reports for the subject project:
• Stormwater Management Calculations
• Stormwater Operation & Maintenance (O&M) Report
13. Preparation of the following permit applications:
• IRC Major Site Plan
• IRC Land Clearing
• IRC Tree Removal
• IRC Concurrency (Conditional and Final)
• IRC Stormwater
• IRC Right -of -Way
• IRC Fire Review
• SJRWMD Environmental Resource Permit
• FDEP NPDES Notice of Intent
14. Submission of civil plans and application packages to permit agencies.
15. Coordination with jurisdictional agency representatives and Owner for up to two rounds of
agency review comments. Changes requested by COUNTY that alter the original submission
design shall be billed under Task 9.
16. Final Construction drawing revisions per jurisdictional comments and resubmittal to agencies
for final approvals.
17. Development of 100% plans Opinion of Probable Cost.
TASK 4- STRUCTURAL DESIGN & PERMITTING
The Consultant will provide the following structural design services design for the proposed windsail
covers, playground equipment, and fitness equipment:
A. Design
• Review of proposed equipment details as provided by COUNTY
• Establish structural design criteria
• Develop structural design and preparation for the foundation and / or footer plans and
sections
• Development of foundation specifications on plans
A TRUE COPY
CERTIFICATION ON LAST PAGE
RYAN L. BUTLER, CLERK
B. Permitting
The Consultant will prepare application packages and provide them to the COUNTY to deliver
to the selected contractor for submission to the IRC Building Department.
The Consultant will respond to Building Department review comments and re -submit plans to
address comments, as necessary. It should be noted the project contractor, or COUNTY will be
responsible for submitting and obtaining the building permit and payment. Fees for building
permit application(s) shall be the responsibility of the Owner.
TASK 5 —LANDSCAPE PLANS AND TREE ARBORIST REPORT
A. Tree Survey & Health Assessment
• Provide a location & health assessment for all existing protected and specimen trees on site.
B. Arborist Report
• Provide mitigation tree deficiency reporting on any specimen trees (13" plus) with a
mitigation score of 3 or less. Pictures and notes on the specific tree and deficiency will be
noted and compiled.
• Coordinate and/or meet with county staff as needed regarding existing trees.
C. Landscape and Tree Mitigation Plans
• Provide a landscape plan for all green areas within project scope to include vehicular use
area, various park program elements, & open space areas.
• Provide a tree disposition plan for all existing protected & specimen trees on site based on
arborist report.
• Provide tree mitigation/preservation strategy, data, & plan to comply with the county's
mitigation code & standards.
• Coordinate and/or meet with county staff as needed regarding landscape plan & tree
mitigation.
• Includes (1) modification to plans due to client comments.
• Provide signed and sealed landscape plans for government submittal.
D. Irrigation Plans
• After landscape plan is finalized for submittal, provide an irrigation plan for proposed
landscape that includes mainline, valve, & head layout, as well as itemized schedule for
construction.
• Includes (1) modification to plans due to client comments.
TASK 6 - BIDDING SERVICES
This task includes those efforts to assist IRC with project bidding and will provide the services below:
• Preparation of civil plan documents for bidding and transmittal to Owner
• Attendance at one pre -bid meeting
• Responses to requests for additional information (RAIs) from bidders
A TRUE COPY
CERTIFICATION ON LAST PAGE
RYAN L. BUTLER, CLERK
NOTE: All construction specifications will be on the applicable Civil plan sheets in lieu of a specifications
manual.
TASK 7— CONSTRUCTION INSPECTIONS, COORDIANTION AND CERTIFICATIONS
This task includes construction inspections and certifications as required by the local and state
regulatory agencies, in addition to the inspections required by the Engineer of Record, to provide final
certifications. The scope below represents the services that will be required at each location during
this phase:
A. Civil Construction Services
Pre -Construction Meeting:
• Coordination and attendance at one meeting at IRC with the selected contractor and IRC
staff.
Parking Lot / Drainage:
• Shop drawing review, Inspections for parking lot (sub -base / base / asphalt), grading, storm
pipe/inlet installation, drainage structures, and final grading / sodding
Overall Site:
• Inspections for Striping / signage, landscape, irrigation, maintenance bond cost estimate
assistance.
Erosion Control:
• Pursuant to the State of Florida NPDES regulations, all construction sites shall be required
to conduct weekly NPDES inspections during site -work construction, and monthly
inspections during vertical construction, by a certified NPDES Inspector. Inspections are
required within 24 hours after the site has experienced %" or more of rainfall during the
construction phase.
Final Certifications:
• Preparation of all permit certification forms, coordination with surveyor / contractor /
owner for required information for certification, submittal(s) to regulatory agencies, as
required.
Contractor RFIs/Coordination:
• Coordination with the site Contractor for construction RFIs
• Attendance at twelve (12) Bi-monthly construction meetings at the project site. Any
additional meetings that are requested shall be billed under Task 9.
TASK 8- PERMIT APPLICATION & REIMBURSABLE FEES
Past project experience indicates that project timelines are optimized when the Civil Engineering firm
pays permit fees upfront and requests reimbursement, mitigating delays associated with the agency's
internal check issuance process. As such, this task is to assist the COUNTY with paying for the various
civil permit application fees upfront that may be required and then seeking reimbursement. This task
A TRUE COPY
CERTIFICATION ON LAST PAGE
RYAN L. BUTLER, CLERK
includes MBV advancing the costs and expenses such as print costs, mileage, courier deliveries, and
overnight deliveries associated with the project. Any additional permit fees will be paid by the COUNTY.
Fees included in this Task include the following:
• IRC Major Site Plan
$2,600
• IRC Land Clearing
$ 120
• IRC Tree Removal
$ 200
• IRC Conditional Concurrency
$ 150
• IRC Final Concurrency
$ 150
• IRC Stormwater
$ 850
• IRC Right-of-way
$ 800
• St. Johns River Water Mngt. District
490
$5,360 Subtotal
TASK 9 — REQUESTED CHANGES OUTSIDE SCOPE (IF APPLICABLE)
This task is to cover any potential costs that may be incurred due to Additional Services requested or
changes/modifications by COUNTY or its representatives that are not included in this scope. Should no
out -of -scope items be requested, this Task will not be utilized, and all monies will be returned to
COUNTY.
EXHIBIT B - DELIVERABLES
The Consultant shall provide the COUNTY with the following at the 100 percent milestone:
• Two (2) sets of plans in 24" x 36" format (signed & sealed)
• One (1) Opinion of Probable Cost (Cost Estimate)
• One (1) electronic version of the plans in pdf and CAD format
STATE OF FLORIDA
INDIAN RIVER COUNTY
THIS IS TO CERTIFY THAT THIS IS A TRUE AND CORRECT
COP THE OR 1N1. FILE IN OFFICE.
L U C
BY% D.C.
DATE ).2
EXHIBIT C - RATE SCHEDULE
The COUNTY agrees to pay and the Consultant agrees to accept for services rendered, pursuant to this
Agreement, fees inclusive of expenses in accordance with the following:
Task
Fee
Task 1 - Survey
A. Existing Conditions Survey Services
$ 10,500
B. Gopher Tortoise Hole Locations (If Applicable)
$ 1,500
Task 2 - Conceptual Site Plan and Preliminary Agency Coordination
$ 5,500
Task 3 - Civil Design & Permitting
$ 52,475
Task 4 - Structural Design & Permitting
$ 12,000
Task 5 — Landscape Plans and Tree Arborist Report
A. Tree Survey & Health Assessment
$ 5,600
B. Arborist Report
$ 3,000
C. Landscape and Tree Mitigation Plans
$ 6,000
D. Irrigation Plans
$ 1,800
Task 6 - Bidding Services
$ 4,000
Task 7 - Construction Inspections, Coordination and Certifications
A. Civil Construction Services
$ 18,900
Task 8 - Permit Application & Reimbursables Fees
• Permit Fees
$ 5,360
• Reimbursables
$ 2,000
Task 9 - Requested Changes Outside Scope (If Applicable)
$ 6,500
Work Authorization Total
$135,135
ADDITIONAL SERVICES
When required by the COUNTY or the Contract Documents, where circumstances exist beyond the
Consultant's control, Consultant shall provide or obtain from others, as circumstances required, those
additional services not listed as part of the Work Order, the Consultant shall notify the COUNTY
promptly prior to commencing said Additional Services, and if agreed upon, will be paid for by County
in accordance with the Master Agreement, Professionals and vendor intended to provide additional
services shall first be approved by the COUNTY, in writing, by the COUNTY's Project Manager.
The COUNTY has selected the Consultant to perform the professional services set forth on this Work
Order. The professional services will be performed by the Consultant for the fee schedule set forth in
this Work Order. The Consultant will perform the professional services within the timeframe more
particularly set forth in this Work Order in accordance with the terms and provisions set forth in the
Agreement. Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work Order shall
conflict with the terms of the Agreement and the terms of the Agreement shall be deemed to be
incorporated in each individual Work Order as if fully set forth herein.