HomeMy WebLinkAbout2015-157CHANGE ORDER NO. 6 - FINAL DATE OF ISSUANCE: EFFECTIVE DATE: OWNER: INDIAN RIVER COUNTY CONTRACTOR: CLOSE CONSTRUCTION, LLC PROJECT: PC South Algal Nutrient Removal Facility OWNER'S PROJECT NUMBER: 949 ENGINEER: INDIAN RIVER COUNTY You are directed to make the following changes in the Contract Documents: Item Description Increase/Decrease in Contract Price Increase/Decrease in Contract Time (Calendar Days) 6.1 Reconcile Pay Item 3.12 - Millings road and millings turnout area. Add 20 square yards to original contract pay item quantity = 20 SY * $20.70/SY $414.00 0.0 0.0 6.2 Deduction for millings road surface rehabilitation by County selected contractor. ($3,082.00) 0.0 6.3 Reconcile Pay Item 3.49 - 6" thick concrete floway. Add 27.30 square yards to original contract pay item quantity due to discrepency between civil/mechanical drawing dimensions and structural drawing dimensions = 27.30 SY * $38.00/SY $1,037.40 6.4 Reconcile Pay Item 3.63 - Type B coated chain Zink fence. Deduct 83.5 LF that was not constructed from original contract quantity = 83.5 LF * $13.11/LF ($1,094.69) 0.0 6.5 Reconcile Pay Item 3.64 - 3 -Strand barb wire on existing water treatment plant fence. Add 115.4 LF to original contract pay item quantity = 115.4 LF * $2.00/LF $230.80 0.0 6.6 Delete Pay Item 3.65 in its entirety (32' wide coated chain-link fence double gates) ($2,360.00) 0.0 6.7 Delete Pay Item 3.66 in its entirety (24' wide coated chain-link fence double gates) ($2,115.00) 0.0 6.8 Delete Pay Item 3.68 in its entirety (18' wide coated chain-link fence cantilevered gates) ($3,050.00) 0.0 0.0 6.9 Replacement of Duperon harvest rake cabinet ($5,570.00) 6.10 Add change order driveway improvements to South Relief Canal pump station site Record Drawing Survey $450.00 0.0 ($15,139.49) TOTALS 0.0 CHANGE IN CONTRACT PRICE Description Amount Original Contract Price $5,856,660.20 Net increase/decrease from previous Change Orders $355,124.73 Contract Price prior to this Change Order $6,211,784.93 Net increase/decrease of this Change Order ($15,139.49) Contract Price with all approved Change Orders $6,196,645.44 CHANGE IN CONTRACT TIME (Calendar Days) Description Amount Original Contract Time for Final Completion 365.0 Net increase/decrease from previous Change Orders 103.0 Contract Time for Final Completion prior to this Change Order 468.0 Net increase/decrease of this Change Order to Final Completion 0.0 Contract Time for Final Completion with all approved Change Orders 468.0 ACCEPTED: CONTRACTOR (Signature) Close Construction, LLC Thomas C. Close, President (Name and Title) Date: 7/29/2015 Attest: Jeffrey R. Smith, Clerk of Circuit Couit Comptroller ,,o��M1S S IOPIERS'•, Deputy Ci.* RECOMMENDED: B Y• V���! ,! EN ' .ER (Signature) - Keith McC , P.E., Indian River County Stormwa r Engineering Division Date: g— 5 - 20/.s APPROVED: OWNER: Indian River County Board of County Commissioners Chairman Wesley S. Davis Date: August 18, 2015 Asphalt Recycling, Inc. P.O. Box 510875 Melbourne Beach, FL 32951-0875 Bill To: Finance Department County Administration Building 1801 27th Street, Bldg A Vero Beach, FL 32960-3365 Description CHANGE ORDER 6 - ITEM 6.2 Est. Qty. Estimate Estimate Date: 7/13/2015 Estimate #: 11391 Project: Stormwater Recycling Plant U/M Rate Total Sq. yds Reclamation ARI will reclaim asphalt milling base, regrade and compact 1,541 sqyd 2.00 3,082.00 Total $3,082.00 Keith McCuIIy CHANGE ORDER NO. 6 - ITEM 6.9 From: Sent: To: Cc: Subject: Hi Chris and Keith, Megan Krieger <mkrieger@duperon.com> Tuesday, June 30, 2015 4:28 PM chrisselph@closeconstruction.us Keith McCuIIy FW: Close Construction Resolution Please see below the confirmation from Tammy on the panel issue. Keith — I'll initiate a credit/refund to the County with our accounting department. Thank you, Megan From: Tammy Bernier Sent: Tuesday, June 30, 2015 3:36 PM To: Megan Krieger Subject: Close Construction Resolution HI Megan, Based on our conversation, 1. Issue: The storage instructions for the panel indicates it must be stored indoors. It was not. The 3 DC team members as well as the County Inspector deemed the panel unsafe to install. The unit is NEMA 4x, but cannot be stored on its back nor in an outdoor condition. The customer, Indian River offered to store panels. It was not chosen to do so. Close Construction is responsible for the impacts for not doing so. 2. Duperon's Response: In order to partner with Close to manage this consequence, Duperon discounted a replacement panel, while also saving $3000 by purchasing a new panel (vs the cost to refurb). You offered dot see if there would be any internal use for the enclosure itself that we could return to Indian River as a discount to help Close mitigate the amount of out of pocket expense. 3. This request was made to the Controls team at DC. It appears that the amount of credit we could offer, though there would be very limited use for the panel would be $2000. As I promised Chris, I would get the details of the issue. We would own what is ours, request that they own what is theirs, and partner to come to a fair outcome. I think that what we have discussed above reflects our commitment. Please forward this email to Chris as I promised that we would be in communication no Tater than EOD Wednesday, 7/1/15. Thanks for your help on this matter. Ta 4Wkt L. 6e4 -i' --r President/CEO Duperon Corporation 1200 Leon Scott Court Saginaw, MI 48601 TF 800.383.8479 P 989.401.7111 1 F 989.754.2175 tbernier(c�duperon.com �DUperott ADAPTIVE TECHNOLOGY' Your Path to the Future" Please consider the environment before printing this email. CONFIDENTIALITY NOTICE: The pages composing this email transmission may contain privileged and confidential information. The information in this email transmission is intended solely for use by the individual or entity named as the recipient. If you are not the intended recipient, be aware that any disclosure, copying, distribution or use of the contents of this e-mail transmission is prohibited. If you have received this e-mail transmission in error, please notify our office. Thank you. 2 Keith McCuIIy CHANGE ORDER NO. 6 - ITEM 6.10 From: Sent: To: Cc: Subject: Chris Selph <chrisselph@closeconstruction.us> Friday, July 10, 2015 9:04 AM Keith McCuIIy Arjuna Weragoda; Mike Delaney; Terry Southard; Jerry Miller, 'Chris Rossi' RE: PC SOUTH - RECORD DRAWING SUBMITTAL I will get the surveyor back out to survey the concrete drive and sidewalk to satisfy the requirement. Respectfully, Chris Selph Project Manager Close Construction, LLC (o) 863-467-0831 ext. 321 (f) 863-763-6337 From: Keith McCully [mailto:kmccully@ircgov.com] Sent: Friday, July 10, 2015 8:47 AM To: Chris Selph Cc: Arjuna Weragoda; Mike Delaney; Terry Southard; Jerry Miller; Chris Rossi Subject: RE: PC SOUTH - RECORD DRAWING SUBMITTAL Chris, We'II add the additional cost to the final change order. Keith Keith McCuIIy, P.E. Stormwater Division 772-226-1562 From: Chris Selph [mailto:chrisselph(acloseconstruction.us] Sent: Wednesday, July 08, 2015 4:34 PM To: Keith McCuIIy Cc: Arjuna Weragoda; Mike Delaney; Terry Southard; Jerry Miller; Chris Rossi Subject: RE: PC SOUTH - RECORD DRAWING SUBMITTAL Keith, The canal pump station was As -Built in October 2014. After the existing As -Built drawings were accepted, Close was given Change Order #5. Our Change Order Proposal did not include any additional As-Builts of the facility. Additional As-Builts will be approximately $450, how would you like to proceed? 1 Respectfully, Chris Selph Project Manager Close Construction, LLC (o) 863-467-0831 ext. 321 (f) 863-763-6337 From: Keith McCully [mailto:kmccully@ircgov.com] Sent: Wednesday, July 08, 2015 11:36 AM To: chrisselph@closeconstruction.us Cc: Arjuna Weragoda; Mike Delaney; Terry Southard; Jerry Miller Subject: PC SOUTH - RECORD DRAWING SUBMITTAL Importance: High Chris, The record drawing surveys don't show the latest improvements at the South Relief Canal pump station (the concrete drive and sidewalk) and it shows the work pad as proposed. It needs to be brought up to date for that location. Also, the entire set of record drawings should be labeled for Pay App 17 (or 18 - see below) and should have a recent July 2015 date. Note that the two survey drawings (C4A and C3) included in your email for Pay Request 17 have "Final Pay App (Jan. 31, 2015)" at the bottom right of the title block. This is different from the signed and sealed submitted record drawings that say "Pay App 14 (Oct. 24, 2014)". We need current final record drawings for all submittals. Per the specifications (Section 01720, 1.4) we also need one digital copy in AutoCad LT format and one .PDF copy. You may want to consider deleting payment for the record drawings from Pay Request 17 so it doesn't hold up payment. Thanks, Keith Keith McCully, P.E. Stormwater Division 772-226-1562 2