HomeMy WebLinkAbout2003-182 7 a �
SECTION 00450
CHANGE ORDER FORM
CHANGE ORDER NO . 02
DATE : July 9 , 2003 CONTRACTOR : Tri-Sure Corporation
OWNER : INDIAN RIVER COUNTY AGREEMENT DATE : February 4 , 2003
PROJECT NAME : 16" Sewage Force Main on Old Dixie Highawy from 49th Street to No
County WWTP & 53 � Street Easement from Old Dixie Highway West & South to Central
County WWTP
The following changes are hereby made :
1 ) Construct 1700 linear feet of 6" PVC Force Main 2-6" MJ Gate Valves and 2-6" MJ Plugs
Original CONTRACT PRICE ( LABOR ONLY) $ 1 , 272 , 782 . 00
Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER $ 1 , 198 , 277 . 25
Net Increase (Decrease ) Resulting from this CHANGE ORDER $ 26 , 500 . 00
The current CONTRACT PRICE including this CHANGE ORDER $ 192249777 . 25
ORIGINAL CONTRACT TIME : 180 days No . Days 180
Current CONTRACT TIME adjusted by previous CHANGE ORDER No . Days N/A
Net Increase ( Decrease ) Resulting from this CHANGE ORDER No . Days N/A
Current CONTRACT TIME Including this CHANGE ORDER No . Days 180
CHANGES ORDERED :
I . GENERAL
This change order is necessary to cover changes in the work to be performed under this
Contract . The ANNUAL LABOR CONTRACT AND SPECIFICATIONS apply to and
govern all work under this change order.
II . REQUIRED CHANGES
Add construction of Bent Pine 6 " force main to redirect sewage to 58th Avenue
III . JUSTIFICATION
To allow existing 8" force main along Lateral " H" to be converted to a reuse main
Funds for the project have been approved by the BCC from the Utilities Department Capital Projects Fund
Account No . 472 - 169000- 02526 . 00
Attachment 3
00450 - - 1 -
m
Change Order For
F:\Utilities\UTILITY - ENGINEERING\Projects - Utility Construction Permits\North County R.O. Brine Disposal Relocation UCP 112208\Attachment 3 - 00450
- Change Order No. 2 to Bid No.
5034. doc
IV. WAIVER
This Change Order constitutes full and mutual accord and satisfaction for the adjustment
in contract price or time as a result of increases or decreases in costs and/or time of
performance caused directly and indirectly from the change .
This Change Order represents an equitable adjustment to the contract and
CONTRACTOR hereby waives all rights to file a claim on this Change Order after it is
properly executed .
V . APPROVAL AND CHANGE AUTHORIZATION
Acknowledgements :
The aforementioned change , and work affected thereby, is subject to all provisions of the
original contract not specifically changed by this Change Order; and ,
It is expressly understood and agreed that the approval of the Change Order shall have
no effect on the original contract other than matters expressly provided herein .
Change Order Request By: Mike Hotchkiss Department of Utility Services ,
Indian River County, Florida
Change (s ) Ordered By: Mike Hotchkiss
Capital Projects Manager Signature & Date
RECOMMENDED BY: Mike Hotchkiss ACCEPTED BY :
Capital Projects Manager
DEPARTMENT OF UTILITY SERVICES Tri-Sure Corporation , Jason Chambers
Engineer: Mike Hotchkiss Contractor
Capital Projects Manager
By: / 7 -.G3 By:
Signature & Date Signature & Date 7— /J 03
Title : Capital Projects Manager Title : Vice President
APPROVED BY:
INDIAN RIVER COUNTY BOARD OF COUNTY COMMISSIONERS
Owner
By:
"Kenneth R . acht zz
Chairman
* * END OF SECTION
00450 2 -
Change Order Fotm
F: \Utilities\UTILITY - ENGINEER17N&Projects - Utility Construction Permits\North County R . Brine Disposal Relocation UCP #2208\Attachment 3 -
00450 - Change Order No. 2 to Bid No.
5034.doc