HomeMy WebLinkAbout2004-132 _ 4 INDIAN RIVER COUNTY, FLORIDA
CHANGE ORDER NO . 3 l -�
PROJECT NO , 0378
PROJECT : 26th Street Bridge Replacement Over Range Line Canal (74th Avenue)
CONTRACTOR NAME/ADDRESS : Sheltra & Son Construction Company, Inc .
PO Box 336
Indiantown, FL 34956
DATE : May 25 , 2004
ITEM DESCRIPTION OF PRICE PRICE
NO , CHANGE INCREASE DECREASE
1 Miscellaneous drainage N. T . E . $ 55000 . 00
modifications to be done on time and (estimate)
materials basis
2 Offset existing 8 " PVC water main $ 5 ,260 . 00
around Structure S -6 with PVC pipe
and relocate existing fire hydrant
3 Offset existing 16 " water main under $ 9 , 050 . 00
proposed 18 " RCP pipe with DI
fittings & PVC pipe ,
4 Offset under proposed 18 " RCP and $ 379920 . 00
install new 16" C900 PVC reuse
main, pipe and fittings (640 LF @
$ 59 . 25/LF)
Total Increase/Decrease $ 57 ,230 . 00 0
NET CHANGE IN AMOUNT (+) $579230 . 00
ORIGINAL CONTRACT PRICE $ 1 , 128 ,084 . 15 TIME 120 DAYS
BEGIN DATE 2/ 16/04
DATE OF SUBSTANTIAL COMPLETION 6/ 16/04
DATE OF FINAL COMPLETION 7/ 17/04
CHANGE ORDER NO . 1 (-)$ 99603 . 00 44 DAYS
CHANGE ORDER NO . 2 (+) $ 1224400 . 00 10 DAYS
CURRENT CONTRACT PRICE $ 1 ,240 , 881 . 15 TIME 174 DAYS
NET CHANGE PRICE/TIME FROM THIS CHANGE ORDER NO . 3 (+) $ 57 , 230 . 00 8 DAYS
NEW CONTRACT PRICE/TIME INCLUDING THIS CHANGE ORDER $ 1 ,298 , 111 . 15 182 DAYS
DATE OF SUBSTANTIAL COMPLETION 8/ 18/04
DATE OF FINAL COMPLETION 9/ 18/04
FAEngineering\Capital Projects\0378-26th Street Bridge\0378 CO #3 -Sheltra-05-25-04-cjk.doc
Page 1 of 2
INDIAN RIVER COUNTY, FLORIDA
CHANGE ORDER NO. 3
PROJECT NO. 0378
APPROVAL
ENGINEERS RECOMMENDATION:
I have examined the above changes . They are necessary to satisfactorily complete the Contract . The price changes
are reasonable a I re mmend that the changes be made .
00
stopher afer r. , Dat
County Ei1gineer
I agree to the amendment of the 26th Street Bridge Contract as indicated on the attached ( 1 ) one page Change Order
No . 3 . This Change Order shall become a part of the 26th Street Bridge Contract and incorporated therein.
SHELTRA & SON CONTRACTORS , INC . INDIAN RIVER COUNTY, FLORIDA
(Narne and CDrp
of Signatory) (! Caroline D . Ginn, ChairmJK Sec
Witnessed by: Approved by BCC June 8 2004
QAttest :
Jeffrey K. Barton, (jerk of Circuit Court
3 ,
ounty Attorney
? 'lfy Clerk
Approved as to Form and Legal Sufficiency '
L
eph A Baird,
ounty Administrator
F :\Engineering\Capital Projects\0378-26th Street Bridge\0378 CO #3-Sheltra-05-25-04-cjk.doc
Page 2 of 2