WORK AUTHORIZATION DIRECTIVE l N ' /
No . 2001 -062
TROPIC GROVES GALVANIZED WATER MAIN , SERVICES & METERS REPLACEMENT
PROJECT
DATE OF ISSUANCE : JUNE 30. 2003 EFFECTIVE DATE : JUNE 30 . 2003
OWNER: Indian River County
CONTRACTOR. Georgie E . French
CONTRACT : WATER SEWER AND RECLAIM WATER LINE REPLACEMENT / EXTENSIONS
AND MISCELLANEOUS LABOR CONTRACT UCP #909 BID NO . 3032 Renewed April 1 2003
PROJECT : TROPIC GROVES GALVANIZED WATER MAIN SERVICES & METERS REPLACEMENT
PROJECT
COUNTY UTILITY PROJECT NO . : UCP #2322 CONTRACTOR ' S PROJECT NO . : N/A
COUNTY W .I.P . No . 471 - 169000-02524 . 00
You are directed to proceed promptly with the following work:
Description:
Replace 1000 feet of 6" water main, 300 feet of 4" water main, 22 service lines and 93 meters
Purpose of Work Authorization Directive :
The construction will eliminate pressure and supply problems the customers are having with their water services
Attachments : (List documents supporting work)
Attachment A Exhibit showing location of work
Method of determining Contract Price :
❑ Unit Prices : Bid Items as established pursuant to Bid No . 3032 , and awarded by the Board of County
Commissioners on January 7, 2001 to George E . French; renewed April 1 , 2003 for one year
❑ Lump Sum
❑ Cost of the Work
The Cost of Labor, Contingency and Contract Time is summarized below:
Estimated Labor Cost = $ 1405329 . 00 Estimated Contract Time : 45 da s
Contingency at 10% = $ 14, 033 . 00
Total Estimated Labor Costs = $ 154, 362 . 00
ACCEPTED : RECO MEND 4COY,
By( B
CONT CTOR ENGINEER HAIRMAN
7 Kenneth R . Macht
Date : oe Date : Date : 07 / 07 ;' 2003
Attachment 2
F:\Utilities\UTILITY - ENGINEERING\Projects • Utility Construction Permits\IRC - Tropic Groves Galvanized Water Main-Services-Meters
Replacement UCP #2322\Work Authorization No. 2001 -062 .doc9