• Project Description
The Central Regional Wastewater Treatment Plant (CRWWTP) is located in Central Indian
River County at 3550 49`h Street north of Lindsey Road in Gifford, Florida. The CRWWTP was
designed by CDM as an advanced wastewater treatment plant with a permitted capacity of 2
million gallons per day (gpd) . However, County staff has been operating the existing plant using
the extended aeration mode of operation since biological removal of nitrogen and phosphorous is
not necessary at this time due to effluent disposal utilizing golf course irrigation. Indian River
County is seeking to increase the permitted wastewater treatment capacity to 4 MGD in order to
accommodate future wastewater flows . Based on discussions with County staff, the 4 MGD
plant will still operated based on the extended aeration mode of operation. This proposal is for
preliminary design, final design, preparation of Construction Plans, specifications, and bid
documents, permitting, bidding services, and services during project construction.
1
Indian River County has contracted separately with another consultant for the design of the
adjacent sludge handling facilities and the CRWWTP anoxic zone odor control improvements .
Since time is of the essence, Masteller & Moler, Inc . and its sub-consultants intend to initiate the
design and preparation of Construction Plans for various treatment components, simultaneously
with the preparation of the Preliminary Engineering Design Report. Also, plan preparation fees
and schedules contained in this proposal are based on Indian River CoLmt providing Masteller
& Moler, Inc. with the CDM As-Built Plans with electronic copies of existing plant plans in
Autocad Format.
In order to execute this project in the most cost effective manner with the most aggressive
schedule, Masteller & Moler, Inc . is using the following sub-consultants :
• Masteller, Moler & Reed, Inc . for the As-Built Survey of the existing facilities .
• Dunkelberger Engineering and Testing, Inc. for soil boring and testing information.
• Jenkins & Charland for structural engineering services.
• Bailey Engineering or Garrison Engineering for electrical design and instrumentation.
1 of 7
Work Authorization #3
09/03/03
Page 2
• Scope of Services
Masteller & Moler, Inc . will provide services either directly or by way of sub-contractors for the
expansion and improvements to the CRWWTP from 2 MGD to 4 MGD . In general, these
services shall include preparation of a Preliminary Engineering Report based on treatment using
the extended aeration mode ; engineering design and preparation of Construction Plans;
preparation and submittal of permitting applications ; preparation of specifications and bid
documents; assistance during bidding and contract award; services during construction including
administration and period field inspection. It is anticipated that the expanded and improved
facilities will generally include the following items :
• Addition of one ( 1 ) mechanical bar screen and one ( 1 ) grit collection system.
• Modification of control elevations at equalization splitter box.
• Addition of two (2) new brush aerators on the existing ditch aeration tanks.
• Addition of two (2) new 70 ' diameter circular clarifiers with return activated sludge
pumps and waste activated sludge pumps to match existing clarifiers.
• Modification of existing waste activate sludge pumps and equip new waste activated
sludge with variable speed drive systems .
• Elimination of existing pneumatic ejectors for scum handling and conveyance and pipe
scum directly to existing plant pumping station.
• Addition of two (2) new traveling bridge automatic backwashing type filters to match
existing filters .
• Addition of two (2) new chlorine contact basins matching and adjacent to existing
chlorine contact basins, including one ( 1 ) additional vertical turbine pump in existing
chamber.
• Addition of a new bulk sodium hypo-chloride system including feed pumps, double
wall tanks, double wall piping and enclosure similar to West WWTP installation.
• Expansion of existing control system with additional I/O cards and software to control
and monitor functions for the proposed expansion equipment.
• Paving and grading modifications as required for new construction.
The estimated construction cost of the project is $ 5 , 500,O0000
2 of 7
' Work Authorization #3
09/03 /03
Page 3
In connection with this project, the County will provide the Engineer with a copy of any
pertinent Preliminary Data or Reports; all available drawings in electronic Autocad format; all
surveys, maps and other documents in the possession of or reasonably available to the County
that are pertinent to the project.
Services not included in this scope of services are listed as follows :
• Excavation for field verification of actual locations of existing underground utilities
and structures . It is requested that Indian River County provide the excavations as
directed by Masteller & Moler, Inc .
• Any services associated with assisting Indian River County in review and evaluation
of patent related disputes, issues, or claims including preparing to serve or serving as a
consultant or witness for Indian River County in litigation, arbitration, public or
private hearings, or other legal or administrative proceedings involving patent related
disputes, issues, or claims .
• Services associated with design of additional aeration basins.
• Any services in connection with the project not otherwise provided for in this scope of
services.
• Method and Amount of Compensation
Masteller & Moler, Inc. proposes to provide the above Scope of Services based on the following
lump sum fees :
Task 1 . Preliminary Engineering Report; preparation of Construction
Plans ; preparation and submittal of Permitting Applications; and
preparation of Specifications and Bid Documents utilizing
Standard IRC Bid Documents, Forms, Documents and
Drawings will be in electronic Format MS Word and
Autocad Release 2000 or Later $2339230 . 00
Task 2 . Assistance during Bidding, Bid Evaluation, Contract
Award and Construction Administration and Periodic
Administration and Periodic Construction /Field
Inspection $ 1929895 . 00
Task 3 . Printing and Reproduction Estimated Cost Based on
Schedule below $ 59000 . 00
3 of 7
Work Authorization #3
09/03 /03
Page 4
• Printing and Reproduction
The County shall make direct payment to our office for the cost of printing project plan sheets
required for utility coordination and for copies of reports, drawings, specifications, bidding and
construction contract documents, and other pertinent items required by federal, state and local
agencies from whom approval of the project must be obtained, prospective bidders, material
suppliers, and other interested parties, but may charge only for the actual cost of providing such
copies based on the following tabulation:
8 - 1 /2 " x 11 " $ 0 . 25/sheet blue line prints $ 0 . 333 /SF
11 " x 17" $ 0 . 50/sheet reproducible sepias $ 0. 75/SF
3Y2" diskette $ 5 . 00/ea. reproducible mylars $ 4 . 40/SF
CD $ 10 . 00/ea.
• Time of Performance
The estimated time frame for completion of services from the approval of this Work
Authorization is as follows :
1 . Engineering Design & Preparation of Construction
Plans, Specifications and Bid Documents 5 Months
2 . Submittal of Permit Applications, Bidding, Contract 3 Months
Award and Receipt of Permits
3 . Project Construction 15 Months
File #0325(workauth#3_rev.090303 .doc)
4 of 7
Work Authorization #3
09/03/03
Page 5
IN WITNESS WHEREOF the parties have executed these presents this 9th day of September , 2003 .
BOARD OF COUNTY COMMISSIONERS
INDIAN RIVER COUNTY, FLORIDA
BY: B14 111f
Y
enneth R. Nhacht
Board of County Commissioners
Title: tP4 j? 4 2 ;11A Approved by the BCC : 09 - 09 - 2003
(If not PRESIDENT, attach evidence of authority of sign.)
.,
WITNESS : Zzu A *
WITNESS : �/z ocl / ATTEST:
Jeffrey K. Barton
Clerk of t"he Co
BY: xoe
9he C.r.�. " ' ` `
DEPUTY CLERK OF COURT
Z:
JAMES E. CHANbLER
COUNTY ADMINISTRATOR
WILLIAM G. COLLINS, II
COUNTY ATTORNEY
5 of 7
INDIAN RIVER COUNTY LUMP SUM FEE TABULATION 7/1 /03
CENTRAL REGIONAL WASTEWATER TREATMENT PLANT EXPANSION FROM 2.0 MGD TO 4.0 MGD
PRELIMINARY ENGINEERING REPORTIPREPARATION OF CONSTRUCTION PLANS & PERMITTING
APPLICATIONS/PREPARTION OF SPECIFICATIONS AND BID DOCUMENTS
Professional En ineer Project Engineer E. I . Designer CAD Administration
$ 135.00 $ 100.00 $ 70. 00 $ 40.00 Total
Hours Amount Hours Amount Hours Amount Hours Amount Costs
Preliminary Design 125 $ 16, 875.00 38 $ 3, 800. 00 20 $ 11400. 00 80 $ 31200. 00 $ 25 , 275. 00
Report
Civil/Mechanical 170 $ 22 , 950. 00 40 $ 41000. 00 960 $ 67, 200. 00 40 $ 10600. 00 $ 95 , 750. 00
Preparation of Construction
Plans, Progress Reviews
Preparation & 40 $ 51400.00 75 $ 71500.00 20 $ 11400 . 00 80 $ 3,200.00 $ 17,500. 00
Acquisition of Permits
Prepare Specifications, 40 $ 5,400. 00 20 $ 20000. 00 10 $ 700. 00 120 $ 41800. 00 $ 12,900 . 00
Bid Documents, and
Cost Estimate
Total (hrs/cost) 188 $ 50,625.00 173 $ 17 ,300. 00 1010 $ 70 ,700. 00 320 $ 12, 800. 00 $ 151 ,425 . 00
SUBCONSULTANTS :
1 . Surveying $ 4,025. 00
2. Soil Boring/Testing $ 5, 330 . 00
3. Structural $ 20, 700. 00
4. Electrical/Instrumentation $ 51 , 750. 00
File 0325LA Total $ 233,230 . 00
Sched_manhours.xls
(Design_Services) Page 6 of 7
LUMP SUM FEE TABULATION 7/1 /03
INDIAN RIVER COUNTY
CENTRAL REGIONAL WASTEWATER TREATMENT PLANT EXPANSION FROM 2.0 MGD TO 4.0 MGD
ASSISTANCE DURING BIDDING AND CONTRACT AWARD
CONTRACT ADMINISTRATION/PERIODIC CONSTRUCTION OBSERVATION
Professional Engineer Project Inspector Administration
$ 135.00 $ 60.00 $ 40.00 Total
Hours Amount Hours Amount Hours Amount Costs
Assistance during 60 $ 81100.00 $ - 80 $ 31200.00 $ 11 ,300.00
Bidding & Contract
Award
Contract Administration 120 $ 169200.00 120 $ 7,200.00 300 $ 12,000.00 $ 35,400.00 "
Periodic Construction 300 $ 400500. 00 1200 $ 72,000.00 $ $ 112, 500.00
Observation
Total (hrstoost) 480 $ 64,800.00 1320 $ 79,200.00 380 $ 151200.00 $ 159,200.00
SUBCONSULTANTS :
1 . Structural $ 101925.00 "
2. Electrical/lnstrumentation $ 22,770.00
Note: Total $ 192,895.00
" Includes review of shop drawings & Construction Period
estimated at ( 15) months.
File 0325LA
Sched_manhoursAs