HomeMy WebLinkAbout2007-347 lfS3
SECTION 00530 - EJCDC
STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
ON THE BASIS OF A STIPULATED PRICE
THIS AGREEMENT, dated the Ill day of (ZtC)beC in the year 2007 by and
between Indian River County, a political subdivision of the State of Florida (hereinafter called
OWNER) and Giannefti Contracting Corporation (hereinafter
called CONTRACTOR).
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth ,
agree as follows:
ARTICLE 1 . WORK
CONTRACTOR shall complete all work as specified or indicated in the Contract Documents. The
work is generally described as follows:
The Contractor shall furnish all labor and materials necessary to construct a new forcemain
and a new watermain along the entire length of the Wabasso Causeway (CR 510). This
construction shall include but may not be limited to all associated tie-ins , piping , valves,
fittings , hydrants, pigging , flushing , site restoration , hauling and disposal of drilling fluids
and cuttings , pressure testing of all piping , bacteriological clearance of the watermain , and
maintenance of traffic in accordance with FDOT standards, as depicted on the drawings
and described in these documents and referenced materials.
The portions of the existing watermain and forcemain parallel to the four causeway bridges
shall be replaced with subaqueous installations. The method the construction of these eight
subaqueous pipe installations shall be horizontal directional drill (HDD ) with 14-inch HDPE
piping . The entire length of all HDD installations is approximately 12 ,610- LF, and shall be
wire line tracked .
The pipe construction between the HDD installations includes approximately 1340-LF of 12-
inch PVC, 500-LF of 8-inch piping , 125-LF 4-inch piping and shall be constructed with a
combination of dig and bury and HDD as depicted on the drawings, in addition to various
segments of smaller pipe necessary to maintain service along this section to the water and
wastewater systems.
CONTRACTOR, as an independent contractor and not as an employee, shall furnish , for the sum
amount of $2,378.000.00 , all of the necessary labor, material , and equipment to perform the
work described above in accordance with the Contract Documents.
ARTICLE 2. ENGINEER
044572007
00530- 1
The project has been designed by Kimley-Hom and Associates, Inc. , hereinafter called
ENGINEER, and who is to act as OWNER'S representative, assume all duties and responsibilities
and have the rights and authority assigned to ENGINEER in the Contract Documents in
connection with completion of the work in accordance with the Contract Documents.
ARTICLE 3. CONTRACT TIME .
3 . 1 The work will be completed in accordance with the following time frame.
(a) Within 180 calendar days from the effective date of Notice to Proceed , the
CONTRACTOR shall complete the following tasks:
1 . Install all pipes , valves, and appurtenant items.
3 . Perform all testing .
4 . Provide a system to the OWNER which is of beneficial use and allows the
OWNER to provide utility service to their customers with normal
operations .
Completion of all tasks outlined above (i .e. , Subparagraphs a ) constitute Substantial
Completion .
(b) From 181 calendar days to 210 calendar days from the effective date of Notice
to Proceed , the CONTRACTOR shall complete the following tasks :
1 . Clean up project area .
2 . Restore all disturbed areas to their pre-construction condition .
3. Correct all deficiencies noted by Engineer.
4. Remove all equipment and material from project site .
5. Perform contract close-out procedures.
Completion of all tasks outlined above (i .e. , Subparagraphs a and b ) constitute Final
Completion .
3.2 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the
essence of this Agreement and that OWNER will suffer financial loss if the work is not
completed within the times specified in Paragraph 3. 1 above, plus any extensions
thereof allowed in accordance with Article 12 of the General Conditions. They also
recognize the delays , expense and difficulties involved in proving in a legal proceeding
the actual loss suffered by OWNER if the work is not completed on time . Accordingly,
instead of requiring any such proof, OWNER and CONTRACTOR agree that as
liquidated damages for delay ( but not as a penalty) CONTRACTOR shall pay OWNER
three hundred and fifty dollars ($350. 00) for each day that expires after the time
specified in Paragraph 3. 1 for Substantial Completion, if CONTRACTOR shall neglect,
refuse or fail to complete the remaining work within the Contract Time or any proper
extension thereof granted by OWNER, CONTRACTOR shall pay OWNER three
hundred and fifty dollars ($350 .00) for each day that expires after the time specified in
Paragraph 3. 1 for completion and readiness for final payment.
044572007
00530-2
3. 3 In addition to the above-stated liquidated damages , the CONTRACTOR shall be
responsible for reimbursing OWNER for all costs incurred by OWNER to third party
consultants including , without limiting the generality of the foregoing , any
ENGINEER in administering the construction of the Project beyond the Substantial
Completion date as specified in the Contract or beyond an approved extension of
time granted to CONTRACTOR, whichever date is later.
ARTICLE 4, CONTRACT PRICE,
4 . 1 OWNER shall pay CONTRACTOR for completion of the work in accordance with the
Contract Documents in current funds in the amount of $ 2,378,000.00
ARTICLE 5. PAYMENT PROCEDURES.
CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the
General Conditions. Applications for Payment will be processed by ENGINEER as
provided in the General Conditions.
5. 1 Progress Payments . The OWNER shall make progress payments to the
CONTRACTOR on the basis of the approved partial payment request as
recommended by ENGINEER in accordance with the provisions of the Local
Government Prompt Payment Act , Florida Statutes section 218. 70 et. seq . The
OWNER shall retain ten percent ( 10% ) of the payment amounts due to the
CONTRACTOR until fifty percent (50% ) completion of the work. After fifty
percent (50% ) completion of the work is attained as certified to OWNER by
ENGINEER in writing , OWNER shall retain five percent (5% ) of the payment
amount due to CONTRACTOR until final completion and acceptance of all work
to be performed by CONTRACTOR under the Contract Documents . Pursuant to
Florida Statutes section 218. 735(8)( b ), fifty percent (50% ) completion means the
point at which the County as OWNER has expended fifty percent (50% ) of the
total cost of the construction services work purchased under the Contract
Documents, together with all costs associated with existing change orders and
other additions or modifications to the construction services work provided under
the Contract Documents.
5. 2 Pay Requests . Each request for a progress payment shall be submitted on the
application for payment form supplied by OWNER and the application for
payment shall contain the CONTRACTOR's certification . All progress payments
will be on the basis of progress of the work measured by the schedule of values
established , or in the case of unit price work based on the number of units
completed . After fifty percent (50%) completion , and pursuant to Florida
Statutes section 218.735(8)(d ), the CONTRACTOR may submit a pay request to
the County as OWNER for up to one half ( 1 /2) of the retainage held by the
County as OWNER , and the County as OWNER shall promptly make payment to
the CONTRACTOR unless such amounts are the subject of a good faith dispute;
the subject of a claim pursuant to Florida Statutes section 255. 05(2005) ; or
044572007
00530-3
otherwise the subject of a claim or demand by the County as OWNER or the
CONTRACTOR. The CONTRACTOR acknowledges that where such retainage
is attributable to the labor, services, or materials supplied by one or more
subcontractors or suppliers, the Contractor shall timely remit payment of such
retainage to those subcontractors and suppliers . Pursuant to Florida Statutes
section 218.735(8 )(c)(2005) , CONTRACTOR further acknowledges and agrees
that: 1 ) the County as OWNER shall receive immediate written notice of all
decisions made by CONTRACTOR to withhold retainage on any subcontractor at
greater than five percent (5%) after fifty percent (50% ) completion ; and 2)
CONTRACTOR will not seek release from the County as OWNER of the
withheld retainage until the final pay request.
5. 3 Paragraphs 5. 1 . 1 and 5.2 do not apply to construction services work purchased
by the County as OWNER which are paid for, in whole or in part, with federal
funds and are subject to federal grantor laws and regulations or requirements
that are contrary to any provision of the Local Government Prompt Payment Act.
In such event, payment and retainage provisions shall be governed by the
applicable grant requirements and guidelines.
5.4 ACCEPTANCE AND FINAL PAYMENT : Upon receipt of written notice that the
work is ready for final inspection and acceptance , the ENGINEER will promptly
make such inspection and when the ENGINEER finds the work acceptable under
the terms of the Contract and the Contract fully performed , the ENGINEER will
promptly issue a final completion certificate stating that the work provided for in
this Contract has been completed , and acceptance by the OWNER under the
terms and the conditions thereof is recommended and the entire balance found
to be due the CONTRACTOR, will be paid to the CONTRACTOR by the
OWNER following County Commission approval of the final Contract payment .
ARTICLE 6, INTEREST.
Not Applicable .
ARTICLE 7. CONTRACTOR'S REPRESENTATIONS .
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following
representations:
7. 1 CONTRACTOR has familiarized itself with the nature and extent of the Contract
Documents, work, site, locality, and all local conditions and laws and regulations
that in any manner may affect cost, progress, performance or furnishing of the
work.
7.2 CONTRACTOR has studied carefully all reports of explorations and tests of
subsurface conditions and drawings of physical conditions which are identified in
the Supplementary Conditions as provided in Paragraph 4.02 of the General
Conditions, and accepts the determination set forth in Paragraph SC-4.02 of the
Supplementary Conditions of the extent of the technical data contained in such
reports and drawings upon which CONTRACTOR is entitled to rely.
044572007
00530-4
7.3 CONTRACTOR has obtained and carefully studied (or assumes responsibility for
obtaining and carefully studying) all such examinations, investigations,
explorations, tests , reports and studies (in addition to or to supplement those
referred to in Paragraph 7.2 above) which pertain to the subsurface or physical
conditions at or contiguous to the site or otherwise may affect the cost, progress ,
performance or furnishing of the work as CONTRACTOR considers necessary for
the performance of furnishing of the work at the Contract Price, within the Contract
Time and in accordance with the other terms and conditions of the Contract
Documents, including specifically the provisions of Paragraph 4 .02 of the General
Conditions; and no additional examinations, investigations, explorations, tests,
reports, studies or similar information or data are or will be required by
CONTRACTOR for such purposes.
7 .4 CONTRACTOR has reviewed and checked all information and data shown or
indicated on the Contract Documents with respect to existing underground facilities
at or contiguous to the site and assumes responsibility for the accurate location of
said underground facilities. No additional examinations, investigations ,
explorations , tests , reports, studies or similar information or data in respect of said
underground facilities are or will be required by CONTRACTOR in order to perform
and furnish the work at the Contract Price, within the Contract Time and in
accordance with the other terms and conditions of the Contract Documents,
including specifically the provisions of Paragraph 4 .03 of the General Conditions.
7 .5 CONTRACTOR has correlated the results of all such observations, examinations ,
investigations, explorations , tests , reports and studies with the terms and
conditions of the Contract Documents.
7 .6 CONTRACTOR has given ENGINEER written notice of all conflicts, errors or
discrepancies that he has is covered in the Contract Documents and the written
resolution thereof by ENGINEER is acceptable to CONTRACTOR.
ARTICLE 8. CONTRACT DOCUMENTS.
The Contract Documents which comprise the entire agreement between OWNER and
CONTRACTOR concerning the work consist of the following :
8. 1 This Agreement (Section 00530).
8.2 Performance and other bonds (Sections 00610 and 00620) .
8.3 Notice of Award and Notice to Proceed.
8 .4 General Conditions (Section 00700).
8.5 Supplementary Conditions (Section 00800).
8.6 Technical Specifications as listed herein the table of contents of these documents.
044572007
00530-5
8.7 Drawings consisting of a coversheet and sheets 2 through 16, inclusive, with each
bearing the title Wabasso Causeway (CR 510) Watermain and Forcemain
Replacement in Indian River County.
8.8 Addenda numbers 0 to 1 inclusive.
8.9 CONTRACTOR'S Bid Form (Section 00310).
8. 10 The following , which may be delivered or issued after the effective date of the
Agreement and are not attached hereto: All written amendments and other
documents amending , modifying , or supplementing the Contract Documents
pursuant to Paragraph 3 .04 of the General Conditions.
8. 11 Specifications bearing the title " IRCDUS Water and Wastewater Utility
Standards , October 2006" , or the latest version thereof.
There are no Contract Documents other than those listed above in this Article 8. The Contract
Documents may only be amended, modified or supplemented as provided in Paragraph 3 .04 of
the General Conditions.
ARTICLE 9. MISCELLANEOUS
9. 1 Terms used in this Agreement which are defined in Article 1 of the General
Conditions will have the meanings indicated in the General Conditions .
9. 2 No assignment by a party hereto of any rights under or interests in the Contract
Documents will be binding on another party hereto without the written consent of
the party sought to be bound .
9. 3 OWNER and CONTRACTOR each binds itself, its partners, successors, assigns
and legal representatives to the other party hereto , its partners, successors,
assigns and legal representatives in respect of all covenants, agreements and
obligations contained in the Contract Documents.
9.4 THE CONTRACTOR SHALL BE PROPERLY LICENSED TO PRACTICE ITS
TRADE OR TRADES WHICH ARE INVOLVED IN THE COMPLETION OF THIS
AGREEMENT AND THE WORK THEREUNDER.
9. 5 This agreement shall be governed by the laws of the State of Florida . Venue for
any lawsuit brought by either party against the other party or otherwise arising out
of this agreement shall be in Indian River County, Florida, or, in the event of
federal jurisdiction , in the United States District Court for the Southern District of
Florida .
9.6 CONTRACTOR agrees to indemnify and hold harmless the OWNER, together with
its agents, employees, elected officers and representatives, from liabilities,
damages, losses, and costs, including but not limited to, reasonable attorney's
fees, to the extent caused by the negligence , recklessness or intentional wrongful
misconduct of the CONTRACTOR and persons employed or utilized by the
044572007
00530-6
CONTRACTOR in the performance of the work under this Agreement. This
indemnification and hold harmless provision shall survive the termination or
expiration of this Agreement.
9.7 Pledge of Credit. The CONTRACTOR shall not pledge the OWNER'S credit or
make it a guarantor of payment or surety for any Agreement, debt, obligation,
judgment, lien or any form of indebtedness. The CONTRACTOR further warrants
and represents that it has no obligation or indebtedness that would impair its ability
to fulfill the terms of this Agreement.
9.8 Counterparts. This Agreement may be executed in one or more counterparts, but
all such counterparts, when duly executed , shall constitute one and the same
Agreement.
9 .9 Public Records. The OWNER and the CONTRACTOR shall comply with the
provisions of Chapter 119 , Florida Statutes (Public Records Law) in connection
with this Agreement.
Article 10 . OTHER PROVISIONS.
IN WITNESS WHEREOF, OWNER AND CONTRACTOR have signed this Agreement in
triplicate . One counterpart each has been delivered to OWNER, CONTRACTOR, and
ENGINEER. All portions of the Contract Documents have been signed or identified by OWNER
and CONTRACTOR or by ENGINEER on their behalf.
OWNER: CONTRACTOR:
Indian River County Con,r2AC7r, ljt. lo (zp_
Board of CourA Commissioners
BY BY
` GEpyC. Wheeler, Chairman 2 �K G >aNNE
" p ( O OSEAL)
Attesf: Attest:
J . K. Barrtto�nvCferk of the Circuit Court ev, A o oL
By: zn �c.
Deputy Clerk
A proved By:
Al
seph AlBaird , County Admini trator
Approved as to Form and Legal Sufficiency:
unty Attorney
044572007
00530-7
Address for giving notices Address for giving notices
1840 25'" Street Vero Beach, FL 32960 6340 Sims Dr.
Sterling Hts. , MI
License No.CVC 056976 , CBC 057979
Agent for service of process :
R. Giannetti
END OF SECTION
044572007
00530-8