HomeMy WebLinkAbout2007-063SECTION 00530 - EJCDC
STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
ON THE BASIS OF A STIPULATED PRICE
THIS AGREEMENT, dated the _day of in the yearbza:-by and
between Indian River County, a political subdivision of the State M Florida (hereinafter called
OWNER) and SPS CnntractinA, Inc. of Vern Rea -h, Flnrida (hereinafter called
CONTRACTOR).
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth,
agree as follows:
ARTICLE 1. WORK
CONTRACTOR shall complete all work as specified or indicated in the Contract Documents. The
work is generally described as follows:
Phase II Force Main West Wastewater Transmission System, Bid No. 2007-029
Furnish all labor, equipment, and materials necessary to construct approximately
10,205-1-F of 24 -inch forcemain including, but not necessarily limited to, a total of 2530 -
LF horizontal directional drill at three (3) locations, all fittings, pipe, appurtenances,
clearing, restoration, and all testing as shown on the drawings and as depicted in these
documents.
CONTRACTOR, as an independent contractor and not as an employee, shall furnish, for the sum
amount of $3,341,598 as, all of the necessary labor, material, and equipment to perform the work
described above in accordance with the Contract Documents.
ARTICLE 2. ENGINEER
The project has been designed by Kimley-Horn and Associates, Inc., hereinafter called
ENGINEER, and who is to act as OWNER'S representative, assume all duties and responsibilities
and have the rights and authority assigned to ENGINEER in the Contract Documents in
connection with completion of the work in accordance with the Contract Documents.
ARTICLE 3. CONTRACT TIME.
3.1 The work will be completed in accordance with the following time frame.
(a) Within 210 calendar days from
the
effective
date of Notice to Proceed, the
CONTRACTOR shall complete
the
following
tasks:
1. Construct facility building and pump station.
2. Install all pipes, valves, and appurtenant items.
044572007
00530-1
3. Perform all testing.
4. Provide a system to the OWNER which is of beneficial use and allows the
OWNER to provide utility service to their customers with normal
operations.
Completion of all tasks outlined above (i.e., Subparagraphs a) constitute Siffictantial
Completion.
(b) From 211 calendar days to 244 calendar days from the effective date of Notice
to Proceed, the CONTRACTOR shall complete the following tasks:
1. Clean up project area.
2. Restore all disturbed areas to their pre -construction condition.
3. Correct all deficiencies noted by Engineer.
4. Remove all equipment and material from project site.
5. Perform contract close-out procedures.
Completion of all tasks outlined above (i.e., Subparagraphs a and b) constitute Final
Completion.
3.2 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the
essence of this Agreement and that OWNER will suffer financial loss if the work is not
completed within the times specified in Paragraph 3.1 above, plus any extensions
thereof allowed in accordance with Article 12 of the General Conditions. They also
recognize the delays, expense and difficulties involved in proving in a legal proceeding
the actual loss suffered by OWNER if the work is not completed on time. Accordingly,
instead of requiring any such proof, OWNER and CONTRACTOR agree that as
liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay OWNER
three hundred and fifty dollars ($350.00) for each day that expires after the time
specified in Paragraph 3.1 for Substantial Completion, if CONTRACTOR shall neglect,
refuse or fail to complete the remaining work within the Contract Time or any proper
extension thereof granted by OWNER, CONTRACTOR shall pay OWNER three
hundred and fifty dollars ($350.00) for each day that expires after the time specified in
Paragraph. 3.1 for completion and readiness for final payment.
3.3 In addition to the above -stated liquidated damages, the CONTRACTOR shall be
responsible for reimbursing OWNER for all costs incurred by OWNER to third party
consultants including, without limiting the generality of the foregoing, any
ENGINEER in administering the construction of the Project beyond the Substantial
Completion date as specified in the Contract or beyond an approved extension of
time granted to CONTRACTOR, whichever date is later.
ARTICLE 4. CONTRACT PRICE.
4.1 OWNER shall pay
CONTRACTOR
for
completion
of the work in accordance with the
Contract Documents in
current funds in
the
amount of
$3,341,598AE.
044572007
00530-2
ARTICLE 5. PAYMENT PROCEDURES.
CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the
General Conditions. Applications for Payment will be processed by ENGINEER as
provided in the General Conditions.
5.1 Progress Payments. OWNER shall make progress payments on account of the
Contract Price on the basis of CONTRACTOR'S Applications for Payment as
recommended by ENGINEER, on or about the 30th day of each month during
construction as provided below. All progress payments will be on the basis of the
progress of the work measured by the schedule of values established in Paragraph
2.07 of the General Conditions (and in the case of Unit Price Work based on the
number of units completed), or, in the event there is no schedule of values, as
provided in the General Requirements.
5.2 Final payment. Upon final completion and acceptance of the work in accordance
with Paragraph 14.07 of the General Conditions, OWNER shall pay the remainder
of the Contract Price as recommended by ENGINEER as provided in said
Paragraph 14.07.
ARTICLE 6. INTEREST.
Not Applicable.
ARTICLE 7. CONTRACTOR'S REPRESENTATIONS.
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following
representations:
7.1 CONTRACTOR has familiarized itself with the nature and extent of the Contract
Documents, work, site, locality, and all local conditions and laws and regulations
that in any manner may affect cost, progress, performance or furnishing of the
work.
7.2 CONTRACTOR has studied carefully all reports of explorations and tests of
subsurface conditions and drawings of physical conditions which are identified in
the Supplementary Conditions as provided in Paragraph 4.02 of the General
Conditions, and accepts the determination set forth in Paragraph SC -4.02 of the
Supplementary Conditions of the extent of the technical data contained in such
reports and drawings upon which CONTRACTOR is entitled to rely.
7.3 CONTRACTOR has obtained and carefully studied (or assumes responsibility for
obtaining and carefully studying) all such examinations, investigations,
explorations, tests, reports and studies (in addition to or to supplement those
referred to in Paragraph 7.2 above) which pertain to the subsurface or physical
conditions at or contiguous to the site or otherwise may affect the cost, progress,
performance or furnishing of the work as CONTRACTOR considers necessary for
the performance of furnishing of the work at the Contract Price, within the Contract
Time and in accordance with the other terms and conditions of the Contract
044572007
00530-3
Documents, including specifically the provisions of Paragraph 4.02 of the General
Conditions; and no additional examinations, investigations, explorations, tests,
reports, studies or similar information or data are or will be required by
CONTRACTOR for such purposes.
7.4 CONTRACTOR has reviewed and checked all information and data shown or
indicated on the Contract Documents with respect to existing underground facilities
at or contiguous to the site and assumes responsibility for the accurate location of
said underground facilities. No additional examinations, investigations,
explorations, tests, reports, studies or similar information or data in respect of said
underground facilities are or will be required by CONTRACTOR in order to perform
and furnish the work at the Contract Price, within the Contract Time and in
accordance with the other terms and conditions of the Contract Documents,
including specifically the provisions of Paragraph 4.03 of the General Conditions.
7.5 CONTRACTOR has correlated the results of all such observations, examinations,
investigations, explorations, tests, reports and studies with the terms and
conditions of the Contract Documents.
7.6 CONTRACTOR has given ENGINEER written notice of all conflicts, errors or
discrepancies that he has is covered in the Contract Documents and the written
resolution thereof by ENGINEER is acceptable to CONTRACTOR.
ARTICLE 8. CONTRACT DOCUMENTS.
The Contract Documents which
comprise the
entire
agreement between OWNER and
CONTRACTOR concerning the
work consist
of the
following:
8.1 This Agreement (Section 00530).
8.2 Performance and other bonds (Sections 00610 and 00620).
8.3 Notice of Award and Notice to Proceed.
8.4 General Conditions (Section 00700).
8.5 Supplementary Conditions (Section 00800).
8.6 Technical Specifications as listed herein the table of contents of these documents.
8.7 Drawings consisting of a coversheet and sheets 2 through 17, inclusive, with each
bearing the title INDIAN RIVER SUBAQUEOUS UTILITY CROSSINGS ALONG
C.R. 510 BRIDGES.
8.8 Addenda numbers 1 to 5 , inclusive.
8.9 CONTRACTOR'S Bid Form (Section 00310).
8.10 The following, which may be delivered or issued after the effective date of the
Agreement and are not attached hereto: All written amendments and other
044572007
00530-4
documents amending, modifying, or supplementing the Contract Documents
pursuant to Paragraph 3.04 of the General Conditions.
There are no Contract Documents other than those listed above in this Article 8. The Contract
Documents may only be amended, modified or supplemented as provided in Paragraph 3.04 of
the General Conditions.
ARTICLE 9. MISCELLANEOUS
9.1 Terms used in this Agreement which are defined in Article 1 of the General
Conditions will have the meanings indicated in the General Conditions.
9.2 No assignment by a party hereto of any rights under or interests in the Contract
Documents will be binding on another party hereto without the written consent of
the party sought to be bound.
9.3 OWNER and CONTRACTOR each binds itself, its partners, successors, assigns
and legal representatives to the other party hereto, its partners, successors,
assigns and legal representatives in respect of all covenants, agreements and
obligations contained in the Contract Documents.
9.4 THE CONTRACTOR SHALL BE PROPERLY LICENSED TO PRACTICE
ITS TRADE OR TRADES WHICH ARE INVOLVED IN THE COMPLETION OF
THIS AGREEMENT AND THE WORK THEREUNDER.
9.5 This agreement shall be governed by the laws of the State of Florida. Venue for
any lawsuit brought by either party against the other party or otherwise arising out
of this agreement shall be in Indian River County, Florida, or, in the event of
federal jurisdiction, in the United States District Court for the Southern District of
Florida.
9.5 CONTRACTOR agrees to indemnify and hold harmless the OWNER, together with
its agents, employees, elected officers and representatives, from liabilities,
damages, losses, and costs, including but not limited to, reasonable attorney's
fees, to the extent caused by the negligence, recklessness or intentional wrongful
misconduct of the CONTRACTOR and persons employed or utilized by the
CONTRACTOR in the performance of the work under this Agreement. This
indemnification and hold harmless provision shall survive the termination or
expiration of this Agreement.
Article 10. OTHER PROVISIONS.
IN WITNESS WHEREOF, OWNER AND CONTRACTOR have signed this Agreement in
triplicate. One counterpart each has been delivered to OWNER, CONTRACTOR, and
ENGINEER. All portions of the Contract Documents have been signed or identified by OWNER
and CONTRACTOR or by ENGINEER on their behalf.
This Agreement will be effective on
OWNER: CONTRACTOR:
044572007
00530-5
Board of County Commissioners
By
a Wheeler, Chairman
Attest:
J. K. Barton: erk of the Circuit Court
Approved By:
osephf A. Baird, County Administrator
Legal Sufficiency:
BY
L 5.7iY/h� ✓ieE
(CORPORATE SFEAL)
Attest: �, e o 4,
Address for giving notices
License No. CGCO07541
Agent for service of process:
END OF SECTION
044572007
00530-6