Prototype Design/Build Part I Agreement
Project No. 5018.001 .02. 1 .2
Dear Mr. King,
I have reviewed the Part I Design/Build Agreement and the Preliminary Opinion of Probable
Cost for the Construction of Fire Station #2 , as provide to me by Barth Construction on 08/25/05
and revised on 08/31 /05 . Based on this review, to the best of my Professional knowledge and
belief, the Design/Build Part I Agreement appears to be inclusive of the required work and the
Preliminary Opinion of Probable Costs are fair and reasonable based on current construction
market conditions.
If you have any questions regarding the above, please feel free to contact me .
Sincere,
An o J D nadio A. I . A . , NCARB
Presid
609 17th Street Vero Beach, Florida 32960 Phone 772 794 2929 Fax 772 562 8600
Email daa@donadio-arch.com License No. AA0002238
PRELIMINARY OPINION OF PROBABLE COST
Indian River County Fire Station #2
Prepared by Barth Construction 8 . 25 . 05
Revised 8. 31 . 05
I . DESIGN
1 . Barth Construction Design Administration, Estimating $ 309107 . 00
2 , Civil Engineering Part 1 $ 31 , 355 . 00
3 , Civil Engineering Part II $ 179350 . 00
4 . Surveying $ 75800 . 00
5 . Geo-technical included in Civil Engineering
6 . Landscape & Irrigation design $ 7 , 500 . 00
7 , Architectural Fees Part I $ 659347 . 00
8 . Architectural fees Part II $ 905620 . 00
Subtotal $250, 079 . 00
SITEWORK
1 . Demolition $ 205000 . 00
2 . Water & Sewer Upgrades & Connections $ 20, 000 . 00
3 , Electric , Transformer Underground $ 155000 . 00
4 , Fire Service , Backflow Preventer $ 215000 . 00
5 , Site Fill to FEMA Base Elevation Plus 6" $ 95 , 000 . 00
6 . Paving & Drainage $ 759000 . 00
7 , Retaining Wall at North Property Line $ 65 , 000 . 00
8 , Control Burm on South Property Line &
River Bank Stabilization $ 759000 . 00
9 . Landscape & Irrigation $ 60,000 . 00
10 , Concrete Sidewalks $ 89000 . 00
11 . Terracing connection to Dock & Boat Area $ 42 , 000 . 00
12 . Right of Way Connection Improvements $ 59000 . 00
13 , Site Lighting ( 8 Poles @ $2 ,000 . 00 ea) $ 16 , 000 . 00
14 , Pad, Piping, Stand, Electric For Gas L . P . Tank $ 8 ,000 . 00
15 , Repairs To Boat Building and Dock Area $ 20, 000 . 00
16 . Contingency @ 10% $ 55 , 000 . 00
Site Development Budget $ 6009000 . 00
BUILDING Cost/S . F .
1 . Concrete & Block $ 40 . 00
2 , Wood Trusses/Deck $ 7 . 00
3 , Metal Roof/Dry-In $ 9 . 50
4 . Windows/Storefronts $ 2 . 50
5 . Doors (Ext . H . M . ) $ 1 . 50
6 . Roll Up Doors $ 1 . 75
7 . Stucco $ 1 . 85
8 . Shutters $ 1 . 50
9 . Framing/Drywall/Insulation $ 4 . 25
10 , Int. Doors/Frames $ 1 . 25
11 , Wall Finishes $ 4 . 50
12 , Floor Finishes $ 5 . 00
13 , Ceramic Wall Tile $ 1 . 50
14 , Ceiling Finishes $ 2 . 55
15 , Kitchen Cabinets $ 1 . 00
16 , Stainless Tops $ 1 . 50
17 , Shower Units $ 1 . 00
18 . HVAC $ 9 . 00
19 . Plumbing $ 5 . 50
20 , Fire Sprinklers $ 3 . 95
21 . Electrical $ 15 . 00
22 . Generator $ 4 . 50
23 . Gas $ 1 . 50
24 , Kitchen Equipment/Ice Maker/Washer $ 1 . 90
25 , Lockers In Dorms $ 2 . 50
26 , EMS Storage Shelves $ 2 . 50
27 , Toilet Partitions $ 0 . 50
Subtotal $ 135 . 00
General Conditions $ 20 . 00
Overhead & Profit $ 25 . 00
Total $ 180 . 00
Contingency $ 20 . 00
Total $200 . 00
New Building 8 , 936 S . F . @ $200 . 00/S . F . $ 1 , 787 ,200 . 00
Total Preliminary Project Budget $29637 „ 279 . 00
Architect ' s Fees :
Construction Budget $2 , 387,200 . 00 X 6 . 3 %(per DMS Schedule) _ $ 150, 394 . 00
Programming (Hourly) $ 51573 . 00
Total $ 155 , 967 . 00
BARTH
Construction , Inc .
PROGRAMMING & PRECONSTRUCTIONS SERVICES
Project: Indian River County EMS Fire Station # 2 months
Date: 8.24.05 0 wks
Enter months and square footage above, all items on the spreadsheet in yellow will automatically change.
Labor I I Mat I TOTAL
CODE DESCRIPTION QTY UNIT Unit LABOR Unit MATERIALS SUB includes
Cost Cost No Taz S[D
TA t °;,0
Deis n Builder
Design Build Executive Phil Barth 4 Hrs 150 600 0 0 0 600
Estimator/Project manager Jason F k 150 Hrs 100 159000 0 0 0 15000
Superintendent 8 Hrs 75 600 0 0 0 600
Clerical 16 Hrs 45 720 0 0 0 720
Architectural Services 1 LS - 0 0 65347 65347
Strutural Engineer 1 LS - 0 0 0 0
MEP Engmeenng 1 LS 0 0 0 0
Civil Design & Permiting LS - 0 0 , 31355 31355
Landscape & Irrigation Design 1 LS - 0 0 7500 7500
Surveys LS - 0 0 7800 7800
Soil Borings/Foundation Report 1 LS - 0 0 0 0
LS - 0 0 0 0
Forensic Demolition I LS - 0 0 0 0
Document Reproduction/Printing Reproduction/Printing250 ea 01 1 250 0 268
IShipping Is 01 0 1 0 1 0
Miscellaneous
Office Overhead 0 LS 01 0 1 0 1 0
Contin enc 10% total 0 01 0 0 1 1299190 12919
Total 16992 2501 142,10
Station #2
Part I Agreement
8/31 /05
TABLE OF ARTICLES
PART 1 AGREEMENT
1 . DESIGN/BUILDER
2 . OWNER
3 . OWNERSHIP AND USE OF DOCUMENTS AND ELECTRONIC DATA
4. TIME
5 . PAYMENTS
6 . DISPUTE RESOLUTION - MEDIATION AND ARBITRATION
7 . MISCELLANEOUS PROVISIONS
8 . TERMINATION OF THE AGREEMENT
9 . BASIS OF COMPENSATION
10 . OTHER CONDITIONS AND SERVICES
I
THIS AGRENrENT 'm� ort Augts � 96
,, �! tfe t0er Iridian Rtvert
3 ; r
County , political suk�dtuistQn of t� �� , Fltt � 1 �40ths See , Vero B+ ch ;
Florida 32960 and ,the I i r � t` � t r. tl"t i�r r , �171 `� Indian River
Suite 202A , Vero Beath, F1 ' rid10 ,32960
For the following Project :
Design -Build Ran ovet�ons T6 Fire 'S�f ot1 # u r
3301 Bridge Plaza le, In 5
Vero Beach , L29C7r
�;
- s
The architectural services described in Article 1 will be provided by the following person
or entity who is lawfully licensed to practice architecture :
Name and address Registration Relationship to
Number Design/Builder
Edlund -Dritenbas-Bikiey; Architects1 : 00�3n8 1°' rtntractual
& associates .
k }
65 Royal "'Palm Boulev rd Suite` C ,
Vero Beach , FL 32060
.c tsrr
Normal structural , mechanical and electrical engineering services will be provided
contractually through the Architect except as indicated below :
Name , address and discipline Registration Relationship to
Number Design/Builder
N
YrJ
The Owner and the Design/Builder agree as set forth below .
TERMS AND CONDITIONS — PART 1 AGREEMENT
ARTICLE 1 DESIGN/BUILDER
§ 1 . 1 SERVICES
§ 1 . 1 . 1 Preliminary design , budget , and schedule comprise the services required to
accomplish the preparation and submission of the Design/Builder's Proposal as well as
the preparation and submission of any modifications to the Proposal prior to execution
of the Part 2 Agreement .
§ 1 . 2 RESPONSIBILITIES
§ 1 . 2 . 1 Design services required by this Part 1 Agreement shall be performed by
qualified architects and other design professionals . The contractual obligations of such
2
professional persons or entities are undertaken and performed in the interest of the
Design/Builder.
§ 1 . 2 . 2 The agreements between the Design/Builder and the persons or entities
identified in this Part 1 Agreement , and any subsequent modifications , shall be in
writing . These agreements , including financial arrangements with respect to this Project ,
shall be promptly and fully disclosed to the Owner upon request .
§ 1 . 2 . 3 Construction budgets shall be prepared by qualified professionals , cost
estimators or contractors retained by and acting in the interest of the Design/Builder.
§ 1 . 2 . 4 The Design/Builder shall be responsible to the Owner for acts and omissions of
the Design/Builder's employees , subcontractors and their agents and employees , and
other persons , ' , performing any
portion of the Design/Builder's obligations under this Part 1 Agreement .
§ 1 Z If the Design/Builder believes or is advised by the Architect or by another design
professional retained to provide services on the Project that implementation of any
instruction received from the Owner would cause a violation of any applicable law , the
Design/Builder shall notify the Owner in writing . Neither the Design/Builder nor the
Architect shall be obligated to perform any act which either believes will violate any
applicable law .
§ 1 . 2 . 6 Nothing contained in this Part 1 Agreement shall create a contractual
relationship between the Owner and any person or entity other than the Design/Builder .
§ 1 . 3 BASIC SERVICES
§ 1 . 3 . 1 The Design/Builder shall provide a preliminary evaluation of the Owner' s
program and project budget requirements , each in terms of the other .
§ 1 . 3 . 2 The Design/Builder shall visit the site , become familiar with the local conditions ,
and correlate observable conditions with the requirements of the Owner's program ,
schedule , and budget .
§ 1 . 3 . 3 The Design/Builder shall review laws applicable to design and construction of
the Project , correlate such laws with the Owner's program requirements , and advise the
Owner if any program requirement may cause a violation of such laws . Necessary
changes to the Owner's program shall be accomplished by appropriate written
modification or disclosed as described in Section 1 . 3 . 5 .
§ 1 . 3 . 4 The Design/Builder shall review with the Owner alternative approaches to
design and construction of the Project.
§ 1 . 3 . 5 The Design/Builder shall submit to the Owner a Proposal , including the
completed Preliminary Design Documents , a statement of the proposed contract sum ,
and a proposed schedule for completion of the Project . Preliminary Design Documents
3
SEEN iiiiiiiiiii
shall consist of preliminary design drawings , outline specifications or other documents
sufficient to establish the size , quality and character of the entire Project , its
architectural , structural , mechanical and electrical systems , and the materials and such
other elements of the Project as may be appropriate . Deviations from the Owner' s
program shall be disclosed in the Proposal . If the Proposal is accepted by the Owner ,
the parties shall then execute the Part 2 Agreement . A modification to the Proposal
before execution of the Part 2 Agreement shall be recorded in writing as an addendum
and shall be identified in the Contract Documents of the Part 2 Agreement .
§ 1 .4 ADDITIONAL SERVICES
§ 1 . 4. 1 The Additional Services described under this Section 1 . 4 shall be provided by
the Design/Builder and paid for by the Owner if authorized or confirmed in writing by the
Owner .
§ 1 .4 . 2 Making revisions in the Preliminary Design Documents , budget or other
documents when such revisions are :
A inconsistent with approvals or instructions previously given by the Owner ,
including revisions made necessary by adjustments in the Owner' s program
or Project budget ;
. 2 required by the enactment or revision of codes , laws or regulations
subsequent to the preparation of such documents ; or
. 3 due to changes required as a result of the Owner's failure to render
decisions in a timely manner.
§ 1 .4 . 3 Providing more extensive programmatic criteria than that furnished by the
Owner as described in Section 2 . 1 . When authorized , the Design/Builder shall provide
professional services to assist the Owner in the preparation of the program .
Programming services may consist of:
A consulting with the Owner and other persons or entities not designated in
this Part 1 Agreement to define the program requirements of the Project and
to review the understanding of such requirements with the Owner ;
. 2 documentation of the applicable requirements necessary for the various
Project functions or operations ;
. 3 providing a review and analysis of the functional and organizational
relationships , requirements , and objectives for the Project ;
. 4 setting forth a written program of requirements for the Owner' s approval
which summarizes the Owner's objectives , schedule , constraints , and
criteria .
§ 1 .4 . 4 Providing financial feasibility or other special studies .
§ 1 .4. 5 Providing planning surveys , site evaluations or comparative studies of
prospective sites .
§ 1 . 4 . 6 Providing special surveys , environmental studies , and submissions required for
approvals of governmental authorities or others having jurisdiction over the Project .
4
§ 1 .4 . 7 Providing services relative to future facilities , systems and equipment .
§ 1 . 4. 8 Providing services at the Owner's specific request to perform detailed
investigations of existing conditions or facilities or to make measured drawings thereof.
§ 1 .4 . 9 Providing services at the Owner's specific request to verify the accuracy of
drawings or other information furnished by the Owner.
§ 1 . 4. 10 Coordinating services in connection with the work of separate persons or
entities retained by the Owner, subsequent to the execution of this Part 1 Agreement .
§ 1 . 4. 11 Providing analyses of owning and operating costs .
§ 1 . 4. 12 Providing interior design and other similar services required for or in connection
with the selection , procurement or installation of furniture , furnishings and related
equipment .
§ 1 .4 . 13 Providing services for planning tenant or rental spaces .
§ 1 .4 . 14 Making investigations , inventories of materials or equipment , or valuations and
detailed appraisals of existing facilities .
ARTICLE 2 OWNER
§ 2 . 1 RESPONSIBILITIES
§ 2 . 1 . 1 The Owner shall provide full information in a timely manner regarding
requirements for the Project , including a written program which shall set forth the
Owner' s objectives , schedule , constraints and criteria .
§ 2 . 1 . 2 The Owner shall establish and update an overall budget for the Project,
including reasonable contingencies . This budget shall not constitute the contract sum .
§ 2 . 1 . 3 The Owner shall designate a representative authorized to act on the Owner's
behalf with respect to the Project . The Owner or such authorized representative shall
render decisions in a timely manner pertaining to documents submitted by the
Design/Builder in order to avoid unreasonable delay in the orderly and sequential
progress of the Design/Builder's services . The Owner may obtain independent review of
the documents by a separate architect , engineer, contractor , or cost estimator under
contract to or employed by the Owner. Such independent review shall be undertaken at
the Owner's expense in a timely manner and shall not delay the orderly progress of the
Design/Builder's services .
§ 2 . 1 . 4 The Design/Builder Owner shall furnish surveys describing physical
characteristics , legal limitations and utility locations for the site of the Project , and a
written legal description of the site . The surveys and legal information shall include , as
applicable , grades and lines of streets , alleys , pavements , and adjoining property and
5
structures ; adjacent drainage ; rights-of-way , restrictions , easements , encroachments ,
zoning , deed restrictions , boundaries and contours of the site ; locations , dimensions
and necessary data pertaining to existing buildings , other improvements and trees ; and
information concerning available utility services and lines , both public and private ,
above and below grade , including inverts and depths . All the information on the survey
shall be referenced to a Project benchmark .
§ 2 . 1 . 5 The Design/Builder Owner shall furnish the services of geotechnical engineers
when such services are stipulated in this Part 1 Agreement , or deemed reasonably
necessary by the Design/Builder. Such services may include but are not limited to test
borings , test pits , determinations of soil bearing values , percolation tests , evaluations of
hazardous materials , ground corrosion and resistivity tests , and necessary operations
for anticipating subsoil conditions . The services of geotechnical engineer(s) or other
consultants shall include preparation and submission of all appropriate reports and
professional recommendations .
§ 2 . 1 . 6 The Owner shall disclose , to the extent known to the Owner, the results and
reports of prior tests , inspections or investigations conducted for the Project involving :
structural or mechanical systems ; chemical , air and water pollution ; hazardous
materials ; or other environmental and subsurface conditions . The Owner shall disclose
all information known to the Owner regarding the presence of pollutants at the Project's
site .
§ 2 . 1 . 8 The Owner shall promptly obtain easements , zoning variances and legal
authorizations regarding site utilization where essential to the execution of the Owner' s
program .
§ 2 . 1 . 9 Those services , information , surveys , and reports required by Sections 2 . 1 . 4
through 2 . 1 . 8 (except for X2 . 1 . 7 ) which are within the Owner's control shall be furnished
at the Owner's expense , and the Design/Builder shall be entitled to rely upon the
accuracy and completeness thereof, except to the extent the Owner advises the
Design/Builder to the contrary in writing .
§ 2 . 1 . 11 The Owner shall communicate with persons or entities employed or retained by
the Design/Builder through the Design/Builder, unless otherwise directed by the
Design/Builder .
6
ARTICLE 3 OWNERSHIP AND USE OF DOCUMENTS AND ELECTRONIC DATA
§ 3 . 1 The Owner hopes to use the plans , Drawings , specifications , and ether
documents and electronic data furnished by the Design/Builder as a prototype for
construction of other fire stations in the future aro instrumeRt of cor. ane The
Design/Builder's Architect and other providers of professional services shall retain all
common law, statutory and other reserved rights , including copyright in those
instruments of service furnished by them , except the owner shall have the right to reuse
the instruments for construction of additional fire stations . , and
etheF dOGUFnents and e ! eGtFOROG data are fuFnished f4GF use solely with respeGt to this
Part 1Agreement .- The Owner shall be permitted to retain copies , including reproducible
copies , of the drawings , specifications , and other documents and electronic data
furnished by the Design/Builder for information and reference in connection with the
Project except as provided in Sections 3 . 2 and 3 . 3 . The Owner intends that the
documents drawings plans specifications and electronic data are intended to be
reused at some future time . Pursuant to FS 287 . 055 ( l 0 ) the documents and plans
shall contain notice to the public that the plans are subiect to reuse
§ 3 . 2 If the Part 2 Agreement is not executed , the Owner shall not use the drawings ,
specifications , and other documents and electronic data furnished by the Design/Builder
without the written permission of the Design/Builder. Drawings , specifications , and other
documents and electronic data shall not be used by the Owner or others on other
projects , for additions to this Project or for completion of this Project by others , except
by agreement in writing and with appropriate compensation to the Design/Builder,
unless the Design/ Builder is adjudged to be in default under this Part 1 Agreement or
under any other subsequently executed agreement , or by agreement in writing .
§ 3 . 3 If the Design/Builder defaults in the Design/Builder' s obligations to the Owner , the
Architect shall grant a license to the Owner to use the drawings , specifications , and
other documents and electronic data furnished by the Architect to the Design/Builder for
the completion of the Project , conditioned upon the Owner's execution of an agreement
to cure the Design/Builder's default in payment to the Architect for services previously
performed and to the extent allowed by law, indemnify the Architect with regard to
claims arising from such reuse without the Architect's professional involvement .
§ 3 . 4 Submission or distribution of the Design/Builder's documents to meet official
regulatory requirements or for similar purposes in connection with the Project is not to
be construed as publication in derogation of the rights reserved in Section 3 . 1 .
ARTICLE 4 TIME
§ 4 . 1 Upon the request of the Owner, the Design/Builder shall prepare a schedule for
the performance of the Basic and Additional Services which shall not exceed the time
limits contained in Section 10 . 1 and shall include allowances for periods of time required
for the Owner's review and for approval of submissions by authorities having jurisdiction
over the Project .
§ 4 . 2 If the Design/Builder is delayed in the performance of services under this Part 1
Agreement through no fault of the Design/Builder, any applicable schedule shall be
equitably adjusted .
ARTICLE 5 PAYMENTS
§ 5 . 1 The initial payment provided in Article 9 shall be made upon execution of this Part
1 Agreement and credited to the Owner's account as provided in Section 9 . 1 . 2 .
§ 5 . 2 Subsequent payments for Basic Services , Additional Services , and Reimbursable
Expenses provided for in this Part 1 Agreement shall be made in accordance with the
Florida Prompt Pavment Act , FS 218 . 70 et seg_ monthly on the hNUVcaica set
aforth in prime
-/y�� V a
V .
§ 5 . 3 Upon the Owner's receipt of a properly submitted and
correct Application for Payment , the Owner shall make payment to the Design/Builder in
accordance with the Florida Prompt Payment Act .
§ 5 .4 Payments due the Design/Builder under this Part 1 Agreement which are not paid
when due shall bear interest in accordance with the Florida Prompt Payment Act4fGm
the legal rate prevailing where the PreleAt 06 IGGated
-- - y a prevailing
ARTICLE 6 DISPUTE RESOLUTION MEDIATION AND ARBITRATION
—
§ 6 . 1 Claims , disputes or other matters in question between the parties to this Part 1
Agreement arising out of or relating to this Part 1 Agreement or breach thereof shall be
subject to the following procedure :
the dispute shall first be addressed by a meeting between the Owner
Design/Builder, Architect and Owner's Representative .
If the dispute is not remedied the parties shall submit the dispute to the County
Administrator or his assign who shall make the final decision on the matter.
The resolution of the dispute shall be reduced to writing and attached to this
agreement .
§ 6 . 2 IR addition to and pFieF to arbitFation , the paFties shall endeavor to settle disputes
by mediatiOR . Demand faF mediation shall be filed OR WFitffiRg With the GtheF paFty to thus
ow
question has arisen , in no eveRt shall the demand for mediation be made afteF
the date when snstitufien of legal or equitable pFaceedings based OR SUGh Glaim , dispi
9F etheF matter in question would be barred by the appliGable statute of Fepose 0
Vis-
§ 6 . 3 Demand fGF aFbitFatien shall be filed in wFiting with the GtheF party to thus Part I
8
• . . . .W=K •
-
•. .
. •
• •
1 • • am
d d Fal .IN • al z raw 3 PMVMLQ dra • • • • . • — • 111TV16WAOLW
• . . • • • . • .
W WEE
• . • • • . . . . • K ram • • 1 • I mFWTW1 • • — • • r.70 Mr.
W7010M :a
• • 1 . • •
• . • &VMSram
'07-111
Amo I . . • • 1
• � . . � .
Is fWI
UP
OF a
• . - . . . - . . . - . . - . . - . r . - .
• • • ' • • • • � ' • i • '
§ 7 . 5 Prior to the termination of the services of the Architect or any other design
professional designated in this Part 1 Agreement , the Design/Builder shall identify to
the Owner in writing another architect or design professional with respect to whom the
Owner has no reasonable objection , who will provide the services originally to have
been provided by the Architect or other design professional whose services are being
terminated .
ARTICLE 8 TERMINATION OF THE AGREEMENT
§ 8 . 1 This Part 1 Agreement may be terminated by either party upon seven (7 ) days '
written notice should the other party fail to perform substantially in accordance with its
terms through no fault of the party initiating the termination .
§ 8 . 2 This Part 1 Agreement may be terminated by the Owner without cause upon at
least seven ( 7) days ' written notice to the Design/Builder .
§ 8 . 3 In the event of termination not the fault of the Design/Builder , the Design/Builder
shall be compensated for services performed to the termination date , together with
Reimbursable Expenses then due and Termination Expenses . Termination Expenses
are expenses directly attributable to termination , including a reasonable amount for
overhead and profit , for which the Design/Builder is not otherwise compensated under
this Part 1 Agreement .
ARTICLE 9 BASIS OF COMPENSATION
The Owner shall compensate the Design/Builder in accordance with Article 5 ,
Payments , and the other provisions of this Part 1 Agreement as described below.
§ 9 . 1 COMPENSATION FOR BASIC SERVICES
§ 9 . 1 . 1 FOR BASIC SERVICES , compensation shall be as follows :
One Hundred Forty Two Thousand One Hundred Nine Dollars and XX/ 100
$ 142 , 109 . 00
§ 9 . 1 . 2 AN INITIAL PAYMENT of Thirty Five Thousand Five Hundred Twenty Seven
Dollars and 25/100 ($ 35 , 527 . 25 ) shall be made upon execution of this Part 1
Agreement and credited to the Owner's account as follows :
§ 9 . 1 . 3 SUBSEQUENT PAYMENTS shall be as follows :
$ 35 , 527 . 25 at the completion of the Schematic Design of building
$ 35 , 527 . 25 at the 50 % completion of the Preliminary Design Documents
$ 35 , 527 . 25 at the completion of the Preliminary Design Documents , statement of the
proposed contract sum and proposed project schedule
10
§ 9 . 2 COMPENSATION FOR ADDITIONAL SERVICES
§ 9 . 2 . 1 FOR ADDITIONAL SERVICES , compensation shall be as follows :
Per the fee schedule attached 6 the 1ltlaster Agreement dated April 19; ,2005
§ 9 . 3 REIMBURSABLE EXPENSES
§ 9 . 3 . 1 Reimbursable Expenses are in addition to Compensation for Basic and
Additional Services , and include actual expenditures made by the Design/Builder and
the Design/Builder's employees and contractors in the interest of the Project, as follows :
NONE . DES I G N/BUILD� k ,, . HLL AStE ALNSE .
9w3m2 FOR REIMBURSABLE EXPENSES , GGMpensatieR shall be a multiple of
) times the amounts expender)
§ 9 .4 DIRECT PERSONNEL EXPENSE is defined as the direct salaries of personnel
engaged on the Project , and the portion of the cost of their mandatory and customary
contributions and benefits related thereto , such as employment taxes and other
statutory employee benefits , insurance , sick leave , holidays , vacations , pensions and
similar contributions and benefits .
§ 9 . 5 INTEREST PAYMENTS
§ 9 . 5 . 1 The rate of interest for past due payments shall be in accordance with the
Florida Prompt Pavment Act as follows:
(9suFy laws and Fequkements under- the F-edeFal Tmth in Lending AGt, similaF state an
PFiRGipal P�aGes of business, at the IGGation of the P-FGj9Gt and elsewhere may affeGt the
§ 9 . 6 IF THE SCOPE of the Project is changed materially , the amount of compensation
shall be equitably adjusted .
§ 9 . 7 The compensation set forth in this Part 1 Agreement shall be equitably adjusted if
through no fault of the Design/Builder the services have not been completed within
( 6 ) months of the date of this Part 1 Agreement .
ARTICLE 10 OTHER CONDITIONS AND SERVICES
§ 10 . 1 The Basic Services to be performed shall be commenced on Septemberl ,
2005 and , subject to authorized adjustments and to delays not caused by the
Design/Builder , shall be completed in "Qne Hundred 'Twenty ( 920 . ) calendar days .
tt
t
The Design/Builder' s Basic Services consist of those described in Section 1 . 3 as part of
Basic Services , and include normal professional engineering and preliminary design
services , unless otherwise indicated .
§ 10 . 2 Services beyond those described in Section 1 . 4 are as follows :
(Insert descriptions of other services, identify Additional Services included within Basic
Compensation and modifications to the payment and compensation terms included in
this Agreement.)
None
§ 10. 3 The Owner's preliminary program , budget and other documents , if any , are
enumerated as follows :
Title Date
Attachment "A" — Project Program
This Agreement entered into as of the day and year first written above .
r,tE�RDE N/ DER
(Signature) ( ign ture)
Thomas Lowther, Chairmen of BCC Phil Barth , President
(Printed name and title) (Printed name and title)
BCC Approved : September 13 , 2005
APPROVED
APPROVED AS TO FORM
AND L aK . DBRAAL
BY
WILLIAMUTT08
ASSISTANT COUNTY ATTORNEY
Cr witty ,� � � # r� r :, tr � tor
J
Atteste , 8KK � LBa1rt ® !R'�' 'Creark
�t
By .
12
ATTACHMENT " A "
Project Program
Indian River County Emergency Services
Station # 2
This will be a 3 bay, approximately 9 , 000 square feet prototype station based on the Miami Dade
County floor plan and specifications provided by Indian River County . The structure will be
concrete block, fully sprinkled and designed to the current building codes . The exterior finishes
will be determined at a later date.
The following item will be included in the design of this station.
Two bays 85 feet in length with two 12 ' x 14 ' roll up doors
Split dorm with a total of 10 beds and lockers for three shifts
Unisex ADA restroom off of lobby
Secure access from lobby to rest of station- lobby is only public access area
Men ' s and Women ' s ADA restrooms with two showers each
Conditioned room for Gear with floor drains and incandescent lighting
Conditioned room for EMS Storage
Work Room with tub sink, washing machine, icemaker and safety shower
Exercise room approximately 20 ' x 24 '
Kitchen is contain, 3 pantries, 3 refrigerators, gas range/oven with hood, dishwasher stainless
counter tops
Office/dispatch area with storage closet
Day room/ dining area
Covered Patio
Lawn equipment storage
100KW backup generator with transfer switch, powered by LP gas
Fire sprinklers through out building
Shore power outlets in apparatus bays
6 " concrete aprons in front of each bay door
Standing seam metal roof
Impact windows with shutters
Note : The programming for all 2 and 3 bay prototype stations was developed at the meeting held on May 25`h in
John King ' s Office. John King, Chief Prime, Chief McCloud, Jason Fykes and John Binkley were present at the
meeting.
13