AMENDMENT TO 1 To
WORK ORDER NUMBER .
This Amendment to Work Order Number 1 is entered into as of this 1Rthday of
September , 200 7 pursuant to that certain Continuing Contract Agreement for
Professional Services entered into as of August 10 , 2004 and amended effective July 24 ,
2007 (as so amended , the "Agreement'), by and between Indian River County Solid
Waste Disposal District, a dependent special district of Indian River County, Florida
("District' ) and Brown and Caldwell (Corporation), a California Corporation
("Consultant') .
The District has selected the Consultant to perform the professional services set
forth on Exhibit 1 , attached to this Work Order and made part hereof by this reference .
The professional services will be performed by the Consultant for the fee schedule set
forth in Exhibit 1 and within the timeframe more particularly set forth in Exhibit 1 , all in
accordance with the terms and provisions set forth in the Agreement. Pursuant to
paragraph 1 .4 of the Agreement, nothing contained in any Work Order shall conflict with
the terms of the Agreement and the terms of the Agreement shall be deemed to be
incorporated in each individual Work Order as if fully set forth herein .
IN WITNESS WHEREOF , the parties hereto have executed this Amendment to
Work Order as of the date first written above .
BROWN AND CALDWELL INDIAN RIVER COUNTY SOLID
(CORPORATION ) WASTE DISPOSAL DISTRICT
By: / / By
Title : Gary C . ' 1 66er Chairman
-? ,���
Attest : J . K . Barton , Clerk of Co rt
By
Deputy Clerk
Approved : //�
i . ALJ
seph . Baird , County Administrator
obed asoforIsufficency:
17,
E . Fell , Assistant ounty Attorney
EXHIBIT 1
ATTACHMENT 1
TO
AMENDMENT NO. 1
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
FELLSMERE CONVENIENCE CENTER EXPANSION
SCOPE OF SERVICES
Amendment No. 1 modifies the scope of work in Brown and Caldwell ' s Work Order No . 1 for
planning, design, permitting, and construction of an expansion to the existing Fellsmere
Convenience Center located at 12510 C .R. 512 to include site planning, surveying, geotechnical and
environmental site investigations, permitting, engineering and landscaping design, bidding
assistance and construction phase services . In addition to on-site improvements, the project also
includes off-site improvements consisting of utility extensions and roadway improvements .
Amendment No. 1 is being implemented at this time for engineering work related to planning,
design, and permitting of the expansion to the existing Fellsmere Convenience Center located at
12510 C .R. 512. Included in this Amendment No . 1 are the services for site planning, engineering,
landscaping, and permitting needed to obtain Indian River County Planning Department approval of
the proposed project. The original Scope of Services did not anticipate the need for this approval
process .
The project location consists of two adjacent tracts, one in the City of Fellsmere and one in
unincorporated Indian River County. The original project scope indicated engineering services for
one site plan submittal process through the City of Fellsmere, anticipating the smaller
unincorporated county parcel would be annexed into the larger parcel located within the city limits .
At the Owner' s request, for county planning review and permitting purposes, the parcel was not
annexed and required planning, design and permitting to be conducted through the additional
County site planning process . The following Scope identifies the Tasks required to obtain the
County site planning and permitting approval .
ORIGINAL TASK 1 — PROJECT MANAGEMENT
Additional work activities to be completed under Task 1 include the following :
1 . Project Design Review Meetings - Conduct project design review of the site plan and
submittals required for County approval.
2. Quality Control — Conduct weekly staff meeting with design team members to maintain flow
of work, review and coordinate work products and communicate design: requirements ;
revisions ; schedule .
ORIGINAL TASK 2 — SITE INVESTIGATIONS
p9gen\indian river county swdd\131858 fellsmere ccc\project management\amendment no. I \amendment I -attachment I .doc
Page I of 3
i
Amendment No. 1 does not require any additional work under Task 2.
ORIGINAL TASK 3 — PRELIMINARY DESIGN PHASE
Amendment No. 1 does not require any additional work under Task 3 .
ORIGINAL TASK 4 — SITE PLAN APPROVAL
Additional work activities to be completed under Task 4 include the following:
1 . Preliminary Site Plan and Calculations - Develop preliminary site plan conforming to Title
IX of the Indian River County Code showing existing site conditions , right-of- ways and
easements, proposed demolition, proposed site improvements and stormwater systems
within the County parcel. Provide dimensional data and develop site data calculations
differentiating the Fellsmere and County parcels . Complete and submit application for site
plan review.
2. Final Site Plan Submittals — Revise initial site plan submittal per comments from County
Planning Department review. Prepare all accompanying exhibits and submittals required for
site plan approval. Complete and submit applications for Indian River County development
permits.
3 . Landscaping — Revise the landscape design within the County parcel to comply with Indian
River County Ordinance 2007-012 (Landscaping Revisions). Coordinate landscaping
requirements with site plan development to provide appropriate grading and location for
landscape buffers and strips ; opaque features ; and irrigation facilities . Locate and calculate
final vegetation quantities .
ORIGINAL TASK 5 — CONSTRUCTION PLANS AND SPECIFICATIONS
Additional work activities to be completed under Task 5 include the following:
1 . Paving_, Drainage. Grading - Revise grading plans to comply with Indian River County
LDR' s .
2. Landscaping — Prepare final construction plans and specifications for landscaping in
conformance with both City of Fellsmere and Indian River County LDR' s .
ORIGINAL TASK 6 — PERMITTING
Additional work activities to be completed under Task 6 include the following:
1 . Tree Removal - Complete application and assist the SWDD in obtaining Indian River
County tree removal permit.
pAgenGndian aver county swdd\ 131858 fellsmere ccc\project management\amendment no. I\amendment I -attachment Ldoc
Page 2 of 3
2. Land Clearing - Complete application and assist the SWDD in obtaining Indian River
County land clearing permit.
ORIGINAL TASK 7 — BIDDING SERVICES
Amendment No. 1 does not require any additional work under Task 7 .
ORIGINAL TASK 8 — CONSTRUCTION PHASE SERVICES
Amendment No. 1 does not require any additional work under Task 8 .
ORIGINAL TASK 9 — OFF SITE ROADWAY IMPROVEMENTS
Amendment No. 1 does not require any additional work under Task 9.
ORIGINAL TASK 10 — REIMBURSABLE EXPENSES
Additional work activities to be completed under Task 10 include the following:
1 . Reimbursables : Direct reproduction costs , communications, mileage, postage, express mail,
etc. attributable to the completion of this project will be billed to the Client in accordance
with Carter Associates, Inc. standard rate schedule (attached to Budget Proposal) and shall
not exceed the amount indicated for this Task.
p:\gen\indian river county swdd\131858 fellsmere ccc\project management\amendment no. I \amendment I _attachment I .doc
Page 3 of 3
EXHIBIT 1
ATTACHMENT 2
TO
AMENDMENT NO. 1
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
FELLSMERE CONVENIENCE CENTER EXPANSION
PROJECT BUDGET
The BC Team proposes to complete the Scope of Services described in Amendment No . 1 ,
Attachment 1 for the lump sum amount of $ 11 ,000. This increases the overall cost of Work
Order No. 1 from $ 179 , 875 to $ 190,875 . An approximate breakdown of this lump sum amount,
by task, is presented below.
Task Budget
Original Work Amendment Revised Work
Order No. 1 No. 1 Order No. 1
Task 1 Project Management $ 15 , 390 $ 1 ,955 $ 17,345
Task 2 On-Site Investigations $ 17,970 $ 0 $ 179970
Task 3 Preliminary Design $ 23 , 880 $ 0 $ 23 ,880
Task 4 Site Plan Approval $ 14,990 $ 5 ,345 $ 20,335
Task 5 Construction Plans and Specifications $ 28, 120 $ 21100 $ 30,220
Task 6 Permitting $ 5,550 $ 880 $ 6,430
Task 7 Bidding Services $ 7 ,700 $ V$ 35 ,500
Task 8 Construction Phase Services $ 25 ,790 $
Task 9 Off-Site Roadway Improvements $ 35,500 $
Reimbursable Direct Expenses $ 4,985 $ 720 $ 59705
Total $ 1799875 $ 11,000 $ 190,875
p9genAindian river county swdd\131858 fellsmere eocAproject managementAamendment no. IAamendment I_ attachment 2.doc
EXHIBIT 1
ATTACHMENT 3
TO
AMENDMENT NO, 1
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
FELLSMERE CONVENIENCE CENTER EXPANSION
PROJECT IMPLEMENTATION SCHEDULE
Amendment No. 1 does not affect the schedule for the planning, design, permitting and
construction of the Fellsmere Convenience Center expansion project. The original project
schedule included with Work Order No. 1 is presented below for reference.
Milestone Completion Date
Notice to Proceed November 15 , 2006
Site Investigations December 22, 2006
Preliminary Design Submittal January 30, 2007
Site Plan Approval April 30, 2007
Construction Plans/Specifications May 31 , 2007
Permits Obtained June 15 . 2007
Building Department Approval' June 30, 2007
Bidding/Construction Contract Award September 30, 2007
Substantial Construction Completion March 31 , 2008
Final Construction Completed April 30, 2008
Project Closeout May 31 , 2008
'Does not include pre-fabricated buildings . Design drawings for these structures will be submitted during
construction.
Assuming that Notice to Proceed is issued by November 15 , 2006 and Site Plan approval is
obtained from the Planning Department in 90 days or less from the date of initial submittal ,
construction plans and specifications will be completed by May 31 , 2007 . All subsequent
milestone completion dates are projected and subject to change.