HomeMy WebLinkAbout2006-106 a 0
AMENDMENT No: 2
DEP AGREEMENT No: H5IRl
FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
BUREAU OF BEACHES AND COASTAL SYSTEMS
2004 HURRICANE RECOVERY PLAN
STATE OF FLORIDA
AMENDMENT TO GRANT AGREEMENT FOR
INDIAN RIVER COUNTY DUNE RESTORATION PROJECT
THIS AGREEMENT as entered into on the 15`h day of March, 2005 , and amended on the 91h day of August,
2005 , between the FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION (hereinafter referred to as the
" DEPARTMENT") and INDIAN RIVER COUNTY, a local government, (hereinafter referred to as the "LOCAL
SPONSOR") is hereby amended as follows:
• Paragraphs 2, 5 , 6, 18 and 20 are hereby revised to read as follows :
2. This Agreement shall begin on the last date executed and end on July 1 , 2007 . Pursuant to Section 161 . 101 ( 18),
Florida Statutes, work conducted on this PROJECT by the LOCAL SPONSOR or its subcontractor beginning on
or after February 1 , 2005 , shall be eligible for cost sharing by the DEPARTMENT.
5 . The LOCAL SPONSOR shall implement the PROJECT and complete said PROJECT upon the terms and
conditions set forth in this Agreement and future requisite authorizations and environmental permits. The
PROJECT consists of dune restoration at North Indian River County (R17-R70), Vero Beach (R70-R86), South
Indian River County (R100-R107), and beach restoration activities along the segment of shoreline known as
Sector 7 (95ft. north of T- 100 — 105ft. south of R- 107). The parties expressly agree that the provisions of this
paragraph shall survive and be enforceable beyond the expiration of this Agreement.
The LOCAL, SPONSOR shall develop a detailed Scope of Work for the PROJECT. It is understood and agreed
that the detailed Scope of Work shall include a narrative description of each task, a corresponding detailed budget
and a project schedule. Written approval of the Scope of Work must be obtained from the Department' s Project
Manager prior to initiating work.
6. The DEPARTMENT and the LOCAL SPONSOR agree that the estimated costs of the PROJECT are identified in
Table 1 below:
Table 1 : Estimated Project Costs
Task # Eligible Project ITEM State ILocal ITotal
2.0 Dune Restoration $69511 349 $6517135 $7,162 484
3 .0 Sand Placement
3 . 1 Sector 7 Beach Restoration $3,5181651 $3519865 $3 ,870,516
TOTAL PROJECT COSTS $ 101030,000 $ 1 ,003 ,000 $11 ,033 ,000
18 . The LOCAL SPONSOR' s Project Manager for all matters is Jonathan C. Gorham, Phone: 772/567-8000 ext. 568 .
The DEPARTMENT's Project Manager for all technical matters is Brian Taylor, Phone: 850/922-7866, and the
DEPARTMENT' s Grant Program Administrator for all administrative matters is Dena VanLandingham, Phone:
850/922-7711 , or their successor(s). All matters shall be directed to the appropriate persons for action or
disposition.
DEP Agreement No. H5IR1 , Amendment No. 2, Page 1 of 3
20. Any and all notices shall be delivered to the parties at the following addresses :
LOCALSPONSOR DEPARTMENT
Jonathan Gorham Dena VanLandingham, Grant Program Administrator
Indian River County Department of Environmental Protection
184025 1h Street Bureau of Beaches and Coastal Systems
Vero Beach, FL 32960 3900 Commonwealth Blvd . , MS 300
(772) 567-8000 Tallahassee, Florida 32399-3000
(850) 922-7711
• All references to Attachment(s) A and E, respectively, are hereby deleted and replaced with references to
Attachment(s) A- 1 , E- 1 .
• Attachment(s) A and E are hereby deleted in their entirety.
• Attachment(s) A- 1 and E- 1 as attached hereto are hereby added to the Agreement.
REMAINDER OF PAGE INTENTIONALLY LEFT BLANK
DEP Agreement No. H51R1 , Amendment No. 2, Page 2 of 3
IN WITNESS WHEREOF, the parties have caused these presents to be duly executed, the day and year last
written below.
INDIAN RIVER COUNTY FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
By. , , . . . .. By.
Title : *Commission Chai amen Secretary or designee
Arthur' R . Neuberger
Apri .1) '4 2006 , .• � ,._ �Zoo (o
Date: ter, Date: Mq � c
_,, �R . Y . ' _`
FCptiidl
LA
FEID No. 59 -j60000674'
AP OVED : DEP Grant Program Administrat
(Q�De , A —wJ C ty Ad iinistrator APPROVED as to form and legality:
APPROV D AS TO FORM
/ANDL S NCDEP Attorney
AN E . LLCOUNTY ATTORNEY
* If someone other than the Commission Chair signs this Agreement, a resolution, statement or other documentation
authorizing that person to sign the Agreement on behalf of the County/City must accompany the agreement.
List of Attachments/Exhibits included as part of this Agreement:
Specify Letter/
Type Number Description (include number of pages)
Attachment A-1 Project Work Plan ( I page)
Attachment E- I Request For Payment (4 pages)
DEP Agreement No. H51R1 , Amendment No. 2, Page 3 of 3
ATTACHMENT A-1
PROJECT WORK PLAN
INDIAN RIVER COUNTY DUNE RESTORATION PROJECT
The PROJECT consists of dune restoration at North Indian River County (R17-R70), Vero Beach (R70-R86), South
Indian River County (RI00-R107), and beach restoration activities along the segment of shoreline known as Sector 7
(95ft. north of T- 100 — 105ft. south of R- 107). The parties expressly agree that the provisions of this paragraph shall
survive and be enforceable beyond the expiration of this Agreement. The PROJECT shall be conducted in accordance
with the terms and conditions set forth under this Agreement, all applicable DEP permits and the eligible project task
items established below. All data collection and processing, and the resulting product deliverables, shall comply with the
standard technical specifications contained in the Department' s Regional Data Collection and Processing Plan and
Geographic Information System Plan, unless otherwise specified in the approved Scope of Work for an eligible PROJECT
item. These plans may be found at http://www.del).state.fl .us/beaches/. Three (3) originals on all written reports
developed under this Agreement shall be forwarded to the Department, unless otherwise specified.
Task No : Eligible Project Item:
2.0 Dune Restoration
Work performed and costs incurred associated with the design, permitting and placement of fill material and
installation of vegetation within the project area. Eligible costs may include mobilization, demobilization,
construction observation or inspection services, beach fill, dune stabilization measures and native beach-dune
vegetation. Construction shall be conducted in accordance with any and all permits issued by the Department.
3.0 Sand Placement
3. 1 Sector 7 Beach Restoration
Professional services required for engineering and design, obtaining environmental permits and other
authorizations and the preparation of plans and specifications. This item specifically excludes permit
application fees or any other fees paid to the State of Florida.
Work performed and costs incurred associated with the placement of fill material and/or the construction of
erosion control structures within the project area. Eligible costs may include mobilization, demobilization,
construction observation or inspection services, beach fill , tilling and scarp removal , erosion control
structures, dune stabilization measures and native beach-dune vegetation. Construction shall be conducted in
accordance with any and all permits issued by the Department.
A monitoring program conducted in accordance with the requirements specified in any and all permits issued
by the Department and the US Army Corps of Engineers. A monitoring plan must be submitted and approved
in writing by the Department prior to the initiation of monitoring activities. The plan shall be developed in a
manner which will coordinate the monitoring activities associated with current shoreline stabilization projects
located within or adjacent to the project area and with the Department' s Regional Coastal Monitoring
Program.
REMAINDER OF PAGE INTENTIONALLY LEFT BLANK
Attachment A- 1 , DEP Agreement No. H51R1 , Amendment No. 2, Page 1 of 1
ATTACHMENT E- 1
FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
2004 HURRICANE RECOVERY PLAN GRANT PROGRAM
REQUEST FOR PAYMENT — PART I
PAYMENT SUMMARY
Name of Project: INDIAN RIVER COUNTY DUNE RESTORATION PROJECT
Grantee: INDIAN RIVER COUNTY DEP Contract Number: H5IR1
Billing Number: Billing Period:
Billing Type: ❑ Interim Billing ❑ Final Billing
Costs Incurred This Payment Request:
Federal Share* State Share Local Share Total
*if applicable
Cost Summary:
State Funds Obligated $ Local Funds Obligated $
Less Previous Payment $ Less Previous Credits $
Less Previous Retained $
Less 'rhis Payment $ Less This Credit $
Less This Retainage (10%) $ Local Funds Remaining $
State Funds Remaining S
Certification: I certify that this billing is correct and is based upon actual obligations of record by the grantee; that
payment from the State Government has not been received; that the work and/or services are in accordance with the
Department of Environmental Protection, Bureau of Beaches and Coastal Systems approved Project Agreement including
any amendments thereto; and that progress of the work and/or services are satisfactory and are consistent with the amount
billed .
Name of Project Administrator Signature of Project Administrator Date
Name of Project Financial Officer Signature of Project Financial Officer Date
Attachment E- 1 , DEP Agreement No. H51R1 , Amendment No. 2, Page 1 of 4
f
FLORIDA DEPARTMENT OF ENVIRONMENTAL. PROTECTION
2004 HURRICANE RECOVERY PLAN GRANT PROGRAM
REQUEST FOR PAYMENT — PART II
REIMBURSEMENT DETAIL
Name of Project: INDIAN RIVER COUNTY DUNE RESTORATION PROJECT
Grantee: INDIAN RIVER COUNTY DEP Contract Number: 115 IR l
Billing Number: Billing Period:
Summary of Invoices :
Task
Date of Invoice Amount of No./ Check Amount Paid
Invoice Number Invoice (Eligible Vendor Name Number Vendor
Project
Item)
TOTAL: $
Certification: I certify that the purchases noted above were used in accomplishing the project; and that invoices, check vouchers,
copies of checks, and other purchasing documentation attached hereto are maintained as required to support the cost reported above
and are available for audit upon request.
Name of Project Administrator Signature of Project Administrator Date
Name of Project Financial Officer Signature of Project Financial Officer Date
Attachment E- 1 , DEP Agreement No. H51R1 , Amendment No. 2, Page 2 of 4
FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
2004 HURRICANE RECOVERY PLAN GRANT PROGRAM
REQUEST FOR PAYMENT - PART III
PROJECT PROGRESS REPORT
Name of Project. INDIAN RNER COUNTY DUNE RESTORATION PROJECT
Grantee: INDIAN RIVER COUNTY DEP Agreement Number: II5IRI
Report Period:
Status of Eligible Project Items : (Describe progress accomplished during report period, including statement(s) regarding
percent of task completed to date. Describe any implementation problems encountered, if applicable .)
Task Eligible Project
No: Item:
2.0 DUNE RESTORATION
3 .0 SAND PLACEMENT
3 . 1 SECTOR 7 BEACH RESTORATION
REMAINDER OF PAGE INTENCIONALLY LEFT BLANK
Attachment E- 1 , DEP Agreement No. H51R1 , Amendment No. 2, Page 3 of 4
FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
2004 HURRICANE RECOVERY PLAN GRANT PROGRAM
REQUEST FOR PAYMENT - PART IV
PROJECT FINANCIAL REPORT
Name of Project: INDIAN RIVER COUNTY DUNE RESTORATION PROJECT
Grantee: INDIAN RIVER COUNTY DEP Contract Number: I15IR1
Report Period :
Project Expenditures
Costs Incurred Costs Incurred Total Funds
Task Eligible Project Items This Report Period to Date Obligated
No.
2.0 Dune Restoration $ $ $7, 1625484
3 .0 Sand Placement
3 . 1 Sector 7 Beach $ $ $3 ,870,516
Restoration
TOTAL $ 11 ,033 ,000
REMAINDER OF PAGE INTENTIONALLY LEFT BLANK
Attachment E- 1 , DEP Agreement No. H51R1 , Amendment No. 2, Page I of