HomeMy WebLinkAbout2006-311 � vo � - � ! !
AMENDMENT NUMBER 2 TO WORK ORDER NUMBER 1
This Amendment Number 2 to work Order Number 1 ("Amendment") is entered into as
of this 12th day of September 2006 ("Effective Date") pursuant to that certain Continuing
Contract Agreement for Professional Services dated entered into as of
August 12 , 2003 ("Agreement') , by and between Indian River County, a political
subdivision of the State of Florida ("COUNTY") AND Ecotech Consultants, Inc .
("CONSULTANT") .
1 . The COUNTY has selected the Consultant to perform the professional services set
forth in Work Order Number 1 dated November 16 , 2004 .
2 . The COUNTY and the Consultant desire to amend Work Order Number 1 as set forth
in Exhibit 1 attached to this Amendment and made a part hereof by this reference, all in
accordance with the terms and provisions set forth in the Agreement.
3 . From and after the Effective Date of this Amendment, Work Order Number 1 is
amended as set forth in this Amendment. Pursuant to paragraph 1 .4 of the Agreement, nothing
contained in any Work Order shall conflict with the terms of the Agreement and the terms of the
Agreement shall be deemed to be incorporated in each individual Work Order as if fully set forth
herein.
IN WITNESS WHEREOF, the parties hereto have executed this Amendment as of the
Effective Date first written above. -
BOARD OF COUNTY COMlv) ISSIONERS
ECOT//E��CH CO ULTANT INC . OF INDIAN RIVER OUNTY'
By C. . �. B
C.E. SVindell, Jr. Arthur.I���eub xger,'.Ch i an
Title : President
Attest: J. K. Barton, Clerk of Court
By
Deputy Clerk
Approved:
seph A. Baird, County Administrator
Parian
ed as to form and legal sufficiency:
E. Fell, Assistant un
Attorney
EXHIBIT 1
ATTACHMENT
INDIAN RIVER UTILITIES DEPARTMENT
NORTH COUNTY BRINE DISPOSAL
SCOPE OF SERVICES
Amendment No . 2 modifies the scope of work in Work Order No . 1 as issued to Ecotech
Consultants, Inc. for assisting the County with responding to request for additional information
(RAI) received from the Florida Department of Environmental Protection (FDEP), meetings with
FDEP in Tallahassee, and the preparation of a mitigation plan for the Spoonbill Marsh using a
portion of the Lost Tree Islands property.
Amendment No. 2 is being implemented at this time to provide professional environmental and
engineering services by Ecotech Consultants, Inc . and Masteller & Moler, Inc . associated with the
project described above. The additional work to be performed as part of this Amendment will
generally included preparation of responses to RAI questions, meetings with FDEP, and the
preparation of mitigation plans .
A brief description of the scope of services for Amendment No . 2 is provided below :
Task 1 . FDEP Tallahassee Presentation
Ecotech Consultants, Inc . (ETC) will prepare a power point presentation outlining the design and
design rationale for the project. ETC will meet with Mr. Mike Sole and the administrative staff of
the technical departments within the Tallahassee FDEP office.
The deliverables for this task will include a summary memo outlining the discussion with FDEP .
Task 2 . Investigate ERP Optional Design
ETC will meet with the FDEP UMAM and ERP staff on the project site to discuss the environmental
aspects of the project, especially as they relate to mitigation. ETC will, with prior concurrence by
the County, modify the Industrial Waste Permit (IWP) to reflect the changes agreed to by FDEP
based on the on-site meeting.
Page 1 of 6
The deliverables for this task will include two copies of the draft IWP application for review by the
County. ETC will modify the draft application as appropriate in response to comments received
from the County, after the County completes their review of the draft application.
Task 3 . ERP Lost Tree Conceptual Design
ETC will meet with Ms. Beth Powell to discuss the use of a portion of the Lost Tree Island tract
owned by the County for mitigation of the Spoonbill Project. ETC will prepare a conceptual
mitigation plan using a portion of the Lost Tree acreage. The plan , once approved by the County,
will be presented to FDEP in Orlando .
The deliverables for this task will include a description of the plan.
Task 4. IWP/ERP Meetings
ETC will meet with FDEP, the U. S . Army Corps of Engineers, the U. S . Fish & Wildlife Service, and
the St. Johns Water Management District to discuss the four RAI letters received for the Spoonbill
project.
The deliverables for this task will include a letter summarizing the information discussed during
these meetings .
Task 5. ERP Lost Tree Plan (if necessary)
If mitigation is required, then ETC will design the Lost Tree mitigation plan and will modify the
ERP application to include this plan.
One copy of the draft plan will be provided to the County for review . ETC will modify the plan as
appropriate in response to comments received from the County, after the County completes their
review of the draft plan. ETC will provide the County with one copy of the modified plan .
Task 6. ERP RAI Response
ETC will assist the County with preparation of a response letter addressing the issues in the request
for additional information received from FDEP .
One copy of the draft RAI response letter will be provided to the County for review . ETC will
modify the draft response letter as appropriate relative to comments received from the County, after
the County completes their review of the draft response letter. ETC will provide the County with
Page 2 of 6
one copy of the letter as sent to FDEP .
Task 7. IWP RAI Response
ETC will assist the County with preparation of a response letter addressing the issues in the request
for additional information received from FDEP .
One copy of the draft RAI response letter will be provided to the County for review . ETC will
modify the draft response letter as appropriate relative to comments received from the County, after
the County completes their review of the draft response letter. ETC will provide the County with
one copy of the letter as sent to FDEP .
Task 8. Engineering Servives
Masteller & Moler, Inc. will assist ETC with the preparation of responses to the FDEP RAI questions
and with the preparation of the mitigation plans . This work will be included with the deliverables
associated with tasks 5 , 6 , and 7 above .
Page 3 of 6
ATTACHMENT 2
INDIAN RIVER UTILITIES DEPARTMENT
NORTH COUNTY BRINE DISPOSAL
PROJECT BUDGET
The Ecotech Consultants, Inc . Team proposes to complete the Scope of Services described in
Amendment No . 2 , Attachment I for the lump sum amount of$35 ,640 .00 . This increases the overall
cost of Work Order No . 1 from $206 , 580. 00 to $242 ,220. 00 . An approximate breakdown of this
lump sum amount, by task, is presented below.
Construction Permitting Construction Total
Plans Services
Original WO No . 1 $0 $84,220 $33800 $ 88 ,020
Amendment 1 $ 775000 $32,940 $8 ,620 $ 118 ,560
Amendment 2 $ 0 $35 ,640 $ 0 $35,640
Ecotech Consultants, Inc . proposes to complete the Scope of Services described in Attachment 1 for
the amount of $35 ,640. 00. A breakdown of the costs for each task is shown below.
Task Budget
FDEP Tallahassee Presentation $ 19995 . 00
Investigate ERP Optional Design $ 55460. 00
ERP Lost Tree Conceptual Design $3 ,255 . 00
IWP/ERP Meetings $55775 .00
ERP Lost Tree Plan (if necessary) $7,245 . 00
ERP RAI Response $2,520 .00
IWP RAI Response $ 19890. 00
Engineering Services $73500. 00
Page 4 of 6
MINIMUM
ADDITIONAL SERVICES
The cost to complete work not included in the Scope of Services as described in Attachment 1 will
be billed at the hourly rates shown below . Direct charges for additional services will be billed to the
County at their actual value.
Principal Engineer $ 155 . 00/hour
Principal Scientist $ 105 . 00/hour
Senior Engineer $95 . 00/hour
Senior Scientist $ 85 . 00/hour
CAD Designer $ 80 .00/hour
GIS $ 75 . 001hour
Page 5 of 6
ATTACHMENT
INDIAN RIVER UTILITIES DEPARTMENT
NORTH COUNTY BRINE DISPOSAL
PROJECT SCHEDULE
An estimated schedule for completion for the scope of services contained in Amendment 2 is shown
below. The time needed to complete each of the tasks described in Attachment 1 by Ecotech
Consultants, Inc . and the County can be reasonably estimated as shown below with the limitation
that neither the County nor Ecotech Consultants, Inc. can control the phase of the permitting process
controlled by the Florida Department of Environmental Protection, the St . Johns River Water
Management District, or the U. S . Army Corps of Engineers .
Milestone Estimated Completion Date
FDEP Tallahassee Presentation 15 September 2006
Investigate ERP Optional Design 30 September 2006
ERP Lost Tree Conceptual Design 15 September 2006
IWP/ERP Meetings 31 October 2006
ERP Lost Tree Plan 30 September 2006
ERP RAI Response 30 September 2006
IWP RAI Response 30 September 2006
Engineering Services 30 September 2006
Page 6 of 6