AMENDMENT NUMBER 5 TO WORK ORDER NUMBER 1
This Amendme, tNumber 5 to Work Order Number 1 ("Amendment') is entered into as
of this ��day o e - 2007 ("Effective Date") pursuant to that certain Continuing
Co tract Agreement for Professional Seryices dated entered into as of
/PJ ("Agreement'), by and between Indian River County, a political
subdivision of the State of Florida ("COUNTY") AND Ecotech Consultants, Inc .
("CONSULTANT") .
1 . The COUNTY has selected the Consultant to perform the professional services set
forth in Work Order Number 1 dated November 16. 2004 .
2 . The COUNTY and the Consultant desire to amend Work Order Number I as set forth
in Exhibit 1 attached to this Amendment and made a part hereof by this reference, all in
accordance with the terms and provisions set forth in the Agreement.
3 . From and after the Effective Date of this Amendment, Work Order Number 1 is
amended as set forth in this Amendment . Pursuant to paragraph 1 . 4 of the Agreement, nothing
contained in any Work Order shall conflict with the terms of the Agreement and the terms of the
Agreement shall be deemed to be incorporated in each individual Work Order as if fully set forth
herein.
IN WITNESS WHEREOF, the parties hereto have executed this Amendment as of the
Effective Date first written above .
BOARD OF COUNTY COMMISS116NERS
ECOTECH CONSULTANTS, INC. OF INDIAN RIVER COUNTY
By C'E• By /
C .E . Swindell, Jr. GaV. Wheeler, Chairinn
Title : President
Attest: J. K. Ba on, Clerk of Court
By
Depu y Clerk
Q Approved :
U Jos A. Baird, County Administrator
UU Approved as to form and legal sufficiency:
r Marian E. Fell, Assistant County Attorney
EXHIBIT 1
ATTACHMENT
INDIAN RIVER UTILITIES DEPARTMENT
NORTH COUNTY BRINE DISPOSAL
SCOPE OF SERVICES
Amendment No . 5 modifies the scope of work in Work Order No. 1 as issued to Ecotech
Consultants, Inc . for assisting the County with permitting, design, and construction management
services. This amendment provides for specialty engineering sub-consulting services not included
in the previous work because of the dynamic and unpredictable course of events associated with the
permitting and design processes .
Amendment No . 5 is being implemented at this time to provide professional environmental and
engineering services by Ecotech Consultants, Inc . and Masteller & Moler, Inc . associated with the
project described above. The additional work to be performed as part of this Amendment will
generally include engineering sub-consulting services, engineering bid assistance, and contract
administration and construction observation for the engineering works associated with the project.
A brief description of the scope of services for Amendment No . 5 is provided below :
Task 1 . Sub-Consultant Services
Sub-Consultants required for finalization of the structural engineering, electrical engineering, and
soil boring/report details needed for completion of project plans and specifications suitable for
competitive bidding of this project.
Task 2 . Services During Bidding
Masteller & Moler, Inc . will assist the County in bidding the project. These services will include
issuing plans with specifications to bidding contractors, maintain a Bidder ' s List, prepare
Addendums; Review bids; and provide letter recommending award of the Contract.
Task 3. Contract Administration and Construction Observation
Masteller & Moler, Inc . will provide Contract Administration and periodic construction observation
of the demineralization concentrate disposal project. These services will include attending pre-
Page I of 5
construction and progress meetings; review and approve shop drawings and test results; review
monthly pay estimates ; review and process construction change orders ; and provide overall project
administration services . Masteller & Moler, Inc . will also provide periodic project observation of
construction on an "as-needed" basis to make certain that the project elements are being constructed
in reasonable compliance with the construction plans and permits .
Page 2 of 5
ATTACHMENT
INDIAN RIVER UTILITIES DEPARTMENT
NORTH COUNTY BRINE DISPOSAL
PROJECT BUDGET
The Ecotech Consultants, Inc . Team proposes to complete the Scope of Services described in
Amendment No . 5 , Attachment 1 for the lump sum amount of$48 ,000.00 . This increases the overall
cost of Work Order No . 1 from $345 , 949. 00 to $ 393 , 949 . 00 . An approximate breakdown of this
lump sum amount, by task, is presented below.
Construction Permitting Construction Total
Plans Services
Original WO No. 1 $ 0 $ 841220 $3 ,800 $88 ,020
Amendment 1 $ 77,000 $32 ,940 $81620 $ 1185560
Amendment 2 $0 $35 ,640 $0 $35 ,640
Amendment 3 $675560 $31 ,915 $ 0 $995475
Amendment 4 $0 $45254 $0 $45254
Amendment 5 $ 159500 $0 $32, 500 $48,000
Ecotech Consultants, Inc . proposes to complete the Scope of Services described in Attachment 1 for
the amount of $48,000. 00. A breakdown of the costs for each task is shown below.
Task Budget
Sub-Consultant Services $ 15 ,500. 00
Services During Bidding $4,500 . 00
Contract Administration and Construction Observation $28 , 000. 00
Page 3 of 5
ADDITIONAL SERVICES
The cost to complete work not included in the Scope of Services as described in Attachment 1 will
be billed at the hourly rates shown below. Direct charges for additional services will be billed to the
County at their actual value .
Principal Engineer $ 155 . 00/hour
Principal Scientist $ 105 . 00/hour
Senior Engineer $ 95 .00/hour
Senior Scientist $ 85 .00/hour
CAD Designer $80. 00/hour
GIS 575 . 00/hour
Page 4 of 5
ATTACHMENT
INDIAN RIVER UTILITIES DEPARTMENT
NORTH COUNTY BRINE DISPOSAL
PROJECT SCHEDULE
An estimated schedule for completion for the scope of services contained in Amendment 5 is shown
below. The time needed to complete each of the tasks described in Attachment 1 by Ecotech
Consultants, Inc . and the County can be reasonably estimated as shown below with the limitation
that neither the County nor Ecotech Consultants, Inc. can control the phase of the permitting process
controlled by the Florida Department of Environmental Protection, the St. Johns River Water
Management District, or the U. S . Army Corps of Engineers.
Milestone Estimated Completion Date
Sub-Consultant Services 30 September 2007
Services During Bidding 30 November 2007
Contract Administration and Construction Observation 30 September 2008