HomeMy WebLinkAbout2009-245 CHANGE ORDER Distribution to : + . 8 A AIA DOCUMENT G701 OWNER oQ 9 a q5~ ARCHITECT _ CONTRACTOR FIELD _ OTHER PROJECT : Fellsmere Convenience Center CHANGE ORDER NUMBER : ONE INITIATION DATE : August 28 , 2009 TO : Barth Construction, Inc . CONTRACT DATE : April 22 , 2008 1717 Indian River Blvd, Suite 202A Vero Beach , FL 32960 You are directed to make the following changes in this Contract : 9P 2 )10 To the Contract Sum as follows Proposal Request # 12 Additional Engineering Services <$69375 . 00> Allowance Reconciliation- See attached Pay Item 436 <$293 . 91 > Pay Item #37 <$2 ,270 . 00> Total Credit <$ 89938 . 91 > To the Contract Time as follows Rain Delay (August 19`h -- August 26`h) 7 days Rain Delay (August 29`h- September 30`h) 3 days Rain Delay (October 1 — October 315`) 5 days Proposal Request # I poOff Site Storm vs . Sewer Conflict 12 days Proposal Request #4 Change to U/G Electrical 15 days Proposal Request #5 Drain pipe South Side of CR 512 15 days Proposal Request #6 Landscape Changes 15 days Proposal Request #7 Guardrail 10 Days Proposal Request # 8 Curbs @ Metal Shed 10 Days Proposal Request # 11 Air Relief Valve Modifications 30 Days Proposal request # 12 Additional Engineering Services 125 Days Total 247 Days NOTE : The costs associated with Proposal Request # 1 and 44 thru # 8 and # 11 were paid through Pay Items # 36 & 937 and do not effect the contract total . Not valid until signed by both the Architect and Owner. Signature of the Contractor indicates his agreement herewith , including any adjustment in the Contract Sum or Contract Time The Original (Contract Sum) (QiAranteed Mgm imum Gost) was . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 1 , 850 , 879 . 53 Net change by previously authorized Change Orders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 00 . 00 The (Contract Sum ) ( ) prior to this Change Order was . . . 6 . 6 . . 0 . 0 . $ 1 , 850 , 879 . 53 The (Contract Sum) ( ) will be (increased) (decreased) (used) bythis Change Order . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 81938 .91 The new (Contract Sum) ( ) including this Change Order will be $ 1 , 841 , 940 . 62 The Contract Time will be ( increased) (decreased) (tinehanged) by ( 247 ) Days The Date of Substantial Completion as of the date of this Change Order therefore is September .) , 2009 ENGINEER CONTRACTOR OWNER Brown & Caldwell Barth Construction Indian River County SWDDD 850 Trafalgar Court 4300 1717 Indian River Blvd . #202A 1325 74`h Avenue Maitland , Fl 32751 Vero Beach , FL 2960 Vero Beach Fl 32968 � DATE : q I � 0I D � ` , c) 7 DATE : September 15 ,_ 2009