HomeMy WebLinkAbout2007-089 INDIAN RIVER COUNTY
BEACH PRESERVATION PLAN
WORK ORDER NO. 5 TO THE
PROFESSIONAL SERVICES AGREEMENT
BETWEEN APPLIED TECHNOLOGY AND MANAGEMENT, INC.
AND INDIAN RIVER COUNTY, FLORIDA
Pursuant to the Professional Services Agreement (MASTER AGREEMENT) dated
December 13 , 2005, by and between INDIAN RIVER COUNTY, a political subdivision of the
State of Florida, hereinafter referred to as the COUNTY, and APPLIED TECHNOLOGY AND
MANAGEMENT, INC. , with a Florida office in WEST PALM BEACH, FL., hereinafter
referred to as the CONSULTANT, this WORK ORDER No. 5 is an extension of and hereby
becomes a part of the MASTER AGREEMENT as follows :
SECTION I - PROJECT DESCRIPTION
Services included in this Work Order are specified in the attached Scope of Work
included as Exhibit "A"
SECTION II - COUNTY OBLIGATIONS
The COUNTY agrees to provide the CONSULTANT with the following material, data,
or services as required in connection with the work to be performed under this Work Order:
A. Currently available studies, survey drawings, plans, calculations, and other data pertinent
to the Project.
B. Review and comment on CONSULTANTS work in a timely fashion.
SECTION IH SCOPE OF SERVICES
CONSULTANT will provide services as specified in the attached Scope of Work included as
Exhibit `B"
SECTION IV - TIME FOR COMPLETION
After the COUNTY issues a written authorization to proceed, all work shall be completed
on or before November 1 , 2006 unless project delays extend the time of completion.
JAMOPOSALSUNDIAN RIVER OOUN'1'YU'- 1034 WORK ORDERS 5 AND 6W'I'M WORK ORDE25.DOC
SECTION V COMPENSATION
The COUNTY agrees to pay, and the CONSULTANT agrees to accept fees for services
rendered according to the attached Cost Proposal included as Exhibit `B".
SECTION VI - PARTIAL PAYMENTS
The COUNTY shall make monthly partial payments to the CONSULTANT for all
authorized work pertaining directly to this project performed during the previous calendar month
The CONSULTANT shall submit invoices monthly for services performed and expenses
incurred pursuant to this Agreement during the prior month.
The CONSULTANT shall submit duly certified invoices to the Director of the Public
Works Department. For lump sum line items, the amount submitted shall be the prorated amount
due for all work performed to date under this phase, determined by applying the percentage of
the work completed as certified by the CONSULTANT, to the total due for this phase of the
work. For each invoice, the CONSULTANT shall certify that the total invoice amount is
correct.
The amount of the partial payment due the CONSULTANT for the work performed to-
date under these phases shall be an amount calculated in accordance with the previous
paragraph, less ten percent (10%) of the invoice amount thus determined, which shall be
withheld by the COUNTY as retainage, and less previous payments.
The ten percent (101/4) retainage withheld shall be paid in full to the CONSULTANT by
the COUNTY, within forty-five days after the date of final acceptance of the work by the
Director of Public Works.
Billings shall be payable in accordance with the provisions of the Local Government
Prompt Payment Act, Florida Statutes section 218. 70 et. seq. at not less than monthly intervals. No
payment shall be made unless the Public Works Director has received and approved the work
products required under the "Scope of Services" herein.
1_U'ROEOSALSUNDIAN RIVER COUNT Yll'- 1034 WORK ORDERS AND 6W'1'M WORK ORDER 5.DOC
SECTION VII - RELATIONSHIP TO MASTER AGREEMENT AND
LAWS OF FLORIDA
Pursuant to paragraph 1 .4 of the Agreement, nothing contained in any WORK ORDER
shall conflict with the terms of the Agreement and the terms of the Agreement shall be deemed
to be incorporated in each individual WORK ORDER as if fully set forth herein.
IN WITNESS WHEREOF the parties hereto have executed these presents this 13th
day of lurch 2007.
APPLIED TECHNOLOGY INDIAN RIVER COUNTY,.FLORiI;VQ
AND MANAGEMENT, INC. BOARD OF COUNTY COMMISSIONEKS
400 S. AUSTRALIAN AVE.
WEST PALM BEACH, FL 33401 '
r .
BY: BY:
Michael Jenkins, Ph.D. Gary C . Wheeler
Coastal Team Leader Chairman
JEFFREY K BARTON, CLERK
Attest:
APPROVED
BY
jeh A. Urd, County Administrator
Approved as to form and legal
uf& ' ency :
C
Assistant County Attorney
JAPROPOSALSVND AN RIVER COUN Y%P-1034 WORK ORDERS3 AND 61ATM WORK ORDER 5.DOC
EXHIBIT "A"
SCOPE OF SERVICES
J:\PROPOSALSUNDL4N RIVER COUNCYT- 1034 WORK ORDERS AND 61ATM WORK ORDER 5.DOC
Attachment A — Scope of Services
February 2007
Work Order 5
Indian River County Beach
Sector 7
Construction Phase and Immediate Post-Construction Services
INTRODUCTION
Florida's Department of Environmental Protection (DEP) and the U.S . Army Corps of Engineers
have issued project permits, and the County has awarded a construction contract to Great Lakes
Dredge and Dock, Inc. (GLDD). A notice to proceed has been issued to GLDD, and construction
is anticipated to commence in March 2007.
This Work Order and Scope of Services will provide the County with the necessary support and
coordination to start construction, necessary monitoring (as required by the project permits) ,
construction phase administration and post-construction services to fulfill permit requirements.
At the County's request, sea turtle nesting surveys will be conducted by County staff, and daily
construction observations will be conducted by County staff experienced in beach nourishment
projects.
The following tasks detail the efforts required throughout the construction phase and immediate
post-construction of the Sector 7 project:
Task 1 Site Inspections and Meetings
ATM will perform site inspections and conduct weekly progress meetings. Based on
discussions to date, it is anticipated that the contractor will commence sand placement on mid-
to end of March . ATM will conduct weekly inspections and conduct on-site progress meetings
March 14th through M!X 18th. Prior to March 14th ATM will conduct weekly conference calls
beginning February 28 . The budget for this task also includes an allowance for contractor
coordination and review of the contractor's requests for payment. This budget for this task is
based on combined trips and meetings for both the Sectors 1 & 2 and Sector 7 portions of the
project.
ATM will prepare and provide the County with meeting notes for each weekly conference call
and meeting.
Task 2 Agency Coordination and Project Certification
ATM will provide agency coordination as needed and will provide project certification upon
completion of the project. Due to the nearshore hardbottom, the regulatory agencies interest in
this project will require significant coordination and interaction , and ongoing coordination and
updates will be provided. This task will also allow for proactive coordination with the regulatory
agencies should any project permit related or regulatory issues arise during construction or
though the County's Substantial Completion .
If needed, ATM will request an permit extension for the placement of the sand from May 1st to
May 15`". The request will require continuous coordination with all agencies.
Upon the contractor's completion of the project to the satisfaction of the ATM , ATM will provide
the County and regulatory agencies project certification per permit requirements .
ATM will provide the County updates via e-mail of any significant conversations or e-mail
exchanges with the regulatory agencies, and will be billed on a time and materials basis. At
ATM 's discretion, Coastal Eco-Group may be consulted on a time and materials basis. ATM will
also provide the County, DEP and USACE with project certification.
Task 3 Sediment Sampling and Reporting
Per permit requirements, sand samples need to be collected and analyzed. Sand samples (two
repetitive) need to be collected at two cross-shore locations at each Y monument station (e.g. ,
R-971 R-97.51 R-98, etc.) upon the County's acceptance of the pay section. The samples will be
collected by ATM staff as part of site visit (Task 1 ) . ATM will be in close coordination with
County staff in the regarding the collection of the samples. Collected samples will be provided
to and analyzed to ASTM standards by a qualified lab (SEA) .
ATM will provide the necessary regulatory agencies and the County with the laboratory analysis
of the sand samples.
Task 4 Shorebird Monitoring
ATM will provide monitoring of nesting and non-breeding (limited to FL breeding species)
shorebirds per permit requirements. The monitoring effort will be conducted under the
supervision of a FWC-approved shorebird monitor. ATM will responsible for the monitoring and
data reporting, but will include County staff. In preparation for the monitoring County staff will
mark the location of each DEP '% monument station (e .g. , R-97 , R-97.5, R-98, etc.) . Prior to
April 1 ", The FWC-approved ATM biologist- in-charge will train the monitoring staff (1 ATM field
biologist and 1 County staff) . The budget is based on County staff, once trained) conducting 13
days of monitoring. The shorebird monitoring will commence April 1 ". During the 1S, week of
monitoring the will provide up to 7 days of direct supervision of the shorebird monitoring
personnel. After April 7`", the shorebird monitoring will be conducted by one of the personnel ,
and will be conducted under the direction of FWC-approved ATM biologist-in-charge. Shorebird
monitoring will continue though May 15`" unless construction is completed prior to May 15`"
The shorebird monitoring will be performed in the morning , and direction will be given to the
dredge contractor as early as possible.
ATM will provide weekly reporting to the regulatory agency as required by FWC protocol. The
County will provide a dedicated ATV for this effort.
EXHIBIT W
COST PROPOSAL
I:\PROPOSALS\DMIAN RIVER COUNTYIP-1034 WORK ORDERSJ AND 6\ATM WORK ORDER 5-DOC
At chmeMB
Work Order 5 - Attachment B
Sector 7
Construction Phase and Immediate Post-Construction
ATM Other
Task Description and Breakdown Total Subcontractor ATM Total Direct Costs Total Task
Labor (ODC's) & Budget
Equipment
Task 1 Site Inspections and Coordination $0 $16,320 $1 , 935 $18, 255
Task 2 Agency Coord and Project Certification $0 $10,950 1 $649 1 $11 , 599
Task 3 Sediment Sampling and Reporting $8,9761 $3,660 1 $183 1 $12, 819
Task 4 Shorebird Monitoring $0 $56,440 $6,475 $62, 915
Total asorder Costs $8,978 1 $37,370 59,242 5108,888
EXHIBIT ` C '
Project Schedule
J:W2OPOSALS\INDIAN RIVER COUNT]1P- 1034 WORK ORDERS AND 6WTM WORK ORDER SDOC
Attachment C - Schedule
February 2007
Work Order 5
Indian River County Beach
Sector 7
Construction Phase and Immediate Post-Construction Services
Task Date of
Completion/Deliverable
1 Site Inspections and Meeting May 2007
2 Agency Coord and Project Cert. June 2007
3 Sediment Sampling June 2007
4 Shorebird Mon. May. 2007