HomeMy WebLinkAbout2005-013 INDIAN RIVER COUNTY , FLORIDA
t CHANGE ORDER NO .2
PROJECT NO : 9327 PROJECT : Milling , Resurfacing and Shoulder Paving
CONTRACTOR : E . J . Breneman L . P . on CR 512 from SR 60 to Fellsmere Farms and
1117 Snyder Road on Oslo Road from 20th Ave . to 27th Ave .
West Lawn , Pa . 19609 DATE ISSUED :
ITEM DESCRIPTION OF CHANGE QTY UNIT UNIT PRICE PRICE PRICE
NO . INCREASE DECREASE
1 Repair soft areas due to clay TN 512 $ 100 . 51 $51 ,461 . 12
2 Leveling due to storm damage TN 628 $20 . 67 $ 121980 . 76
3 Milling and grading at boat ramps LS 1 $3 , 533 . 25 $3 , 533 . 25
4 Aggregate for shoulder backup TN 496 $43 . 09 $219372 . 64
5 334- 1 2 " SP 12 . 5 , LEVEL C TN -21140 $46 . 50 -$ 99 , 510 . 00
6 573- 1 Hydroseed SY -969000 $0 . 25 -$24 , 000 . 00
7 706-3 REFLECTIVE PAVEMENT MARKERS EA -823 $3 . 70 -$ 3 , 045 . 10
8 710-22-61 SKIP , 6" YELLOW PAINT LF -51950 $0 . 22 -$ 1 , 309 . 00
9 710-23-61 SOLID , 6" WHITE PAINT LF 109 , 340 $0 . 12 $ 13 , 120 . 80
10 710-23- 181 SOLID , 18 " WHITE PAINT LF 60 $ 1 . 10 $66 . 00
11 710-23-241 SOLID, 24 " WHITE PAINT LF -59 $ 1 . 60 -$94 . 40
12 710-24-61 SOLID , 6 " YELLOW LF 11 , 047 $0 . 12 $ 17325 . 64
13 575- 1 SODDING ( BAHIA) SY -2 , 600 $ 1 . 30 -$3 , 380 . 00
SUBTOTAL $ 103, 860 . 21 ($ 131 , 338 . 50 )
NET CHANGE -$27 , 478 .29
ORIGINAL CONTRACT PRICE/TIME $ 1 , 326 , 909 . 00
CURRENT CONTRACT PRICE/TIME $ 1 , 285, 161 . 00
AS ADJUSTED BY PREVIOUS CHANGE ORDERS
NET CHANGE IN CONTRACT PRICE/TIME ($27 ,478 . 29 )
DUE TO THIS CHANGE ORDER
NEW CONTRACT PRICE/TIME INCLUDING $ 19257 ,682 . 71
THIS CHANGE ORDER
ORIGINAL SUBSTANTIAL COMPLETION DATE August 31 , 2004
SUBSTANTIAL COMPLETION DATE AFTER THIS CHANGE ORDER September 30, 2004
FAPublicWorks\Capital Projects\Oslo 43rd\Change Order\Change OrderNo2.xls 12/8/2004
OSLO & 43rd AVENUE
CkANGE ORDER NO. *
s PAGE 2 of 2
ENGINEER'S RECOMMENDATION :
I have examined the above changes . They are necessary to satisfactorily complete the contract.
The price changes are reasonable and I recommend that the changes be made .
Terry B . T o pson , P . E . , Project Manager Date
CONTRACTOR'S APPROVAL :
I agree that the above changes in said Contract, in accordance with Specifications for the price
changes sh_ovvf'li are satisfactory .
12 / 6104
J n M . DeMartino, Partner, E .J . eneman L . P . Date
ACCEPTED BY:
Approved as to for and legal s iciency:
23 ��
• n Aftorndy Date
ONa3Lit
eph A. Bad Da e
unty Administrator
BOARD OF COUNTY COMMISSIONERS
INDIAN RIVER COUNTY
" Indian River Approved Date
a - County
01 - 04 - 2005 Admin. 1a
Tho Cx}d Date Budget
Chairmai f w issioners Legal 2
Risk Mgt.
+ � • Public Works
€ ' Cap. Proj.
,/ •• f k ,s h Date
Deputy
r t-
F:\PublicWorks\Capital Projects\Oslo 43rd\Change Order\http://192. 168.0. 108/exchange/Jdemarti/Inbox/Change Order No. 2 and Final Payment
Application. EML/1 _multipart_xF8FF_4_Change OrderNo2.xls/C58EA28C-18C0-4x97-9AF2-036E93DDAFB3/Change OrderNo2.xls?attac