Board of County Commissioners.
180127th Street
Vero Beach, Florida 32960
Telephone : (772) 567= 8000
FAX : 772= 778=9391
WORK ORDER NO . 13 (Engineering )
FOR
PROFESSIONAL BRIDGE DESIGN SERVICES AGREEMENT
FOR ANNUAL BRIDGE DESIGN SERVICES CONTRACT
WITH
Bridge Design Associates , Inc .
This Work Order No . 13 is in accordance with the existing AGREEMENT dated October 3 ,
2006 between Bridge Design Associates , Inc . (ENGINEER) and Indian River County
( COUNTY) .
This Work Order No . 13 amends the agreement as follows :
SECTION I — PROJECT LIMITS
57`h Street Bridge over Lateral "A" Canal
SECTION II — SCOPE OF SERVICES
This Work Order No . 13 is for providing modification to the design phase and for construction
phase service ( construction engineering and inspection) for the above mentioned project .
SECTION III = TIME FOR COMPLETION
90 calendar days from notice to proceed for final design modification and permits .
SECTION IV — COMPENSATION
The COUNTY agrees to pay, and the ENGINEER agrees to accept , a fee for services
rendered according to the " Scope of Services " identified in Section II and III of this Work
Order No . 13 as follow :
Lump Sum Fee for modification of current design : $ 14 , 520 . 00
Ir
Not To Exceed fee for Construction Phase Services : $ 22 , 135 . 00
Not to Exceed GRL Pile Testing : $ 51000 . 00
S :APERS0NNEL\Kim\2008\December 2008\BCCBridgeDesignWorkOrderNo. 1312 -22 -08 .doc
PAGE TWO
Work Order No . 13 Bridge Design Associates , Inc .
January 6, 2009 BCC agenda
The AGREEMENT is hereby amended as specifically set forth herein . All remaining sections
of the AGREEMENT shall remain in full force and effect , and are incorporated herein .
IN WITNESS WHEREOF the parties hereto have executed these presents this
6th day of January 2009 ,
BRIDGE DESIGN ASSOCIATES , INC . INDIAN RIVER COUNTY , FLORIDA
BOARD O COUNTY COMMISSIONERS
BY : BY ,
WESLEY S . DAMS ; CHAIRMAN
Title : BRIAN C . RHEAULT , P . E . ,
PRESIDENT
Approved by the BCC : ' "
Witnessed By : _ ATTEST :
---� JEFFREY i(.--)3 ARTON - -
CLERK OF CIkCU1T �' OVRT
BY : �
DEPUTY CLERK OF COURT
tSEPHIRD
OR
.4WILLIAM G . COLLINS , II
COUNTY ATTORNEY
Approved as to Form and Legal Sufficiency
S :APERS0NNEL\Kim\200Mecember 2008\BCCBridgeDesignWorkOrderNo. 1312 -22-08 . doc
BRIDGE DESIGN ASSOCIATES , INC .
CONSULTING ENGINEERS
BRIAN C. RHEAULT, P.E.
President
December 15 , 2008 DEC 17
2008
Indian River County
1800 271h Street _
Vero Beach , Florida 32960
rfsc 0 L
ATTENTION : Chris Kafer, P . E .
REGARDING : 57T" Street Bridge over Lateral "A" Canal
Dear Chris :
Pursuant to your request Bridge Design Associates , Inc. can modify the existing
replacement bridge plans prepared in 2007 to lower the proposed bridge approximately
T-0 feet .
The bridge plans will also incorporate provisions so that the bridge can be raised in the
future re-using both the substructure and the superstructure components .
New guardrail attachments and approach slabs will be required when the bridge is raised .
The piles will be designed to accept the future pile cap extension and jacking forces
required to raise the bridge superstructure .
The attached Exhibit "A" is an approximate hourly breakdown of tasks for the design phase
of the project and Exhibit " B " is the construction phase services .
If you have any questions , please give me a call .
Respectfully,
BRIDGE DESIGN ASSOCIATES , INC .
Brin C . Rheault, P . E . , #38797
President
BCR : kedS:\2008-Jobs\PROPOSALS - RFPS\57th Street & 66th Avenue\proposal 12- 15-08 . wpd
1402 Royal Palm Beach Boulevard • Building 200 • Royal Palm Beach , Florida 33411
(561 ) 686-3660 9 Fax : (561 ) 791 - 1995
BRIDGE DESIGNS ASSOCIATES, INC.
57TH STREET BRIDGE OVER LATERAL "A" CANAL
December 15, 2006
HOURLY BREAKDOWN OF SERVICES
EXHIBIT "A"
PROJECT PROJECT FIELD REP CAD TOTAL LABOR
MANAGER EHGU#M EJ- TECHMICfAN HOURS COST
ACTIVITY BY BY
ACTMITY ACTIVITY
$145.00 $115. 00 $60. 00 $80. 00
Cover Street 4.0 4.0 $320. 00
Modify Summary Sheet Quantities 4.0 4.0 8.0 $560.00
Mod' Plan Sheet 4.0 4.0 $320.00
Modify Elevation Sheet 4. 0 4.0 $320. 00
Modify Substructure pile n 0.0 $0.00
Modffy Pile Date table 4.0 4.0 8.0 $780.00
Modify finish grade plan 4.0 4.0 8.0 $780.00
Modify end bent #1 8.0 4.0 8.0 20.0 $1 ,800.00
Modify end bent #2 2.0 8.0 10.0 $870.00
Modffy end bent details 2.0 8.0 8.0 18. 0 $1 ,850.00
Modify Post Tension Details 4.0 4.0 8.0 $780.00
4.0
Modffy closure pours 4.0 4.0 $320.00
Revise quantfies and cost estimate 20 8.0 10. 0 $770.00
Coordinate with roadway and su 6.0 6. 0 $870.00
File IRCWCD Permit 8.0 4.0 12.0 $1 ,240.00
File ACOE Permit 8.0 4.0 12.0 $1 ,240. 00
File SJWCD Permit 8. 0 4.0 120 $1 ,240.00
TOTAL MANHOURS 10.0 58.0 16.0 68.0 148.0
DIRECT LABOR COST $1 ,450.00 $6,670.00 $960.00 $5,440.00 $14,520.00
$14,520.00
812008-Jobs1PROPOSALS - RFPS157th Street & 66th Aveenuelprorwsal 12- 15-08
1 �
BRIDGE DESIGN ASSOCIATES , INC .
57TH STREET BRIDGE OVER LATERAL OX CANAL
CONSTRUCTION PHASE SERVICES
December 15, 2006
HOURLY BREAKDOWN OF SERVICES
EXHUT Ir
PROJECT PROJECT FIELD REP CAD TOTAL LABOR
MANAGER ENGINEER EJ. TECHNICIAN HOURS COST
ACTiV1TY BY BY
$145.00 $115.00 $60.00 $80.00 ACTIVITY ACTIVITY
Pre Construction Meeti 5.0 5.0 10.0 $1 ,025.00
Shop Drawing Reviews / concrete mix, best pile
pre-cast com 2.0 16.0 16.0 34.0 $3,090. 00
Pile Casting / Sheet Piles 80.0 80. 0 $4.800.00
Pile Driving 64.0 64.0 $3,840M
Pile Caps 16.0 16.0 $960.00
Prestressed Placement ! Closure Pour 12.0 12.0 $720.00
Post Tensioning 2.0 2.0 12.0 16.0 $1 ,240.00
Sidewalks 8.0 8. 0 $480.00
Barriers 16.0 16.0 $960.00
N?proach Slab 16.0 16.0 $960,00
Approach Slabs sidewalks 16.0 16.0 $960.00
roach Slab barriers 24.0 24.0 $1 ,440.00
Revetment & misc. pipes 16.0 16.0 $960. 00
Final Inspection 2.0 2.0 4. 0 $410. 00
Final Report & Certification 2.0 2.0 $290.00
0.0 $0. 00
0.0 $0. 00
TOTAL MANHOURS 13.0 18.0 303. 0 0. 0 334.0
DIRECT LABOR COST $1 ,885.00 $2,070.00 $18, 180.00 $0.00 $22, 135.00
ENGINEERING FEEES $22, 135. 00
GRL TEST PILE $5,000. 00
TOTAL FEES $27, 13,5. 00
SA2008-Jobs1PROPOSALS - RFPSl57th Street & 66th Avenuelproposal Exhibit 8