HomeMy WebLinkAbout2009-078 - r77 oq
Q78
AMENDMENT NUMBER 5 WORK ORDER NUMBER 1
This Amendment Number 5 to Work Order Number 1 ( " Amendment") is entered into
as of this 17th day of March 2009 Effective Date " ) pursuant to that
certain Continuing Contract Agreement for Professional Services entered into as of April 6, 2004
( "Agreement" ), by and between Indian River County, a political subdivision of the State of
Florida ( " COUNTY") and Camp Dresser & McKee Inc . ( "Consultant" ) .
1 . The COUNTY has selected the Consultant to perform the professional services set
forth in Work Order Number 1 dated April 13, 2004 .
2 . The COUNTY and the Consultant desire to amend Work Order Number 1 as set forth
in Attachment A to this Amendment and made a part hereof by this reference all in accordance
with the terms and provisions set forth in the Agreement.
3 . From and after the Effective Date of this Amendment, Work Order Number 1 is
amended as set forth in this Amendment. Pursuant to paragraph 1 . 4 of the Agreement, nothing
contained in any Work Order shall conflict with the terms of the Agreement and the terms of
the Agreement shall be deemed to be incorporated in each individual Work Order as if fully set
forth herein .
IN WITNESS WHEREOF, the parties hereto have executed this Amendment as of the
Effective Date first written above .
CONSULTANT BOARD OF COUNTY COMMISSIONERS
Camp Dresser & McKee Inc . OF INDIAN RIVER COUNTY
By : By
Eric J . dtke, P . E . , BCEE Wesley S . Davis, Chairman
Principal Engineer
BCC : Approved :
Attest: J . K . Barton, Clerk of Court
By: � � -
Deputy Clerk
Approved .0
JtMaian
. aird, County Admini trator
d as to fo gal sufficiency:
. Fe , Assistant County Attorney
j12142.doc
ATTACHMENT A
Part A
PROJECT DESCRIPTION
The North County Water Treatment Plant expansion has been under construction for the last
two years . This amendment is a final reconciliation of additional engineering services rendered
by CDM throughout the course of construction . Indian River County Utilities staff, CDM and
the Contractor have worked closely to contain capital cost of the plant while increasing the
plant' s productivity .
This phase of the project was originally intended to add to add three more functioning
nanofiltration skids ( treatment trains that purify 1 . 5 million gallons each of water per day) with
three additional skids being installed but not loaded with membranes . The final project loaded
two of those three skids with membranes . This provided the ability to purify an additional
3 . OMGD of water which can be blended with 1 .29MGD of well water for distribution .
The expansion provided Indian River County with operational flexibility and reliability, as well
as reserve water treatment capacity to meet future demands, enhancing the overall water utility .
This amendment is the final reconciliation amendment to close out the project compensating
CDM for the engineering services necessary for the successful completion of the project.
COMPENSATION FOR SERVICES
North County WTP - Phase II Expansion Services
Amendment No . 5
Task 3 - Permitting Services $ 10,000 Lump Sum
Task 6 - Out of Scope Construction Services $62,500 Lump Sum
Total $ 72,500
CDM will submit monthly invoices for services performed .
A- 1 1121 a2.doc
ATTACHMENT A
Part B
SCOPE OF WORK
INDIAN RIVER COUNTY
NORTH COUNTY WATER TREATMENT PLANT
AMENDMENT NO . 5 - FINAL RECONCILIATION AMENDMENT FOR
ADDITIONAL PERMITTING AND ENGINEERING SERVICES
BACKGROUND
The North County Water Treatment Plant (NCWTP) is a permitted 3 . 53 million gallons per day
(mgd) (3 . 0 mgd of permeate) facility serving northern Indian River County (IRC ) . Construction
of the original water plant began in June 1996 and was placed into operation in July 1998 . The
facility utilized two 1 . 5 mgd membrane treatment nanofiltration skids and incorporated a raw
water blend rate of approximately 15 percent (0 . 53 mgd ) to achieve the facility finished water
capacity of 3 . 53 mgd . The facility layout was designed for future expansion at such time
customer demand in the North County service area warranted .
This Admendment is for the close out of the Phase II plant expansion which was successfully
bid and the contract was awarded to Poole and Kent of Florida to construct the plant. This
phase was to add three new 1 . 5 mgd nanofiltration skids along with three skids for future water
production which will be installed without membranes . The actual project added five new skids
with membranes and one empty skid for future expansion . This will allow for additional water
production without a major plant upgrade after the well field has been expanded to provide the
necessary raw water supply. This amendment is for additional services expected for
unanticipated permitting services and additional engineering services during construction .
SCOPE OF SERVICES
CDM shall provide additional engineering services related to extra permitting in Task 3, and
supplementary construction services in Task 5 . The original project design activities started in
2004 and the construction oversight period and scope of work have been modified over the last
four years due to various project changes . During the construction period, additional items
have been added to the project or modified, which upgraded the facilities improving the ability
to economically expand the plant in the future and efficiently operate the plant. CDM has
worked closely with IRC staff to minimize additional engineering effort associated with the
plant expansion .
The following described engineering services are additional scope items not previously covered
in the Phase II plant expansion Amendments 1 , 2, 3, and 4 . The following descriptions are for
additional services to be covered under this amendment:
Task 1 . 0 Preliminary Design (No Changes in this Amendment)
Task 2 . 0 Preparation of Contract Documents (No Changes in this Amendment)
Task 3 . 0 Permitting Services (Amendment No . 5 Additional Services)
A-2 i121 a2 . doc
This task provides for the preparation of necessary permit applications, meetings, and
negotiations with regulatory agencies and preparation of one response to Request for
Additional Information (RAI) from IRC Planning and Zoning and Florida Department of
Environmental Protection (FDEP) .
■ A change was initiated by IRC that increased water production (by loading additional skids
with membranes ) and produced a deductive change order for the construction project. The
contractor was to replace the nanofilitration membranes in the existing skids 1 and 2 with
new membranes . Since the existing membranes are performing well, the decision was made
to keep them in place and load two skids that were to be left empty during this expansion .
This saves IRC the expense of removing the existing membranes and gives operational
flexibility to the plant so the pumps can be exercised regularly and other maintenance can be
performed without disrupting water production . These changes will require performance
testing and test result review . These changes will have to be incorporated into the
certification of the construction permit to FDEP .
■ IRC has also made some field changes regarding the location and amount of impervious area
by relocating sidewalks from areas of little traffic to areas of greater traffic . While these
changes do not negatively affect the project contract price the changes will have to be
demonstrated to the IRC planning and zoning as a deviation from the permitted plan .
Preparation of additional documentation for planning and zoning was required .
Task 4. 0 Bidding Assistance Services (No Changes in this Amendment)
Task 6. 0 Out of Scope Services During Construction
Contract Extension
The contract administration task has increased in duration as a result of the concentrate permit
delays that impacted the procurement of the FDEP construction permit . The following time line
illustrates the extent of the project being lengthened .
Advertisement to Bid : June 30, 2006
Bid Opening: August 16, 2006
Construction Contract November 14, 2006
Notice to Proceed January 12, 2007
Issuance FDEP Permit April 23, 2007
Extended NTP April 27, 2007
The notice to proceed was extended by 105 days for the contractor because site work could not
commence until the FDEP permits were in place . This provided the contractor with additional
time for generating requests for additional information and could have resulted in a delay
change order for IRC, which was tabled through the efforts of IRC staff and CDM .
Additional RFI Reviews
One of the cost containment measures was to limit the engineering oversight of the Resident
Project Representative (RPR) . The periodic field representative task was subcontracted through
temporary labor service provider. This greatly reduced RPR cost to the project . IRC used staff
A-3 112142.doc
inspectors to further reduce the engineering oversight costs required for this project; however
the extended project time has increased the number of requests for additional information and
submittals . There have been 81 requests for additional information to date in this project .
Accelerated Walkthroughs
In an effort to reduce the potential for a delay change order to the construction contract, IRC is
considering accelerating substantial completion inspection for the contractor . While this creates
more effort in the inspection process, it improves the contractor's ability to provide final
payment on materials that are benefiting IRC . This arrangement increases the contractor's
motivation to finish early or on time by improving their cash flow .
Membrane Procurement
Procurement of the nanofiltration membranes was originally in the contract as the contractor ' s
responsibility . IRC processed Change Order No . 1 to remove that responsibility from the
contractor and realized a cost savings of $44,000 in sales taxes by direct purchasing the
membranes . CDM has assisted IRC with the change order and the procurement of the
membranes . This effort was beyond the original scope of work .
Additional Pay Application Review
CDM has incurred out of scope costs associated with review of the pay application for
reduction in retainage . CDM worked with staff to provide input into a reduction in retainage
agreement for the contractor to be paid for substantially complete portions of the plant which
benefit IRC This task is for the additional effort in reviewing these pay applications and
contract amendments .
Instrumentation Review and Coordination
The instrumentation for a project of this magnitude is very complex . CDM has provided more
support for the instrumentation system supplier than estimated . These efforts were for review
of system enhancements and equipment selected by the instrumentation system supplier.
Wellfield Electrical Coordination
The NCWTP and the wellfield development had to be coordinated at the plant. The wellfield
configuration was different from the design expectations used in the yard piping and the
electrical duct banks onsite . Most of the wells were to be powered by the onsite switch gear
allowing the generator system to provide backup power. Modifications to the onsite duct banks
were made to accommodate the wellfield changes . This work was not in the original scope of
work .
Stormwater Discharge Monitoring
In the course of the construction project, the contractor encountered discolored groundwater
that was displaced when the yard piping was being installed . This anomaly required additional
effort to ensure the construction contract was not negatively affected by this occurrence . CDM
incurred additional effort to meet with the County' s stormwater discharge compliance officer,
which was not foreseen in the original scope of work .
A4 112142 . doc
Start Up Services and O &M Manuals
The original contract specifically excluded start up services and Operation and Maintenance
(O&M) Manuals . CDM provided limited start up services to review operating equipment and
also reviewed O&M Manuals submitted by Contractor.
Additional Record Drawing Production
The original scope of work for the design of the plant expansion identified 139 drawings for the
design of the plant. The actual number of sheets for the plant design was 169 sheets . This task is
for the effort to conform the project record drawings beyond the original scope of the project.
This task does not seek to recover the additional design costs for these sheets .
SCHEDULE
The project is expected to be complete within the next 30 days .
A- 5 j12142. doc
ATTACHMENT A
Part G- 1
PROJECT BUDGET
INDIAN RIVER COUNTY
NORTH COUNTY WATER TREATMENT PLANT
AMENDMENT NO . 5 - ADDITIONAL PERMITTING and ENGINEERING SERVICES
PROJECT
DESCRIPTION: North County WTP - Phase II Expansion
Task 3 . 0 - Additional Permitting Services
CategorX Hours Rate Cost
Officer 0 $ 160 $0
Principal / Associate 2 $ 140 $280
Senior Professional 14 $ 120 $ 1 , 680
Professional II 24 $ 105 $2,520
Professional I 12 $90 $ 1 , 080
Senior Support Services 40 $75 $3,000
Staff Support Services 12 $65 $780
Project Administration 0 $65 $0
TOTAL HOURS 104
SALARY $9,340
OTHER DIRECT COSTS $660
OUTSIDE PROFESSIONAL $00
TOTAL ESTIMATED COSTS - LUMP SUM $ 10 ,000
A-6 j12142.doc
ATTACHMENT A
Part C-2
PROJECT BUDGET
INDIAN RIVER COUNTY
NORTH COUNTY WATER TREATMENT PLANT
AMENDMENT NO . 5 - ADDITIONAL PERMITTING and ENGINEERING SERVICES
PROJECT
DESCRIPTION : North County WTP - Phase II Expansion
Task 6 . 0 - Out of Scope Construction Services
Category Hours Rate Cost
Officer 6 $ 160 $960
Principal / Associate 14 $ 140 $ 1 ,960
Senior Professional 238 $ 120 $28,560
Professional Il 104 $ 105 $ 10,920
Professional I 42 $90 $3, 780
Senior Support Services 15 $ 75 $ 1 , 125
Staff Support Services 151 $65 $9,815
Project Administration 8 $65 $520
TOTAL HOURS 578
SALARY $57,640
OTHER DIRECT COSTS $4,860
OUTSIDE PROFESSIONAL $00
TOTAL ESTIMATED COSTS - LUMP SUM $62,500
A- 7 j12142 . doc
ATTACHMENT A
Part C4
ESTIMATED PROJECT LABOR DISAGGREGATION
NORTH COUNTY WATER TREATMENT PLANT
AMENDMENT NO. 5 - ADDITIONAL PERMITTING and ENGINEERING SERVICES
Officer PrincipaU Senior Staff Senior Professional Professional Project
Associate Professional 11 1 Support Support Administration Total
Description Services Services
Task 3. 0 Additional Permitting Services
Final Certification of Plant Permit FDEP with 7 skids 0 0 6 24 0 24 0 0 54
Site Plant permits minor modifications Impervious area 0 2 8 0 12 16 12 0 50
Subtotal Hours : 0 2 14 24 12 40 12 0 104
Task 5 General Services During Construction
Additional RFI review because of contract extension 0 2 60 80 0 0 40 2 184
Accelerated walk throw hs 3 at 8 hours each 2 4 24 0 0 0 6 0 36
Membrane Procurement 0 4 8 0 2 0 0 2 16
Additional Pay Applications Review 2 0 16 0 0 0 10 0 28
Additional Electrical Effort for Generator 0 2 42 12 0 0 0 2 58
Instrumentation Review and Coordination 2 2 48 8 0 0 8 2 70
Wellfield Electrical Coordination 0 0 12 4 0 0 2 0 18
Stormwater Discharge Monitoring 0 0 8 0 0 0 1 0 9
Start Up Services and O& M Manuals 0 0 12 0 40 0 4 0 56
Record Drawings on Additional 30 sheets 8 0 0 15 80 0 103
Subtotal Hours : 6 14 238 104 42 15 151 8 578
TOTAL 6 16 252 128 54 55 163 8 682
A-8 i12142. doc