1. PROJECT DESCRIPTION
Consulting Engineering services to provide Engineering services to evaluate the
feasibility of modifying the Class I Landfill sideslopes to increase the amount of airspace
available . This is an effort to maximize the available space for Class I Waste and to
increase the life of the landfill site . Also, included is the submittal of a modification to
the Indian River County (IRC) Class I Operating permit.
if. SCOPE OF SERVICES
Reference is made to Attachment B, the attached Scope of Services and the " Professional
Engineering Services Master Agreement for Solid Waste" .
III. CONSULTING ENGINEER INSURANCE REQUIREMENTS
A . Workers Compensation Insurance in accordance with Florida Statues ,
B . Automotive Liability with coverage of $1 ,000, 000 for a combined single limit.
C . General Liability with a limit of $2, 000,000 for general aggregate damage .
D . Professional Liability with an aggregate limit of $3, 000,000 .
IV. COMPENSATION FOR SERVICES
Task 1 . 0 Landfill Geotechnical Evaluation Not To Exceed $ 17,900
Task 2 . 0 Modification of Class I Landfill
Operating Permit Not to Exceed $ 25 ,300
Total $ 43,200
A-1 rb4475.doc
Not To Exceed Cost Elements - Salary Cost Basis with Upper Limit
For the basic services performed on a salary cost basis with an upper limit, IRC
agrees to pay CDM as follows :
For engineering services performed by CDM, the payment will be equal to the
salary cost of such services for each employee times 2 . 35 for overhead and profit
plus actual out-of-pocket expense costs . Salary cost is equal to 1 . 393 times direct
salary costs and is defined as the cost of salaries (including sick leave, vacation,
and holiday pay applicable thereto) for time directly chargeable to the project;
plus unemployment, excise, and payroll taxes; and contributions for social
security, employment compensation insurance, retirement benefits, and medical
and other group insurance benefits .
Actual out-of-pocket expense costs are all costs other than salary costs that are
incurred during the progress of the work . The actual out-of-pocket expense costs
include : air fare, automobile rental if required, mileage charges, parking tolls,
taxi, meals, and lodging all in accordance with reimbursement rates set forth in
Section 112 . 061 , Florida Statutes (1999) , as amended, and telephone, printing and
reproduction costs, and other miscellaneous costs incurred specifically for this
project. The maximum cost for blueprint sheets is $1 . 10 . The maximum cost for
mylar sheet is $11 . 00 and sepia sheet is $5 . 00 . The charges for in-house computer
program and word processor usage will be at CDM' s regular rates . For outside
computer services, charges will be made at invoiced cost to CDM.
SUBMITTED BY : APPROVED BY:
CAMP DRESSER & McKEE INC . INDIAN RIVER COUNTY
Solid Waste Disposal District
u B,Y:
ex H . Makled, P. E . , DEE --Kenneth R. acht
Vice President Chairman
BCC Approved : 09 - 16 - 2003
Witnessed by : Attest: J . K. Barton, Clerk
By : Deputy Clerk
� .
w
i
A-2 AN E . FEL 4475 .doc
Sf ANT COUNTY ATTORNEY
ATTACHMENT B
SCOPE OF SERVICES AND PROJECT SCHEDULE
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
ENGINEERING SERVICES FOR
LANDFILL GEOTECHNICAL EVALUATION
PROTECT UNDERSTANDING
Indian River County (IRC) is interested in modifying the design of the final landfill scope
geometry to provide more air space in the landfill . CDM will provide consulting services to
evaluate the feasibility of modifying the Class I Landfill sideslopes to increase the amount of
airspace available . The current design includes 3H : 1V side slopes with terraces every 20 feet of
vertical rise . The proposed geotechnical evaluation will consider a range of revised slopes and
terrace locations and widths to increase the air space in the landfill. In addition, preparation of a
permit application to modify the Class I Operations permit is included as Task 2 . 0 in this
proposal .
TASK 1 . 0 - LANDFILL GEOTECHNICAL EVALUATION
The following is the proposed scope of work for the geotechnical evaluation. This proposal
assumes that we can base the evaluation on existing geotechnical data and reports and that we
will need only a limited field investigation. This work is expected to proceed with the following
subtasks :
■ Review available information including design documents and previous geotechnical
reports . We will visit the site to observe site conditions . We have assumed that there is
sufficient available geotechnical information and that no additional field or laboratory
investigations are needed .
■ Estimate settlement of the final cover system based on the revised slope geometry .
■ Perform global stability analyses of the landfill mass .
■ Perform veneer stability analyses of the proposed cap system.
■ Evaluate settlement-induced strain in the liner due to foundation settlement.
■ Evaluate the Geocomposite drainage layer .
■ Prepare a letter report presenting the results of our analyses .
TASK 2 . 0 - LANDFILL OPERATIONS PERMIT MODIFICATION
CDM will prepare a modification of the IRC SWDD Landfill Class I Operations permit which
includes the results of the landfill geotechnical evaluation approved by IRC . This proposal has
been budgeted on the assumption that Florida Department of Environmental Protection (FDEP)
B-1 rb4475 .doc
will consider this an intermediate modification of the Class I Operations permit. CDM expects
to complete the following portions of the FDEP Solid Waste Application form to modify the
permit:
■ Complete Part A General Information
■ Complete Part B Disposal Facility General Information
■ Complete Part E Solid Waste Management Facility Permit Requirements, General
■ Complete Part F Landfill Permit Requirements — prepare Plot Plan and revised
Topographic Plan for the Class I Landfill . Also included is updated Class
I facility life information.
■ Complete Part J Geotechnical Investigation Requirements — this will be the letter report
developed for the Geotechnical analysis .
■ Modify Part L Landfill Operation Requirements
■ Modify Part P Landfill Closure Requirements — existing cross sections will be modified
to show the changes to the Class I Landfill . Also changes to the
stormwater letdowns will be shown .
■ Complete Part T Certification by Applicant and Engineer
A contingency has also been added to allow for CDM to address any issues raised by FDEP
during the Pre-Application meeting. This will cover additional figures, tables, or language
needing to be written to address any concerns for the initial submittal to FDEP .
CDM has also budgeted 3 meetings with IRC SWDD and 1 Pre-Application meeting with FDEP
to discuss the geotechnical evaluation and permit modification submittal to FDEP .
CDM will respond to one Request for Additional Information ( RAI) by FDEP .
CDM will request on SWDD ' s behalf that the yard trash operation be placed under the General
Operating Permit in this modification. This will relieve the County of their yearly yard trash
operation registration commitment. Placing the yard trash operation into the General Operating
Permit is expected to be covered with a simple request in the larger permit modification. This is
the most economical way to make the transition since the permit modification fee is much
greater than the yearly registration fee . No contingencies are specifically made in the budget if
FDEP has an RAI for this item.
SCHEDULE
Task Completion Date
1 . 0 Landfill Geotechnical Evaluation October 30, 2003
2 . 0 Modify Class I Operations Permit November 30, 2003
B-2 rb4475 .doc
ATTACHMENT C4
PROJECT BUDGET
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
ENGINEERING SERVICES FOR LANDFILL GEOTECHNICAL
EVALUATION & PERMIT MODIFICATION
PROJECT
DESCRIPTION : Indian River County SWDD Landfill
Geotechnical Evaluation& Class I Operations Permit Modification
Task 1 . 0 - Landfill Geotechnical Evaluation
CONTRACT
REFERENCE : Agreement between Indian River County Board of County
Commissioners and Camp Dresser & McKee Inc .
Labor Category Hours Rate Total
Officer 2 $60 . 00 $120
Associate / Principal ( ENEV-7/ 8) 28 $45 . 00 $1 ,260
Engineer (ENEV-5/ 6) 8 $35 . 00 $280
Engineer (ENEV-3/ 4) 120 $25 . 00 $3, 000
Drafter/ Designer 8 $18 . 00 $144
Support 16 $15 . 00 $240
Total Hours 182
Direct Salary Cost $5,044
Indirect Salary Cost (x0 . 393) $1 ,982
TOTAL SALARY COST $ 7,026
SALARY COST TIMES MULTIPLIER (x2 . 35) $16,511
OTHER DIRECT COSTS
Printing, Copies, Communication, Computer $1 ,400
TOTAL ESTIMATED FEE $17, 911
USE 17 900
For the basic services under this Agreement, the County agrees to pay the Consultant a fee not
to exceed of $17, 900 . Partial payments will be made on a monthly basis in accordance with the
referenced contract.
C-1 rb4475.doc
ATTACH -2
PROJECT BUDGET
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
ENGINEERING SERVICES FOR LANDFILL GEOTECHNICAL
EVALUATION & FDEP PERMIT MODIFICATION
PROJECT:
DESCRIPTION : Indian River County SWDD Landfill
Geotechnical Evaluation & Class I Operations Permit Modification
Task 2 . 0 - Class I Operations Permit Modification
CONTRACT
REFERENCE : Agreement between Indian River County Board of County
Commissioners and Camp Dresser & McKee Inc .
Labor Category Hours Rate Total
Officer 4 $60 . 00 $240
Associate/ Principal ( ENEV- 7/ 8) 16 $45 . 00 $720
Engineer (ENEV-5 / 6) 54 $35 . 00 $1 ,890
Engineer (ENEV-3 / 4) 12 $25 . 00 $300
Engineer Intern (ENEV-1 / 2) 100 $20 . 00 $2, 000
Drafter/ Designer 88 $18 . 00 $1 ,584
Support 36 $15 . 00 $540
Total Hours 310
Direct Salary Cost $ 7,274
Indirect Salary Cost (x0 . 393) $2,859
TOTAL SALARY COST $10,133
SALARY COST TIMES MULTIPLIER (x2 . 35) $23,812
OTHER DIRECT COSTS
Printing, Copies, Communication, Computer $ 1 ,490
TOTAL ESTIMATED FEE $25,302
USE
$25 , 300
For the basic services under this Agreement, the County agrees to pay the Consultant a fee not
to exceed of $25,300 . Partial payments will be made on a monthly basis in accordance with the
referenced contract.
C-2 rb4475.doc
ATTACHMENT C-3
DETAILED SUMMARY OF HOURS AND SALARY COSTS
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
LANDFILL GEOTECHNICAL EVALUATION & PERMIT MODIFICATION
Principal/ Engineer ;Engineer Engineer Drafter/
Task/ Description Officer Associate 5/6 4 1 /2 Desi ner Su$60 . 00 $45 . 00
g PPo� Totals
Task 1 . 0 - Landfill Geotechnical Evaluation $ 35 . 00 00 $20 . 00 $ 18 . 00 $ 15 . 00 Hours $
1 . 1 - Site visit 0 8 0 0 0 0
1 . 2 - Geotechnical Evaluation 0 12 4 4 12 $420
80
1 . 3 - Report 0 0 4 100 $2 , 740
28 4 40 0 8 8 70 $ 1 , 884
Subtotal Task 1 . 0 ( Not to Exceed ) 2 28 8 120 0 8 16 182
$ 5, 044
Task 2. 0 - Class I Operations Permit Modification
2 . 1 - Permit Modification 2 4 26 0 60 64
2 . 2 - Contingency 0 4 8 0 20 176 $ 39862
24 16 8 60 $ 1 , 348
2 . 3 - Meeting with SWDD & FDEP
2 4 12 12 0 0 4 34 $ 1$980
8
2 .4 - RAI 1 RAI for FDEP ) 0 4 8 0 16 g
4 40 84
Subtotal Task 2. 0 Not to Exceed) 4 16 54 12 100 88 36 310 $ 7 , 274