HomeMy WebLinkAbout2009-208 WORK ORDER NUMBER 14
This Work Order Number 14 is entered into as of this day of
2009 , pursuant to that certain Continuing Contract Agreement for
P 6fessi6nal Services entered into as of April 6 , 2004 and amended effective April 7 , 2007
( as so amended , the "Agreement" ) , by and between INDIAN RIVER COUNTY , a political
subdivision of the State of Florida (" COUNTY" ) and CAMP DRESSER & McKEE INC .
( " CONSULTANT' ) .
The COUNTY has selected the Consultant to perform the professional services set
forth on Exhibit 1 ( Scope of Work ) , attached to this Work Order and made part hereof by
this reference . The professional services will be performed by the Consultant for the fee
schedule set forth in Exhibit 1 ( Fee Schedule ) , attached to this Work Order and made a
part hereof by this reference . The Consultant will perform the professional services within
the timeframe more particularly set forth in Exhibit 1 (Time Schedule ) , attached to this
Work Order and made a part hereof by this reference all in accordance with the terms and
provisions set forth in the Agreement . Pursuant to paragraph 1 . 4 of the Agreement ,
nothing contained in any Work Order shall conflict with the terms of the Agreement and the
terms of the Agreement shall be deemed to be incorporated in each individual Work Order
as if fully set forth herein .
IN WITNESS WHEREOF , the parties hereto have executed this Work Order as of
the date first written above .
CONSULTANT : BOARD OF COUNTY COMMISSIONERS
CAMP DRESSER & cKEE INC . OFjNQIAN RIVER COUNTY
By : Bim-
4es ey S . avi Chairman
Title : Principal Engineer
BCC Approved Date : July 21 . 2009
Attest : J . K . Barton , Clerk of Court
By-r\ � L
Deputy Clerk
Approved :
/J seph A Bair oun y Administrator
=E .
m and legal sufficiency :
ior A is ant County Attorney
EXHIBIT 1
SCOPE OF WORK
INDIAN RIVER COUNTY
SOUTH COUNTY WATER TREATMENT PLANT
REHABILITATION OF WELL NO . 5
BACKGROUND
Indian River County Department of Utility Services ( County) owns and operates the South
County Water Treatment Plant (WTP) which currently operates with six existing Upper
Floridan Aquifer (UFA) production wells . The County recently discovered that the existing Well
No . 5 has suffered from a formation collapse and several partial blockages of the open hole,
which have restricted flows available from the well . The County is therefore in need of
rehabilitation services on the damaged well .
The following is the scope of services to be provided under this authorization .
SCOPE OF SERVICES
CDM will perform the following task services .
TASK 1 . 0 PREPARATION OF REHABILITATION PROTOCOL
CDM will work with the well contractor (Aquifer Maintenance and Performance Systems, Inc .
( AMPS) ) to develop the appropriate multi-phased approach for rehabilitating the well and
placing it into service . This will include physical reaming of the well to remove the obstructions,
a video survey to confirm success of the reaming activities, air-lifting of the removed formation
and sediment, acid treatment for the removal of calcification and organic buildup in the open
hole portion of the well, and ultimately the disinfection of the well prior to placing it back in
service . The contractor will also be required to develop the well until such time as the Silt
Density Index test is acceptable to the County . CDM will prepare and provide a written
protocol to the County and AMPS for review and discussion prior to beginning the work .
TASK 2 . 0 INSTRUMENTATION AND PROGRAMMING
CDM will include a requirement for AMPS to conduct performance testing to insure that the
existing instrumentation from Well No . 5 is operating properly upon reinstallation in the
rehabilitated well . Communications at the South County WTP rely on wireless telemetry; CDM
will insure that the existing equipment functions accordingly .
TASK 3 . 0 GENERAL SERVICES DURING CONSTRUCTION
Subtask 3 . 1 Resident Project Representative
CDM will provide part time field oversight during the rehabilitation of the well . CDM will
coordinate with the Contractor to be on site during the critical components of the project,
during all testing activities and surveys, and to verify the condition of all down-hole
components prior to reinstallation in the well . CDM will conduct periodic site visits during the
rehabilitation, amounting to up to 8 hours per week, as needed . CDM anticipates that the
rehabilitation activities will take approximately 3 weeks . CDM ' s project representative will keep
A- 1 j12317. doc
a field log of activities observed during each site visit, including photographs of key activities .
The field log will be made available to the County upon request.
Subtask 3 . 2 Progress Meetings During Construction
CDM will conduct weekly progress meetings with County staff and the Contractor during the
rehabilitation project . Progress meetings will be held on site at the South County WTP .
TASK 4. 0 PROJECT MANAGEMENT AND QUALITY CONTROL
Activities performed under this task consist of those general administrative functions required
to assure that the project remains on schedule, within budget, and that the quality of the work
products defined within this scope is consistent with CDM' s standards and the County's
expectations .
OTHER SERVICES NOT INCLUDED IN THIS SCOPE OF SERVICES
This authorization does not include :
■ Design or specification of replacement components;
■ Permitting (none is anticipated to be required) ;
■ Water quality sampling and testing. The County will contract directly with a laboratory to
provide analytical services related to the required bacteriological testing (bactis) .
COUNTY RESPONSIBILITIES
The County will provide all reasonable data requested by CDM for the purpose of completing
the aforementioned tasks . The County will also provide a timely review of all work products .
The County will coordinate analytical laboratory services, as needed, and provide staff for
collection of all water quality samples not required of the contractor .
A-2 j12317 .doc
EXHIBIT 1
INDIAN RIVER COUNTY
REHABILITATION OF SOUTH COUNTY WTP WELL NO. 5
Senior Project
Task Associate Principal Professional Professional II Administration Total Hours
Task 1 .0 — Preparation of Rehabilitation Protocol 0 2 8 0 2 12
Task 2.0 — Instrumentation and Programming 4 2 4 4 2 16
Task 3.0 — General Services During Construction
Subtask 9. 1 - Resident Project Representative 02 24 8 2 36
Subtask 9.2 - Progress Meetings During Construction 0 2 4 4 2 12
Task 4.0 — Project Management and Quality Control 0 8 8 4 2 22
TOTALI 4 1 16 48 20 10 98
CM
j12317 Exhibit Tables.xis
EXHIBIT 1
BUDGET
PROJECT :
Rehabilitation of South County WTP Well No . 5
PROJECT
DESCRIPTION: As Outlined in the Scope of Services .
REFERENCE : Agreement between Indian River County Board of County Commissioners
and Camp Dresser & McKee Inc .
Labor Category Hours Rate Cost
Associate 4 $ 190 $ 760
Principal 16 $ 180 $2,880
Senior Professional 48 $ 145 $6,960
Professional 11 20 $ 130 $2,600
Admin Support 10 $75 $750
TOTAL HOURS 98 $13,950
SALARY $ 13,950
OTHER DIRECT COSTS $ 1 ,000
GRAND TOTAL $ 14,950
USE AN UPPER LIMIT (NOT TO EXCEED) $ 14,950
j12317 Exhibit Tables.xls