Subject: Professional Engineering
Indian River County Solid Waste Disposal District
Class 1 Landfill Gas System Modifications
CDM Work Authorization No . 9901-28
Dear Ms . Kratman:
CDM is pleased to submit this proposal to Indian River County to perform engineering
services for the above referenced project. This scope includes modifications of the Landfill
Gas Collection System Design to accommodate a vertical expansion of the Class 1 -Segment 1
Landfill.
The following attachments are provided herewith as part of the proposal :
■ Attachment A Engineering Work Authorization
■ Attachment B Scope of Work and Project Schedule
■ Attachment C Project Budget Summary and Schedule
We appreciate the opportunity to assist Indian River County in performing this project. If you
have any questions or require additional information, please call our office .
Very truly yours, APPROVED :
t
dner, P. E . ex H . Makled, P. E ., DEE
ject Manager Vice President
Camp Dresser & McKee Inc . Camp Dresser & McKee Inc
mh1266
consulting • engineering • construction • operations
ATTACHMENT A
ENGINEERING WORK AUTHORIZATION
Date : Work Authorization No. 28 for Consulting Services
County No . 9901-28 Camp Dresser & McKee Inc . (Consultant) CDM Project No ,
I . PROTECT DESCRIPTION
Consulting Engineering services related to LFG System Modifications of the LFG design
to accommodate a vertical expansion of the Class 1 -Segment 1 Landfill.
II. SCOPE OF SERVICES
Reference is made to Attachment B, the attached Scope of Work and the "Professional
Engineering Services Master Agreement for Solid Waste ."
III. CONSULTING ENGINEER INSURANCE REQUIREMENTS
The following insurance requirements will be provided in accordance with the Master
Services Agreement:
A . Workers Compensation Insurance in accordance with Florida Statutes .
B . Automotive Liability with a coverage of $1,000,000 for a combined single limit.
C . General Liability with a limit of $2,000,000 for general aggregate coverage .
D . Professional Liability with an aggregate limit of $3,000,000.
IV. COMPENSATION FOR SERVICES
Engineering Services :
Task 1 . 0 - Modification of the Landfill Gas
Collection System (Not To Exceed) $31 ,920 .
Total $31 ,920 .
A-1 mh1268
Salary Cost Basis with Upper Limit
For the basic services performed on a salary cost basis with an upper limit, IRC agrees to
pay CDM as follows :
For engineering services performed by CDM, the payment will be equal to the salary cost
of such services for each employee times 2.35 for overhead and profit plus actual out-of-
pocket expense costs . Salary cost is equal to 1 .393 times direct salary costs and is defined
as the cost of salaries (including sick leave, vacation, and holiday pay applicable thereto)
for time directly chargeable to the project; plus unemployment, excise, and payroll taxes;
and contributions for social security, employment compensation insurance, retirement
benefits, and medical and other group insurance benefits .
Actual out-of-pocket expense costs are all costs other than salary costs that are incurred
during the progress of the work. The actual out-of-pocket expense costs include : air fare,
automobile rental if required, mileage charges, parking tolls, taxi, meals, and lodging all in
accordance with reimbursement rates set forth in Section 112. 061, Florida Statutes (1999) ,
as amended, and telephone, printing and reproductions costs, and other miscellaneous
costs incurred specifically for this project. The maximum cost for blueprint sheets is $1 . 10 .
The maximum cost for mylar sheet is $11 . 00 and sepia sheet is $5 . 00 . The charges for in-
house computer program and word processor usage will be at CDM' s regular rates . For
outside computer services, charges will be made at invoiced cost to CDM .
SUBMITTED BY: APPROVED BY:
CAMP DRESSER & McKEE INC. INDIAN RIVER COUNTY, FLORIDA
fs o3 By.
Al akled. , P. E . hairman Kenneth R. Macht
ice President BCC Approved : August 12 , 2003
Witnessed ley : Attest: J. K. Barton, Clerk
By :
Nam
Deputy Clerk
F 9
U !" t
A-2 mh1268
ATTACHMENT B
SCOPE OF SERVICES
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
CLASS I ACTIVE LANDFILL GAS EXTRACTION AND
CONTROL DESIGN MODIFICATIONS
INTRODUCTION
Indian River County (IRC) is preparing for the construction of an active Landfill Gas (LFG)
Extraction and Control System for the Class I Landfill. The LFG system will consist of gas wells
installed into the waste and collection system of header pipes, which will convey the landfill gas
to a flare station where it will be burned .
The current Master Plan calls for the current Segment 1 portion of the landfill to have a final
elevation about 45' higher than present. The Class 1 Segment 1 Landfill is currently closed with
a clay cap and with passive gas vents installed into the waste .
The purpose of this Landfill Gas Extraction and Control System Design Modification is to
accommodate a vertical expansion of the Segment 1 Landfill . This will be done by providing
connection points for a horizontal gas collection system to be designed and installed at some
future time. Because there are existing landfill gas wells on top of Segment 1, additional
modifications to these existing wells will be required for them to continue to operate during
filling operations of the expansion.
This scope reflects a significant effort to modify the design to accommodate a future system
expansion, which would primarily use horizontal Landfill Gas Collectors in the Indian River
County Landfill. In addition, this change makes it possible to design a landfill gas control
system in the future, which will effectively collect gas from the vertical expansion area of
Segment 1 .
TASK 1 . 0 - LANDFILL GAS COLLECTION SYSTEM MODIFICATIONS
The Landfill Gas Collection System design will be modified to serve the Landfill Gas Collection
demands of a future landfill gas system expansion which will collect and extract landfill gas
from the vertical expansion of Segment 1 of the Landfill. There are currently eight landfill gas
wells, which passively vent gas on the top of Segment 1 . The current landfill gas collection
system design uses lateral headers to connect these wells into a perimeter header, which then
conveys the gas to a gas flare .
CDM will design connection points along these lateral headers to allow for connection of future
horizontal collectors to the existing vertical well network.
B-1 mh1268
S
The future horizontal gas collectors should be configured in a way to maximize performance
under the future waste to be placed on Segment 1 . The layout of the existing perimeter header
will also be modified to allow gas wells/ horizontal collectors placed in the vertical expansion in
the future to be connected to the header .
CDM will revise the KYGas model used to size and balance the gas collection header system.
The model will reflect the new header configuration and the additional gas, which would be
expected to be generated by the additional waste from the vertical expansion. Components of
the existing design, which will be affected by the additional gas flow, will be modified.
CDM will also develop new details as required for these design revisions . The connection points
for the future horizontal gas collectors to the collection header will be detailed . The additional
design details will include a modification of the existing layouts and details. These details will
be added to the plans and referenced as needed on the existing plans . In addition to these
details the base file, which shows existing grade, will be modified to include the most recent
aerial topography work performed in 2002 .
CDM has budgeted two meetings with IRC to discuss these design modifications .
SCHEDULE
These design modifications will be performed over an 8-week period . This period includes the
meetings with Indian River County Solid Waste Disposal District.
B-2
mh1268
ATTACHMENT C
PROJECT BUDGET
INDIAN RIVER COUNTY SOLID WASTE DISPOSAL DISTRICT
CLASS 1 LANDFILL GAS SYSTEM DESIGN MODIFICATIONS
TASK 1 . 0
PROJECT: Indian River County - Class 1 Landfill
Gas System Design Modifications
DESCRIPTION: Gas Collection System Design Modifications
CONTRACT
REFERENCE : Agreement between the Indian River County Board of County
Commissioners and Camp Dresser & McKee Inc .
Labor Category , Hours Rate Total
Officer (ENEV-8/ 9) 4 $60 . 00 $240 .
Engineer (ENEV-7/ 8) 48 $45. 00 $2,160 .
Engineer (ENEV-3/ 4) 88 $25. 00 $2,200 .
Drafter (DFGN-4) 80 $18 . 00 $1,440 .
Support 24 $15 . 00 $360 .
Total Hours 244
Direct Salary Cost $6,400 .
Indirect Salary Cost (0 .393) $2,515 .
TOTAL SALARY COST $8,915 .
SALARY COST TIMES MULTIPLIER (2.35) $20,950 .
OTHER DIRECT COSTS: $1 ,470 .
OUTSIDE PROFESSIONALS $9,500 .
TOTAL ESTIMATED FEE
$31 ,920 .
For the basic services under this Agreement, the County agrees to pay the Consultant a Not to
Exceed fee of $ 31 ,920 . Partial payments are to be made on a monthly basis in accordance with
the referenced contract.
C-1 mh1268
w
INDIAN RIVER COUNTY
SOLID WASTE DISPOSAL DISTRICT
LANDFILL GAS SYSTEM DESIGN MODIFICATIONS
DETAILED SUMMARY OF HOURS AND SALARY COSTS
Task Officer Principal Engineer 5/6 Engineer 3/4 Engineer 1 /2 Drafter Clerical
Description $60 . 00 $45. 00 $35. 00 $25. 00 $22. 00 $ 18. 00 $ 15. 00 Total Total
hrs hrs hrs hrs hrs hrs hrs hours $
1 . 0 LFG System Design Modifications 4 48 0 88 0 80 24 244 $ 61400
GRAND TOTAL OF CDM LABOR - Hours 4 48 0 88 0 80 24 244 $ 6 ,400
mh1268