HomeMy WebLinkAbout2008-269Board of County Commissioners
1801 27th Street
Vero Beach, Florida 32960
Telephone: (772) 5674000
FAX: 772-778-9391
INDIAN RIVER COUNTY PARKS MAINTENANCE COMPLEX
SUPPLEMENTAL No. 2 to WORK ORDER NO. 1
TO THE
PROFESSIONAL CIVIL ENGINEERING SERVICES AGREEMENT
WITH
CARTER ASSOCIATES, INC.
This Supplemental No. 2 to Work Order No. 1 is in accordance with the existing
AGREEMENT dated January 9, 2007 and the extension thereof, between Carter
Associates, Inc. (ENGINEER) and Indian River County (COUNTY).
This Supplemental No. 2 to Work Order No. 1 amends the agreement as follows:
SECTION I — PROJECT LIMITS
Consultant services are required for the re -design of the stormwater management system
and the potable water service connection for the construction of the Indian River County
Parks Maintenance Complex.
SECTION II — SCOPE OF SERVICES
The Scope of Services for this Supplemental No. 2 to Work Order No. 1 is to perform the
following tasks as requested by the County:
Stormwater Management System to include:
• Revise the Paving, Grading and Drainage Plan to call out revised stormwater pond
control structure weir elevations and show revised permanent pool contours.
• Revise the control structure detail.
• Revise and update the stormwater calculations report.
• Submit revised plans and calculations to the SJRWMD and IRC Engineering Dept.
C:\Documents and Settings\SeanM\Local Settings\Temporary Internet Files\OLK I \0701 Supplemental No 2 to WO No I Carter 08-
21-08.doc
PAGE TWO
Supplemental No. 2 to Work Order No. 1 Carter Associates, Inc.
August 21, 2008
Water Service
0 Revise the Utility Plan to add a fire hydrant and call -out connection to the
converted 16" water main.
• Modify water supply system permit with the FDEP.
• Modify utility construction permit with the IRCDUS.
SECTION III - TIME FOR COMPLETION
Supplemental tasks shall be completed within 30 calendar days from the date of
execution of this Supplemental No. 2 to Work Order No. L
SECTION V - COMPENSATION
The COUNTY agrees to pay, and the ENGINEER agrees to accept, a fee for services
rendered according to the "Scope of Services" and further identified in all the Sections
of this Supplemental No. 2 to Work Order No. 1, a Lump Sum of $15,740.00.
All and/or any additional services not described hereon shall be pre -approved by the
COUNTY. Approved additional services shall be invoiced at the rates disclosed in the
approved fee schedule with the SURVEYOR for the 2006 — 2007 contract year.
All invoicing and payments shall be in accordance with the original Professional Civil
Engineering Services Agreement with the COUNTY and as stated hereon. Invoices
shall include the work order and project number, invoice number related to this work
order, original contract amount, current billing amount and retainage amounts.
The AGREEMENT is hereby amended as specifically set forth herein. All remaining
sections of the AGREEMENT shall remain in full force and effect, and are incorporated
herein.
C:\Documents
and Settings\SeanM\Local Settings\Temporary Internet Files\OLKI\0701
Supplemental No 2 to WO No 1 Carter 08-
21-08.doc
PAGE THREE
Supplemental No. 2 to Work Order No. 1 Carter Associates, Inc.
August 21, 2008
Attachment: Carter Associates Scope of Services (Exhibit A)
OWNER
BOARD OF COUNTY COMMISSIONERS
INDIAN RIVER COUNTY, FLORIDA
I- - rff -v f
Nl
anL•: $ovvde n, Chairman
�(Pfinted name- axd title)
Approved^by BCC: September 9, 2008
ATTEST.
,Xedj ey.K=$art6h? 40lerk of Circuit Court
Deputy Clerk
Approved as to Form an gal Sufficiency:
eI/// �/1/
William G. Collins II, COUNTY Attorney
Carter Associates, Inc.
(Signature)
(Printed name and title)
Witnessed by: (Carter,Associates, Inc)
ed name) �Eo�t4E sem,/ /�clkiRE
Baird, COUNTY
C:\Documents and Settings\SeanM\Local Settings\Temporary Internet Files\OLKI\0701 Supplemental No 2 to WO No 1 Carter 08-
21-08.doc
CARTER ASSOCIATES, INC.
CONSULTING ENGINEERS AND LAND SURVEYORS
1708 21 sF STRF,F;17
VERO BEACH, FLORIDA 32960-3472
772-562-4191
772-562-7180 (FAX)
August 20, 2008
MARVIN
F.. CARTER,
P.S.M.
DEAN F.
LUFI FUE,
P.E.
irispuri
13
r,wm.�J{Y�JlIN 11. BI UM, P.F
'- DAVID t 111�UETH.IF, P.S.Al-
G. SEAN MCGUIRE, P.E.
GEORGE SIMONS, P.E.
AUG 1 ���$ STEVF? SNOBERGFR, 1'.F,.
PATRICK S. WAI-IIIL'R. P.E.
Mr. Christopher J. Kafer, Jr., P.E., County Engineer INDIAN R i V ` IJNTY
Indian River County Engineering Division E N G I N E E R I G` SIU N
1801 27`h Street RECD BY:
Vero Beach, FL 32960
Re: Indian River County Parks Maintenance Complex (CAI Project No. 05-60E)
Supplemental No. 2 to Work order No. 1 to the Professional Civil Engineering Services Agreement
Dear Chris:
We are pleased to present this proposal for additional services relative to re -designing the stormwater
management system and the potable water service connection for the project. All provisions of the original
Work Order No. 1 to the Professional Civil Engineering Services Agreement (dated January 9, 2007),
including Supplemental No. 1, shall remain in full force and effect, unless otherwise specifically modified
herein. A man-hour fee estimate is attached as Exhibit "A" for your use. The following describes our
proposed scope of services and terms of agreement between Carter Associates, Inc. (Engineer) and Indian
River County (County):
Stormwater Management System:
The stormwater management system will be revised to comply with the phosphorus loading analysis
requirements stipulated as item L in the SJRWMD's letter of 2/21/08. This analysis requirement has been
applied by the SJRWMD to this project since the North Canal drainage basin has recently been classified as
an impaired water body, This requirement is a change in the permitting process that could not have been
anticipated and was not included in the original scope of professional services.
The stormwater management system will also be revised to utilize the wet detention system methodology in
lieu of the stormwater re -use alternative method in order to remove the automatic shut-off/turn-on switch
requirement for the irrigation pump, as is stipulated as item 21 in the SJRWMD's letter of 4/16/08. This
requirement is also a change in the permitting process that could not have been anticipated and it requires a
re -design of the previously designed and submitted plans and calculations. The project documents will be
modified as follows:
• Revise the Paving, Grading and Drainage Plan to call out revised stormwater pond control structure
weir elevations and show revised permanent pool contours.
• Revise the control structure detail.
• Revise and update the stormwater calculations report.
• Submit revised plans and calculations to the SJRWMD and IRC Engineering Dept.
Water Service:
A fire hydrant will be added at the project frontage along 77`h Street and the water service connection will be
re -designed to connect to a 16" diameter water main on the north side of 77`h Street. This water main is
currently shown on the project plans and the Utilities Department as-builts as a brine line. The brine line will
-AIScrv7 nig Florida
s1rice 1911
be converted to a potable water main by others. Professional services to be provided under this supplement
are as follows:
• Revise the Utility Plan to add a fire hydrant and call -out connection to the converted 16" water
main.
• Modify water supply system permit with the FDEP.
• Modify utility construction permit with the IRCDUS.
Compensation:
Supplemental No. 2 fees will be invoiced on a percent complete lump sum basis. The total amount to be
billed shall not exceed $15,740.00 unless authorized by an additional written agreement.
Please call on me should you have any questions or concerns regarding our proposed scope of work or terms
of agreement.
Sincerely,
G. Sean McGuire, P.E.
Project Manager
Attachments - Exhibit "A" (man-hour fee estimate)
N:\GSM\P\05-60E(IRC Parks Complex)\Agreements\Proposal8-20-08.doc
Serving Florida
Since 1911
Indian River County
Parks Maintenance Complex
Supplemental No. 2 (Revise stormwater design for new SJRWMD rules)
Fee Estimate (rate schedule as per CAI continuing services agreement with IRC)
8/20/2008
$140.00
$125.00
$110.00
$55.00
S40.00
Fnn_
I Prin_
Pro- 1-
P -F_
Frig.
II_ P.E.
Ena. III.
E.I.
Clerical
Dean Steve Sean/Ken KelleyTrisha
Exhibit "A"
Subtotal
Revise Stormwater Report
Stormwater Calculations Report
4
32
31160.00
Plan Revisions
12
2
8
900.00
Re -submittal to SJRWMD
2
4
2
8
2
900.00
Quality Control
2
4
2
440.00
Coord/Meetin s/Incidentals/Printin
2
1
1 4
2
800.00
sub -total = $692UU.UU
Redesign as Wet Detention
Stormwater Calculations Report
12
11320.00
Plan Revisions
12
16
1,760.00
Re -submittal to SJRWMD
2
4
6
2
660.00
Coord/Meetin s/Incidentals/Printin
2
4
2
800.00
Sub -total = $4,t4UMU
Redesign Water Service
Plan Revisions
8
880.00
Re -submittal to FDEP
12
4
11940.00
Coord/Meetin s/Incidentals/Printin
2
4
12
2
2,180.00
sub -total =
Grand Total =
$5,000.00
$15,740.00
Sery ng Florida