IMPLEMENTATION OF THE
EAST INDIAN RIVER COUNTY MASTER STORMWATER
MANAGEMENT PLAN :
WORK ORDER No . 3
TO THE
PROFESSIONAL ENGINEEERING SERVICES AGREEMENT
BETWEEN CARTER ASSOCIATES, INC., AND
INDL4NRIVER COUNTY, FLORIDA
FORA
PRELIMINARY ENGINEERING REPORT FOR THE
SOUTHWEST INDUSTRIAL STORMWATER PARK, PHASE I
Pursuant to the Professional Engineering Services Agreement ( MASTER
AGREEMENT) dated May 8 , 2001 , by and between INDIAN RIVER COUNTY , a
political subdivision of the State of Florida , hereinafter referred to as the COUNTY , and
CARTER ASSOCIATES , INC . , Vero Beach , Florida , hereinafter referred to as the
ENGINEER , this WORK ORDER No . 3 is an extension of and hereby becomes a part
of the MASTER AGREEMENT as follows :
SECTION 1 - PROJECT LIMITS AND DESCRIPTION
In accordance with the East Indian River County Master Stormwater
Management Plan ' s ( Master Plan ) recommended improvements and actions , WORK
ORDER NO . 3 is for the preparation of a Preliminary Engineering Report for the Phase
design of Alternative No . 6 of the Master Plan (Southwest Industrial Stormwater Park) .
In general , Phase I of Alternative No . 6 consists of the construction of a storage
reservoir and treatment system on an existing 35-acre COUNTY-owned parcel in the
vicinity of 4th Street and 74th Avenue . This reservoir will be incorporated into a future
stormwater treatment and storage system that may total up to 195 acres . This Work is
discussed in more detail in SECTION III — SCOPE OF SERVICES PROVIDED BY THE
ENGINEER .
SECTION II - COUNTY OBLIGATIONS
A . The COUNTY will comment on the ENGINEER' s work in a timely fashion .
[The remainder of this page was left blank intentionally]
F:\Public Works\KeithM\Stcr nwater Projects\East IRC\Contracts\Consultant Contract with Carter & Associates\Wcrk Order No. 3 - Calpine Node
Phase Mork Order #3 - Latest Revision .doc
1
SECTION III - SCOPE OF SERVICES PROVIDED BY THE ENGINEER
A. PROJECT ASSIGNMENTS
The "design team" is collectively comprised of Carter Associates , Inc . and
Environmental Consulting & Technology , Inc. Specific assignments follow:
1 . Carter Associates , Inc . — Carter Associates , Inc . (CAI ) shall provide
project quality control services . The following CAI personnel are required
to work on this project .
a . Dean F . Luethje , P . E .
2 . Environmental Consulting & Technology ( ECT) — ECT shall provide all
preliminary engineering design and related work . The following ECT
personnel are required to work on this project:
a . Frank E . Marshall , P . E . , Ph . D .
b . Robert Naleway , P . E .
c . Lora Saunders , Associate Scientist
B . GENERAL
The Southwest Industrial Stormwater Park will be a regional stormwater
treatment and storage facility, receiving water from Indian River Farms Water Control
District ( IRFWCD ) canals . The Stormwater Park' s primary purpose is to protect the
water quality of the Indian River Lagoon and thereby aid in restoring the Lagoon ' s
seagrass coverage , by treating and storing stormwater runoff and groundwater seepage
carried to the Lagoon by IRFWCD canals . The canal water will be treated in the
Stormwater Park to remove pollutants such as nutrients and suspended solids .
The facility' s secondary purpose is to provide process cooling water to a
proposed private power plant called the Blue Heron Energy Center. If the power plant
is constructed , some of the treated water will be pumped from the storage reservoir to
the power plant , where it will be evaporated . A tentative withdrawal point for the canal
water has been determined by the COUNTY , Blue Heron Energy Center, L . L . C . ( a
wholly owned subsidiary of Calpine Corporation ) , and IRFWCD .
The Stormwater Park shall also function as a wildlife sanctuary and this shall be
considered in the Phase I preliminary engineering design . The Nature Conservancy will
be a partner for this project and therefore , coordination with The Nature Conservancy is
necessary and expected under this Work Order. This input shall be specifically
addressed in the Preliminary Engineering Report ,
The COUNTY owns the 35- acre Phase I site . Up to 160 additional acres may be
purchased and incorporated into the stormwater treatment and storage system .
Unfortunately , the final configuration of the built-out Stormwater Park may not be known
when Phase I is designed . Therefore , the Phase I preliminary engineering design shall
be based on a " modular ' concept , so that the facility will function properly regardless of
the Stormwater Park' s final boundary .
FAPublic Works\KeithM\Stcrmwater Projects\East IRC\Contracts\Consultant Contract with Carter & Associates\Work Order No. 3 - Calpine Node
- Phase Work Order #3 - Latest Revision .doc
2
C . ENGINEERING SERVICES
Task 1 — Preliminary Engineering Report asPrepare a preliminary engineering
report that includes , but is not limited to : Analyze stormwater treatment, storage
and operation alternatives and provide estimated costs and recommendations ,
including preliminary engineering calculations and drawings for the
recommended facility . Determine proposed operational water levels and provide
schematic drawings showing water level elevations . Cost information shall
include a preliminary opinion of probable construction cost and yearly operation
and maintenance costs . Note that part of the Phase I site includes an
abandoned unregulated landfill (former "stump dump " ) and therefore , some
geotechnical investigations and water quality sampling and testing will be
necessary to determine if design constraints will be placed on certain parts of the
site . (The geotechnical investigations and water quality sampling and testing will
be performed by COUNTY consultants . ) Coordinate this effort with St . Johns
River Water Management District (SJRWMD ) and the Florida Department of
Environmental Protection ( DEP ) to ascertain what design constraints , if any ,
those agencies may place on the property ( i . e . perform preliminary permitting ) .
Coordinate with and schedule the COUNTY' s geotechnical engineering
consultant and testing laboratory as necessary.
Further, investigate the potential for withdrawing the most polluted canal water
possible from the IRFWCD ' s canals for treatment in the Stormwater Park .
Perform a cost- benefit analysis and recommend whether or not the currently
proposed canal water withdrawal point should be relocated .
( Note : Calpine Corporation is responsible for designing , permitting , and constructing the
Stormwater Park' s influent pumping station in the IRFWCD canal , and also a Power
Plant cooling water pumping station at the reservoir. Coordinate with Mr. Charles
Wright, Calpine Water Quality Specialist at (813 ) 637-7300 , regarding the Stormwater
Park' s flow requirements and the cooling water pump station ' s design requirements ,
including water quality requirements . The reservoir must be designed to meet the
Power Plant' s cooling water quantity and quality requirements . )
Task 2 = Proiect Meetings = Meet with COUNTY personnel as requested by the
COUNTY at the County Administration Building or project site . As a minimum ,
the following meetings will be held :
a . At least 3 coordination meetings to discuss the project and develop
criteria to guide the Preliminary Engineering Report , and one or
more meetings to review the Preliminary Engineering Report.
b . Meet to discuss the Project with The Nature Conservancy and
COUNTY .
C , Meet with local and state regulatory personnel as necessary to
determine design constraints and to minimize final design efforts .
F:\Pubhc Works\KeithM\Stc mwater Projects\EastIRC\Contracts\Consultant Contract with Carter & Associates\Wank Order No. 3 - Calpine Node
- Phase Work Order #3 - Latest Revision.doc
3
SECTION IV = TIME FOR COMPLETION
Time is of the essence for this Project . The COUNTY has a contractual
obligation with Blue Heron Energy Center, L . L . C . , to have the Phase I reservoir in place
for start-up and testing , on or before December 2004 . Schedule and perform the work
to accomplish this goal . Submit the Preliminary Engineering Report to the COUNTY for
final approval on or before the 60th calendar day after the COUNTY issues a written
authorization to proceed .
SECTION V - COMPENSATION
The COUNTY agrees to pay, and the ENGINEER agrees to accept , a fee for
services rendered according to the "Scope of Services Provided by the ENGINEER , "
identified in Section III of this WORK ORDER , with a maximum charge of $22 , 775 . 00 .
This maximum fee is itemized as follows :
TABLE V-1 — MAXIMUM COMPENSATION SCHEDULE
Task Description ENGINEER ' s
Compensation
1 Preliminary Engineering Report $ 189850 . 00
2 Project Meetings $ 3 , 925 . 00
TOTAL MAXIMUM COMPENSATION $22 ,775 . 00
SECTION VI - ADDITIONAL WORK
Additional work shall be in accordance with the MASTER AGREEMENT .
Additional work performed on a time and material basis shall not exceed the unit values
listed in the following schedule . Lump sum fees for additional work shall be negotiated .
TABLE VI - 1 — MAXIMUM UNIT PRICES FOR WORK PERFORMED
ON A TIME AND MATERIAL BASIS
ENGINEER I . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . $ 100 . 00/hr
ENGINEER 11 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . $ 85 . 00/hr
ENGINEERIII . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . $ 60 . 00/hr
ENGINEER TECHNICIAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . $ 50 . 00/hr
BOTANIST . . $ 110 . 00/hr
BIOLOGIST . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . $ 110 . 00/hr
PLANNER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . $ 100 . 00/hr
SENIOR SCIENTIST . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . $ 100 . 00/hr
LANDSCAPE ARCHITECT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . $ 100 . 00/hr
SURVEYOR I ( Principal ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . now " $ 100 . 00/hr
SURVEYOR li ( Registered ) . 65 . 00/hr
F:\Public Works\KeithM\Stamwater Projects\FastIRC\Contracts\Consultant Contract with Carter & Associates\WQk Order No. 3 - Calpine Node
- Phase Work Order #3 - Latest Revision.doc
4
SURVEYORIII . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . $ 55 . 00/hr
SURVEY CREW (3- MAN ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . $ 90 . 00/hr
CADD TECHNICIAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . $ 50 . 00/hr
DRAFTING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . $ 45 . 00/hr
SECRETARY/WORD PROCESSOR . . . . . . . . . . ones a 30 . 00/hr
RESIDENT PROJECT REPRESENTATIVE . 35 . 00/hr
GRAPHICS ASSISTANT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . $ 25 . 00/hr
RECORDING AND PERMIT FEES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cost
MATERIALS , I & @ & & woes@ a balm @agave a be 64 , 09 * 9 ago a at bassoon so we a a 6 a above@ a a 60 , 6606 soesea a 0 sea me Cost
+ 10 %
TRAVEL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . $ 0 . 29/Mile
SUB -CONSULTANTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . Cost
REIMBURSABLE EXPENSES .
Postage , Long Distance Calls , Federal Express ,
Handouts for Public Meetings , etc , Cost
Blueprints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . $ 1 . 00/sheet
Mylars . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . $4 . 00/sheet
Xerox . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . $ 0 . 15/page
SECTION VII = PARTIAL PAYMENTS
The COUNTY shall make monthly partial payments to the ENGINEER for all
authorized work pertaining directly to this project performed during the previous
calendar month . The ENGINEER shall use the form provided in "Attachment 1 , " herein .
The ENGINEER shall submit invoices monthly for services performed and expenses
incurred pursuant to this Agreement during the prior month .
The ENGINEER shall submit duly certified invoices in duplicate to the Director of
the Public Works Department. For lump sum line items , the amount submitted shall be
the prorated amount due for all work performed to date under this phase , determined by
applying the percentage of the work completed as certified by the ENGINEER , to the
total due for this phase of the work . For time and material line items , the amount
submitted shall be based on the actual hours worked and expenses incurred for the
billing period .
The amount of the partial payment due the ENGINEER for the work performed to
date under these phases shall be an amount calculated in accordance with the previous
paragraph , less ten percent ( 10 % ) of the invoice amount thus determined , which shall
be withheld by the COUNTY as retainage , and less previous payments . Per F . S .
218 . 74 (2 ) , the COUNTY will pay approved invoices on or before the forty-fifth day after
the COUNTY receives the ENGINEER ' s invoice .
Per F . S . 218 . 74 (2 ) , the ten percent ( 10 % ) retainage withheld shall be paid in full
to the ENGINEER by the COUNTY , on or before the forty-fifth day after the date of final
acceptance of the Work by the Public Works Director,
The Agreement is broken into deliverable units . No payment shall be made
unless the Public Works Director has received and approved the work products
required under the "Scope of Services Provided by the ENGINEER , " herein .
F:\Pubhc Works\KeithM\Stc mwater Projects\EastIRC\Contracts\Cmsultant Cmtractwith Carter & Associates\Wcrk Order No. 3 - Calpine Node
- Phase Mork Order #3 - Latest Revision.doc
5
SECTION VIII = VENUE
Venue for any lawsuit brought by either party against the other party or otherwise
arising out of this Contract shall be in Indian River County, Florida , or, in the event of a
federal jurisdiction , in the United States District Court for the Southern District of Florida .
SECTION IX - RELATIONSHIP TO MASTER AGREEMENT AND LAWS
OF FLORIDA
All conditions set forth in the MASTER AGREEMENT shall control unless
otherwise specified in this WORK ORDER .
This WORK ORDER No . 3 , regardless of where executed , shall be governed by
and construed according to the laws of the State of Florida .
IN WITNESS WHEREOF the parties hereto have executed these presents this
day of March , 2003 .
CARTER ASSOCIATES , INC . INDIAN RIVER COUNTY , FLORIDA
170821 ST STREET BOARD OF COU COMMISSIONERS
VER , FLO D 32# 0
BY 61 BY :
Dean F . Luet je , Vice Presi nt Kerffieth R . Macht , Chairperson
Witnessed by: Approved by BCC 03 - 04 - 2003
Attest :
Jeffrey K . Barton , Clerk of Circuit Court
Indian River County
Approved Date
Administration Deputy Clerk
Budget
Count Attorne
Risk Management ou y Attorney
Public Works u�
Stormwater Mo
EngineeringZounty
es E . Chary er,
Administrator
F:\Pubhc Works\KeithM\Stornwater ProjectsTast IRC\Contracts\Cmsultant Contract with Carter & Associates\Wcrk Order No. 3 - Calpine Node
- Phase Mork Order #3 - Latest Revision .doc
6
• ' • ' •
• - - • - • - -
• - i - - • -
• - • - - - • -
RMI
a'�r.6.:. .s
• • • - . 1 • � - . - -.
` • a TA
Lkfif
• 0 - 1 I ON FMATCI
WWII I Roll I Ile wig lzm
• - 1 . • • - I] • I] •
ME
��Il kli Lois ] - • apill =K1
wto Mel MR 111611
• - - ' •
ATTACHMENT 1
CONSULTANT' S APPLICATION FOR PAYMENT NO . for
WORK ORDER No . 3
ENGINEER ' S CERTIFICATION :
THE UNDERSIGNED ENGINEER ' S REPRESENTATIVE CERTIFIES that I have checked
and verified the above Application for Payment No . and that to the best of my
knowledge and belief, it is a true and correct statement of work performed and/or material
supplied by the ENGINEER ; that all work and/or materials included in the Application for
Payment have been inspected by me and/or by my duly authorized representative or
assistants ; that it has been performed and/or supplied in full accordance with the
requirements of the referenced Contract and with sound engineering practice and
judgment; and that the payment amount claimed and requested by the ENGINEER is
correctly computed on the basis of work performed and/or materials supplied to date .
THE UNDERSIGNED ENGINEER' S REPRESENTATIVE ALSO CERTIFIES that all
previous progress payments received from the COUNTY on account of Work done under
the Contract referred to above have been applied on account to discharge ENGINEER ' s
legitimate obligations incurred in connection with Work covered by prior Applications for
Payment numbered 1 through inclusive ; and if this is a Final Pay Request , I further
certify that all persons doing work upon or furnishing materials or supplies for this project
under this foregoing Contract have been paid in full .
Dated
ENGINEER : CARTER ASSOCIATES , INC .
1708 21 st Street
Vero Beach , Florida 32960
(561 ) 5624191
ENGINEER' S REPRESENTATIVE :
Name and Title :
State of Florida .
County of Indian River.
Subscribed and sworn to before me this day of , 200