CHANGE ORDER NUMBER 1
DATE : October 11, 2007
TO: Keith McCully, P.E.
Indian River County Stormwater Division
4375 43d Ave., Unit 102
Vero Beach, FL 32967
FROM: Ralph Brown, Project Manager
RE: CONTRACT/PURCHASE ORDER NUMBER: SF611AA
Change Order Number 1 to Work Order Number n/a
CONTRACT NAME : Sediment Flow Reduction and Other Water Quality Improvements with the
Indian River Farms Water Control District
PROJECT NAME: Indian River Lagoon Stormwater Management
ACCOUNT NUMBER: 73-4241 -6390-8301 -04003 70-42-51 -6390-8301 -04003 76-42-58 -6390-8301 -04019
CHANGE ORDER IMPACTS: This no-cost time extension will not have any effect on other proiects. The
Indian River Countv is procressing toward completion of this Memorandum Of Understanding
JUSTIFICATION FOR EXTENSION (if applicable) : The District entered into a Memorandum Of
Understanding (MOU) with Indian River County to provide an advancement of a Master Stormwater Plan to
reduce sediment and nutrient flows to the Indian River Laizoon. Due to several construction bid protests and an
unforseen delay caused by the Federal Aviation Administration requiring a permit for the construction crane at
the site construction of the Main Relief Canal Pollution Control System has been delayed. Final completion of
the Main Relief Canal Pollution Control System is estimated for June 2008 . The Eizret Marsh Stonnwater Park
has undergone a re-design to allow construction under a phased approach because initial bids exceeded the
protect budget New bids will be solicited in January 2008 and construction is estimated to be complete by
October 2008 . The County has requested a 15-month no cost time extension to complete this MOU on A ril 15
2009. District staff concurs with the County's no cost time extension request
SCHEDULE/WORK ORDER AMOUNT IMPACTS:
® Extend the completion date from January 15 2008 to April 15 2009 (impact on schedule 456 days)
❑ The completion date of will not be affected by this change order.
® The amount will not be affected by this chance order.
GOVERNING BOARD
David G. Graham, CHAIRMAN Ann T. Moore, SECRETARY Duane L Otlenstroer, TREASJRER Susan N. Hughes
JACKSONVILLE BUNNELL JACKSONVILLE PONTEVEORA
Michael Ertel Hersey 'Herky' Huffman Arlen N. Jumper William W Kerr W. Leonard Wood
OVIEDO ENTERPRISE FORT McCOY MELBOURNE BEACH FERNANDINA BEACH
Change Order continued
Approved: Original Amount . . .. . . .. . . . . . . . . .. . . . .. . . . . . .. .. .. $ 41330,000.00
Kirby B. Gr n tlt, Execu ve Director Total Additions / Deductions to-date. .. $ 1,741 ,600.00
// %r; * Amount of this Change $ 0.00
Date: / O Z// 7 ( O T Revised Amount . . .. . . .. . . . . . . . . . . . . . . . . .. . . . . .. . . $ 610719600.00
r .
Acknowledged: � . Date:
an It�vGr County ,
cc: Procurement WorkingYNf*Chasing File
Financial Management
C my A t inistrator
APPROVED AS O
Fl :GS FICI
MN E . FE
TANT COUNTY ATTORNEY
GOVERNING BOARD
Ometrias D. Long. CHAIRMAN David G . Graham, alcE CHmeuAN R. Clay Albright, sEcRETAav Duane Ottenstroer, TnEAS_PER
APOPKA JACKSONVILLE OCALA JACKSONVILLE
W. Michael Branch John G. Sowinski William Kerr Ann T Moore Susan N. Hughes
FERNANDINA BEACH ORIANDO MELBOURNE BEACH
BONNE!L JACKSONVILLE