HomeMy WebLinkAbout2007-062 CHANGE ORDER 2, 091- Nil
No. 1
PROJECT West Wabasso Water Lines
DATE OF ISSUANCE EFFECTIVE DATE
OWNER Indian River County
OWNER ' s Contract No. Project No. U ED BY
CONTRACTOR : Sheltra and Son Construction Inc.
ENGINEER Indian River County/Himanshu Mehta— FEB 1 3 2007
You are directed to make the following changes in the Contract Documents : BOARD OF COUNTY
Cn � urrni�N
Item # 1 Description :
Deduct 530 LF of 6" PVC water main at a unit price of $22 .00 (Total $ 11 , 660. 00) and Add
530 LF of 6" HDPE water main at a unit price of $ 75 . 00. ($ 39,750 . 00)
Reason for change order: Total $ 28,090.00
a) Approximately 280 LF of directional bore (HDPE) was needed on 87th Place. In general , the
Contract drawings specified a standard open & cut method for installation of the 6 " PVC water
main along the property line. The primary reason to employ the directional bore method was to
avoid obstructions such as tall dense trees and vegetation area, to avoid a fence and a garden, and
to avoid compromising a residential trailer that was too close to the property line. These
obstructions were not identified on the survey that was used for the design.
b) Approximately 180 LF of directional bore was needed at the end of 61 st Drive. Although
most of the road is paved, the last 210 LF of the road was heavily vegetated. Per the Contract
drawings, this area was to be cleared along the path of the water main. Upon clearing most of
this area, it was determined that first there was a significant drop in elevation and second that
there was water pooled at the end of the road. The directional bore method was selected to avoid
extensive dewatering and handling of the water and to avoid backfilling the area with soil . Both
of these items were not in the scope of the project. These were unknown conditions at the time of
the design since the survey did not identify these possible conditions .
c) Approximately 70 LF of directional bore was needed on 61 st Drive to avoid open & cut
installation of a new residential concrete driveway that was not identified on the survey at the
time of the design.
Item #2 Description :
Add additional 120 LF of 4 " PVC water main at the unit price of $ 19 .00 ( S2,280. 00).-
Total
2280 00).Total $ 2,280.00
Reason for change order: The Contract drawings specified extending 160 LF of 4 " PVC to
provide water services for seven homes into an area that was not properly platted . This extension
was designed to minimize the long service lines that were needed to reach these homes.
However, upon installation of this water main it was determined that the location at which this
pipe ended was not in a suitable location and that it did not adequately serve the purpose for
minimizing the long service line. Therefore, an additional 120 LF of 4" PVC water main was
needed in which the shorter service lines provide a better water pressure to the house.
Reason for change order: The Contract drawings specified extending 160 LF of 4" PVC
to provide water services for seven homes into an area that was not properly platted. This
extension was designed to minimize the long service lines that were needed to reach these
homes . However, upon installation of this water main it was determined that the location
at which this pipe ended was not in a suitable location and that it did not adequately serve
the purpose for minimizing the long service line. Therefore, an additional 120 LF of 4"
PVC water main was needed in which the shorter service lines provide a better water
pressure to the house.
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price Original Contract Times
$_ 575,000. 00 Substantial Completion: March 27,2007
Ready for final payment: April 27,2007
Days or dates
Net changes from previous Change Orders Net change from previous Change Orders
No. 0 to No. 0 No. 0 to No. 0
$ -0-
-0- days
Contract Price prior to this Change Order Contract Time prior to this Change Order
$ 575,000.00 Substantial Completion: March 27,2007
Ready for final payment: April 27,2007
Days or dates
Net Increase (decrease) in this Change Order Net Increase in this Change Order
$ 30,370. 00
days
Contract Price with all approved Change Contract Time with all approved Change
Orders Orders
$ 605 .370. 00 Substantial Completion:
Ready for final payment:
Days or dates
RECOMMENDED : APPROVED : ACCEP ED :
By:
By: r � B
Engineer (Authorized Signature) Own (* ho zed Si at e) ontractor (Authorized
Signature) —1 GaryC .., Jhes er ; B C C�iairman
Date: I — 30 — D ! Date: _ 02 / 13 /07 Date:
EJCDC No. C-700 (2002 Edition)
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated
General Contractors of America.