HomeMy WebLinkAbout2007-420 ATTACHMENT 1 NOV U 92M
CHANGE ORDER
No. 1
PROJECT 12" Force Main between Wabasso and Ad-A
DATE OF ISSUANCE EFFECTIVE DATE
OWNER Indian River County Utility Department
OWNER's Contract No. 2007060 ' M&M Project No. 0649
CONTRACTOR- SPS Contracting Inc ENGINEER-Earl H . Masteller, P. E DEE
You are directed to make the following changes in the Contract Documents:
Description : Tie in modification to Lift Sta . on east side.
Reason for change order: Wet tap not possible due to bad existing pipe Lift Station Rehab
Attachments: List documents supporting chane Cost Estimate Exhibit
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price Original Contract Times
$308 . 708. 25 Substantial Completion : N/A
Ready for final payment:
Das or dates
Net changes from previous Change Orders Net change from previous Change Orders
No._ to No. No. to No.
$ N/A N/A davs
Contract Price prior to this Change Order Contract Time prior to this Change Order
$308. 708.25 Substantial Completion: N/A
Ready for final payment:
Das or dates
Net Increase (Decrease) in this Change Net Increase in this Change Order
Order
N/A
$49 .069.00 days
Contract Price with all approved Change Contract Time with all approved Change
Orders Orders
$357, 777. 25 Substantial Completion: N/A
Ready for final payment:
Das or dates
RECOMMENDED: APPROVED: ACCEP
By.- By: t --�e
Engi`neee`r`�(Au onzed ignature) Owne Authorized Signature) Contra or (Autthhonzed ignature)
Date: _�� l lol Date: 12 Date: b 7
EJCDC No. C-700 (2002 Edition)
' r
ATTACHMENT 2
IRCUD 12" Force Main
CR 510
Wabasso Bridge to A1A
Change Order # 1
Cost Exhibit
Item Description Quantity Unit I Unit Price Total
1 14 " HDPE Pie 400 LF $ 31 . 30 $ 12 , 520 . 00
2 12" Gate Valve 3 EA $ 3 , 200 . 00 $ 9 , 600 . 00
3 12" x 6" Cross 1 EA $ 1 , 575 . 00 $ 1 , 575 . 00
4 12" Tee 1 EA $ 1 , 575 . 00 $ 1 , 575 . 00
5 12" MJ Ta Ca 1 EA $ 310 . 00 $ 310 . 00
6 10" Gate Valve 1 EA 21800 . 00
7 6" C900 PVC 40 LF $ 19 . 50 $ 780 . 00 -
8 6" Gate Valve 2 EA $ 11654. 00 $ 3308 . 00 -
9 Rehab WetWell w/ B Pass Pum 1 LS $ 261301 . 00 $ 267301 . 00
10 Lift Station Dewatenn 1 LS $ 11500 . 00 $ 1 , 500 . 00
11 12" Wet Ta w/Gate Valve 2 EA $ 5 , 600 . 00 $ 11 , 200. 00
Change Order #1 Total Cost $ 49 , 069 . 00
Hand digging of a trench is from exiting grade to bottom of the trench .
Partial hand digging of a trench is not considered a hand dug trench .
The rate for hand digging is $32. 50 per linear foot and will be an addition to the contract if encountered .
fa 0'7
Earl H . Masteller E. , DEE Date
President
Masteller & Moler, Inc.
Prepared by Masteller & Moler, Inc.
/Ikb
Rev 5 Revised
File #0649