HomeMy WebLinkAbout2007-448 SECTION 00450
CHANGE ORDER FORM
CHANGE ORDER NO. 1
DATE : December 18 , 2007 CONTRACTOR : TLC Diversified of Palmetto Florida
OWNER: INDIAN RIVER COUNTY AGREEMENT DATE : February20 2007
PROJECT NAME : Master In-Line Sewer Pump Station at the South R O WTP 1550 9'h St SW
The following changes are hereby made:
Original CONTRACT PRICE $ 1 ,504,783.00
Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER $ N/A
Net Increase ( Decrease) Resulting from this CHANGE ORDER $ 12 . 226 . 27
The current CONTRACT PRICE including this CHANGE ORDER $ 1 , 517 . 009. 27
ORIGINAL CONTRACT TIME: No. Days 210
Current CONTRACT TIME adjusted by previous CHANGE ORDER No. Days N/A
Net Increase (Decrease) Resulting from this CHANGE ORDER No. Days 90
Current CONTRACT TIME Including this CHANGE ORDER No. Days 300
CHANGES ORDERED :
I . GENERAL
Misc. additions to contract.
II . REQUIRED CHANGES
III . JUSTIFICATION
The change order is necessary to add a flow meter to the force main to the South WWTF,
upgrade the telemetry antenna and upsize the sample line valves , as well as increase the
allowable time to do the work.
IV. WAIVER
This Change Order constitutes full and mutual accord and satisfaction for the adjustment
in contract price or time as a result of increases or decreases in costs and/or time of
performance caused directly and indirectly from the change.
This Change Order represents an equitable adjustment to the contract and
CONTRACTOR hereby waives all rights to file a claim on this Change Order after it is
properly executed.
Attachment 2
Change Order Farm
DD450 - I -
C\Dowments and Se¢ingsglambersonVurel getfings\Temporary lntemet Files\Covmvt.OutlookVaHU12HUWAA - NASD - Change Order No 1 - GOPoon Revisaddac
V. APPROVAL AND CHANGE AUTHORIZATION
Acknowledgements:
The aforementioned change, and work affected thereby, is subject to all provisions of the
original contract not specifically changed by this Change Order; and ,
It is expressly understood and agreed that the approval of the Change Order shall have
no effect on the original contract other than matters expressly provided herein .
Change Order Request By: Gordon Sparks
Environmental Engineer
Department Utility Services,
C
Indian River County , Florida
Signature
Contractor: TLC Diversified of Palmetto, Florida
/1 III 4
Signature and Date
APPROVED BY:
INDIAN RIVER COUNTY, FLORIDA
By: Sandia L.: Bowdeh , ,tChairman ,
Board of County Conirfussioners
otL)L
Sighature and Date
* * END OF SECTION
Change Order Form
004i0 - - 2 -
CDocuments and Sevings\dambersomLocal SeningstTemporary Internet HWContent.Outlook04HU 12g ,AAA - 00450 - Change Order No 1 - Gordon Revised.clot
TLC Diversified, Inc. Spreadsheet Report Paye 1
Valve Swap 1013112007 9;01 AM
Bid
It LoeatiTakeoff
ion
m . Quantity Grand Total Notes
001 Bond
Bond_ 1 .001s 62 .
001 Bond 1 .00 LS 62
002 General Conditions
General Conditions _ 1 .00 Is 11438
002 General Conditions 1 .00 LS 1 ,438
003 20" Valve Change Over
20" Valve Change Over 1 .00 1s 1 ,083 '.
20" Pipe Support 1 .00 Is 1450
20" Megalug W/Acc Kits 316 SS 1 .00 Is 584
Labor 1 .00 Is 2153
9 5,370
003 20" Valve Change Over 1 .00 LS 370
Estimate Totals
Description Amount :Totals Hours Rate Cost BasisCost per Unit Percent of Total
Labor 31879 52.300 hrs 3,879. 150 /LS 56.47%
Material 2,534 2,534.260 /LS 36.89%
Subcontract
Equipment 394 1 .290 hrs 394.340 ILS 5.74%
Other 62 61 , 860 /LS 0. 90%
6,869 6,869 6,869. 000 /LS 100,00 100.00%
Total 61869 6,869.000 /LS
NOV 0 9 2007
UTIL 1 -1 - 1E '�
We agree to do the above estimated work for the price of 6,870 dollars
Signature Signature
Print Name Print Name _
Date Date
Attachment 1
i of 3
TLC Diversified, Inc. Spreadsheet Report Page 1
RTU Antenna Upgrade 1013012007 3 .02 PM
Bid Item W Pe Location Phase Description Takeoff Quantity Grand Total Unit Grand
Price Total Notes
001 Bond 1 .00 LS 23. 13 /LS 23
002 General Conditions 1 .00 LS 384. 11 ILS 384
003 _ Antenna Upgrade- 1 .00 LS 29048.97 /LS 2,049
00
We agree to do the above estimated work for the price of 21456 dollars
Signature Signature
Print Name Print Name
Date Date
Attachment 1
2of3
TLC Diversified, Inc. Spreadsheet Report Page 1
2Inch SS Valves 111612007 12:25 PM
Bid Item Work Grand Grand Total Unit
Location Phase Description Takeoff quantity Notes
Type Total Price
001 Bond 1 .00 LS 27 27. 14 /LS
002 General Conditions 1 .00 LS 397 397.39 /LS
I_ 003_ 316 S/S Ball Valves 1 .00 LS 22477 2,476.74 ILS
2.3
We agree to do the above estimated work for the price of 2,903 dollars
Signature Signature
Print Name Print Name
Date
Date
Attachment 1
3 of 3