INDIAN RIVER COUNTY , FLORIDA avo �
CHANGE ORDER NO . 1
PRCJECT: Sectors 3 and 5 Emergency Beach Restoration Project No . 0502
CONTRACTOR : Ranger Construction Industries , Inc.
4510 Glades Cut Off Road , P . O . Box 14589 , Ft . Pierce , FL 34979
DATE OF ISSUANCE : 13-Jun -06
ITEM DESCRIPTION OF CHANGE QUANTITY Unit QUANTITY UNIT PRICE PRICE
No. REDUCTION PRICE INCREASE DECREASE
1 North Project Area Sector 3
Provide Fill 125 , 000 Tons 14 , 110 . 10 $8 .25 $ 116 ,408 . 33
Deliver Fill 125 , 000 Tons 14 , 110 . 10 $6 . 85 $ 96 , 654 . 19
Grade Fill 125, 000 Tons 14 , 110 . 10 $3 . 50 $49 , 385 . 35
2 South Project Area Sector 4
Provide Fill 170, 000 Tons 591465 .92 $8 .25 $490 , 593 . 84
Deliver Fill 170, 000 Tans 59 ,465 . 92 $5 . 35 $318 , 142 . 67
Grade Fill 170 , 000 Tons 59 ,465 . 92 $5 .80 $344 , 902 . 34
3 Sea Grape Trail Park Resurfacing
Overbuild/Leveling Asphalt 106 Tans $ 117 . 50 $ 12 ,455 . 00
1 " Type S III Asphalt Overlay 11700 SY $5 .40 $9 , 180 . 00
Temcrary Striping 1 LS $726 . 00 $726 . 00
Permanent Striping 1 LS $ 1 , 555 .40 $ 1 , 555 .40
4 Turtle Trail Park Resurfacing
Overbuild/Leveling Asphalt 128 Tons $ 117 . 50 $ 15 , 040 . 00
1 " Type S III Asphalt Overlay 2 , 050 SY - $5 .40 $ 11 , 070 .00
Temorary Striping 1 LS - $913 . 00 $ 913 . 00
Permanent Striping 1 LS $ 1 , 775 .40 $ 1 , 775 .40
TOTAL INCREASE/DECREASE IN CONTRACT PRICE $52 , 714 .80 $ 1 ,416 , 086 . 71
NET CHANGE IN CONTRACT AMOUNT $ 1 , 363 , 371 .91
CURRENT CONTRACT PRICE/TIME
AS ADJUSTED BY PREVIOUS CHANGE ORDERS $5 , 999 , 999 . 00
NET CHANGE IN CONTRACT PRICE/TIME
DUE TO THIS CHANGE ORDER ($ 1 , 3635371 . 91 )
NEW CONTRACT PRICE/TIME INCLUDING
THIS CHANGE ORDER $4 , 636 , 627 . 09
NEW CONTRACT COMPLETION DATE August-06
Sectors 3 and 5 Emergency Beach Restoration Change Order # 1 —Updated 6_ 1 9 06
PROJECT MANAGERS RECOMMENDATION
I have examined the above changes . They are necessary to satisfactorily complete the Contract. The
pr'c changes are reasonable and I recommend that the changes be made .
612b] VV
AL
In an River Coun DATE
C astal Engineer
CONTRACTORS APPROVAL
I agree that the above chan es in said Contract , in accordance with Specifications for
the pric a es own a s tisfactory .
OGCONTRACTOR DATE —T
Ranger Construction u tries , Inc.
INDIAN RIVER OUNTY BOARD OF COUNTY COMMISSIONERS
Arthur , R .: Neu ' er�er,, Chairm Date
�.
Y W k
a,
Attest :
c ^ Jeffery K Barton ClkY of Court
Approved!
seph A. Baird ,1County Administrator
APPR VED AS TO FORM
AN UFFI _ ENCY
B
MARIAN E .
SSISTANT COUNTY ATTORNEY
Sectors 3 and 5 Emergency Beach Restoration Change Order # 1 _Updated 6_ 1 9 06
Sectors 3 and 5 Emergency Dune Restoration Project
Total Quantities Delivered
Orginal Contract Quantity 295,000.00 Tons
Reduced Project Quantity Placed 221 ,423.98 Tons
Sector 3 Sector 5
110,889.90 Tons 110,534.08 Tons
Percent Of Contract Quantity Placed 75.06%
Total Orginal Contract Price $5, 9990999.00
Quantity Reduction Change Order to the Contract 24. 94%
Modified Schedule of Values
Construction Item Unit Amount Quantity Amount Reduction
Mob/Demob $286,089.00 1 $2869089.00
North Project Area - Sector 3
Provide Fill $8.25 110889.90 $914,841 .68 ($1169408.33)
Deliver Fill $6.85 110889.90 $7599595.82 ($96,654. 19)
Grade Fill $3.50 110889.90 $388, 114.65 ($49,385.35)
South Project Area - Sector 5
Provide Fill $8.25 110534.08 $911 ,906. 16 ($490,593.84)
Deliver Fill $5.35 110534.08 $5913357.33 ($318, 142.67)
Grade Fill $5.80 110534.08 $641 ,097.66 ($344,902.34)
Site Restoration $683950.00 1 $68, 950. 00
As-Built Survey $21 ,960.00 1 $21 ,960.00
Change Order Contract Price $4 M3,9112,29 ($19416; 86.7E
Change Order Reduction Amount ($1 ,416,086.71 )
JUN . 19 , 2006 3 : 31 PM RANGER FT PIERCE
ti N0. 044 P . 1
Lkoft 101 Sansburys Way
angeV West Palm Beach, FL33411
ConstructionG Phone: (581 ) 793-9400
Lxiustrimr Inc. Fax: (561 ) 7904332
www.rangerconstruction. com
CHANGE ORDER REQUEST
Submitted To; IRC COASTAL ENGINEERING Date: 15-Jun-06
Phone: (772) 567-8000
Address : 1840 25TH STREET Fax: (772) 778-9391
VERO BEACH , FL 3: :960 Job Name: IRC BEACH RESTORATION
SECTOR 3 & 5
Job Location : SEA GRAPE & TURTLE TRAIL
Contact: JONATHAN GORHAM Prop. Owned By: INDIAN RIVER COUNTY
COR 1 (REVISED) - ASPHALT RESURFACING @ SEAGRAPE AND TURTLE TRAIL
ITEM No, DESCRIPTION QUANTITY UNIT UNIT PRICE EXTENSION
SEA GRAPE TRAIL PARK
10 OVERBUILD/LEVELING ASPHALT 106. 000 TN $ 117. 50 $ 12 ,455. 00
20 1 " TYPE $ III ASPHP LT OVERLAY 11700.000 SY $5.40 $9, 180, 00
30 TEMPORARY STRIP ING 1 . 000 LS $726.00
40 PERMANENT STRIPING $726.00
1.000 LS $ 1 , 555.40 $ 11555.40
TURTLE TRAIL PARK $231916.40
50 OVERBUILD/LEVELING ASPHALT 128. 000 TN $117.50 $ 15,040. 00
60 1 " TYPE 5 III ASPHPLT OVERLAY 21050. 000 Sy $5.40 $ 11 ,070. 00
70 TEMPORARY STRIP ING 1 .000 LS $913. 00 $913. 00
80 PERMANENT STRIPING 1 . 000 LS $ 1 , 775 ,40 $ 1 ,775.40
$28 ,798.40
GRAND TOTAL $52,714 ,80
ACCEPTED: CONFIRMED:
Tho abwa pr1ma, sparancmiona and omidiflmos are aanaraclory ar i are hereby acoaplaa. Ranger Construction Industries, Inc. _
Buyer
Authorized
Signature Signature
Date Accepted Name & Title
as . Dale ect Mana er
Page 1 of 1