HomeMy WebLinkAbout2005-266 SECTION 00942 - Change Order Form
No . 2 :
DATE OF ISSUANCE : 7/08/05 EFFECTIVE DATE : 8/03/05
OWNER : Indian River Countv
CONTRACTOR Summit Construction Management Inc
Contract :
Project: Utilities Operations Complex
OWNER's Contract No . 6037 ENGINEER's Contract No . 6037
ENGINEER Brown and Caldwell
You are directed to make the following changes in the Contract Documents :
Description :
Deduct cost of Owner Direct Purchase of Materials (Ceco , Rexel Southern , Graybar) ;
increase cost of on -site sanitary sewer; extend contract time by 15 days .
Reason for Change Order:
County Direct Purchase of Materials ; revised design of on-site sanitary sewer system .
Attachments : ( List documents supporting change )
See attached Work Change Directive forms from Summit Construction .
CHANGE IN CONTRACT PRICE : CHANGEIN CONTRACT
TIMES
Description Amount Description Time
Original Contract Price $52148 . 921 Original Contract Time : (days or dates )
Substantial Completion : 300
Final Completion : 345
Net Increase (Decrease) from $(801 , 350 ) Net change from previous
previous Change Orders No . 0 to Change Orders No . 0 to 1 : (days )
1 Substantial Completion : 0
Final Completion : 0
Contract Price prior to this $4 , 347 . 571 Contract Time prior to this
Change Order: Change Order: (days or dates )
Substantial Completion : 300
Final Completion : 345
Net increase (decrease) of this $ 434 158 Net increase (decrease) this
Change Order: Change Order: (days or dates )
Substantial Completion : 15
Final Completion : 15
Contract Price with all approved $3 , 913 ,413 Contract Time with all approved
Change Orders : Change Orders : (days or dates )
Substantial Completion : 315
Final Completion : 360
ACCEPTED : ENDED , APPROVED :
Brad Schuh James . Nisse , T m4as . Lowther
By: B B
CONTRACTOR (Signature) Zate .:, 07/08/05
EER (Signature) OWNER ( ignature)
Date : `7 ( ( z e Date : 08 / 02 / 2005
00942 - 1 Summit Change Order No. 2