Loading...
HomeMy WebLinkAbout2006-304 INDIAN RIVER COUNTY, FLORIDA CHANGE ORDER NO. 4 J O y PROJECT NO: 9705B PROJECT: Oslo Road/Lateral "J" Canal CONTRACTOR: Lucas Marine Construction, LLC Bridge Replacement 3130 SE Slater Street ORIGINAL NTP: 25-Jan-06 Stuart, FL 34997 DATE ISSUED: 23-Aug-06 ITEM DESCRIPTION OF CHANGE QTY UNIT UNIT PRICE PRICE PRICE NO. INCREASE DECREASE 1 Remove and reinstall 60" RCP 1 LS $8,875.00 $8,875.00 ` $0.00 2 Install junction box 1 LS $12,550.00 $12,550.00 • $0.00 3 Thrustb1mking 1 LS $1 ,765.00 $1 ,765. 00 $0.00 4 530-34 Riprap 281 .57 TN $ 198. 00 $55,750.86 $0.00 5 1600-900 Watermain Removal 165 LF $58.75 $9,693.75 $0. 00 6 102-14 Traffic Control Officer 1 LS $6,000.00 $0. 00 $6,000. 00 7 1204 Subsoil Excavation 143 CY $36.00 $0.00 $5, 148.00 8 173-74 Cement (Pressure Grouting) 22.5 CY $500.00 $0.00 $11 ,250.00 9 430-11 -338 Concrete Pipe Culvert (SS) (Class III) (361) 24 LF $230.00 $0.00 $5,520.00 10 522-1 Sidewalk Concrete (4" Thick) 184 SY $39. 50 $0.00 $7,268.00 11 575-1 -1 Sad (Bahia) 6571 SY $2.00 $0.00 $13, 142.00 6" Yellow Skip Traffic Stripe (6'-10' Skip) 12 711 -34 (Thermoplastic) 146 LF $0.60 $0. 00 $87.60 13 711 -35-61 6" White (Solid) (Thermoplastic) 2050 LF $0.44 $0.00 $902.00 14 711 -35-241 24" White (Solid) (Thermoplastic) 12 LF $4. 06 $0.00 $48.72 15 711 -36-61 6" Yellow (Solid) (Thermoplastic) 3800 LF $0.44 $0.00 $1 ,672.00 16 1612-190-821201" PE WM (SDR 11 ) 55 LF $270.00 $0.00 $14,850.00 17 1613-140-12 20" DIP WM 60 LF $150. 00 $0.00 $9,000.00 SUBTOTAL $88,634.61 $74,888. 32 NET CHANGE $13,746.29 ORIGINAL CONTRACT PRICEITIME $2, 188,848.87 ORIGINAL SUBSTANTIAL COMPLETION DATE (Bridge Culvert) 25-May-06 120 Calendar Days ORIGINAL SUBSTANTIAL COMPLETION DATE 24-Jul-06 180 Calendar Days ORIGINAL FINAL COMPLETION 23-Aug-06 210 Calendar Days CHANGE ORDER NO. 1 $36, 905.00 CHANGE ORDER NO. 2 $17, 157.50 CHANGE ORDER NO. 3 $18,265.00 CURRENT CONTRACT PRICE/TIME $2,261 , 176.37 CURRENT SUBSTANTIAL COMPLETION DATE (Bridge Culvert) 8-Jun-06 14 Calendar Days CURRENT SUBSTANTIAL COMPLETION DATE 24-Jul-06 0 Calendar Days CURRENT FINAL COMPLETION 23-Aug-06 0 Calendar Days NEW CONTRACT PRICE/TIME INCLUDING $2,274,922.66 SUBSTANTIAL COMPLETION DATE (Bridge-Culvert) AFTER THIS CHANGE OR 8-Jun-06 0 Calendar Days ORIGINAL SUBSTANTIAL COMPLETION DATE AFTER THIS CHANGE ORDER 24-Jul-06 0 Calendar Days FINAL COMPLETION AFTER THIS CHANGE ORDER 23-Aug-06 0 Calendar Days ENGINEER'S RECOMMENDATION: I have examined the above changes. They are necessary to satisfactorily complete the contract. The price changes are reasonable and I recommend that the \ag s be made. e -Zo Janet B. Dunlap, P. .APro gine D e CONTRACTOR'S APPROV J I agree that the above ch s ' s i ont in acco lth Specifications forte price changes shown, are satisfactory. Z3 06 ade Diekman, Vice-President D to Lucas Marine Construction, LLC F1Public WorkMCapital Projects\Oslo Road Lateral J\Lucas MannelChange Orders and Work Change Directives\Work Change 2_BCCMemo.doo 8/232006 ACCEPTED BY: ((�� r ed�toI sufficiency: Dat J ph A. B ib Date my Administrator LMgt. Approved Date Board of County Commissioners 1171 Indian River Coun 9 / 12 /06 �1 60� Arthur R. Netiberge� _7. -' - Date Cti(a�i'�man Board of CouritylDommissloners 1`EC �.- 2 Date Deputy Clerk b J.�t. RARTON C EF 4 C:F^rJ1T COURT F:\Public Works\Capital Projects\Oslo Road Lateral J\Lucas Madne\Change Orders and Work Change DirecfiveslWork Change 2_BCCMemo.doc 812312006