HomeMy WebLinkAbout2006-069 IA it Document G701TM 11111111112001 Change Order PROJECT (Name and address): CHANGE ORDER NUMBER: 001 OWNER: 43rd Avenue Sub-Complex DATE: March 7, 2006 ARCHITECT: 43rd Avenue Vero Beach, Florida CONTRACTOR: TO CONTRACTOR (Name and address): ARCHITECT'S PROJECT NUMBER: 2102 FIELD: ❑ Chilber Construction Co., Inc CONTRACT DATE: AugustoA, 2005 v\Gx 90516 1h Place CONTRACT FOR: New Construction OTHER: ❑ Vero Beach. Florida 32970 THE CONTRACT IS CHANGED AS FOLLOWS: (Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives) Description Amount Additional Pipe Runs - Increase of 988 lineal feet $ 59,709.03 Additional Bond Expense Ca $. 1604 per $ 100 $ 95.77 Subtotal : $ 59,804.80 Contractor's Fee: $ 7, 176.58 CHANGE ORDER TOTAL: $ 66,981 .38 The original (Contract Sum) was $ 3, l 16,305.00 The net change by previously authorized Change Orders $ -000 , The (Contract Sum) prior to this Change Order was $ 3, 1 16,305.00 The (Contract Sum) will be increased by this Change Order in the amount of $ 66,981 .38 The new Guaranteed Maximum Price including this Change Order will be $ 3, 183,286.38 The Contract Time will be changed by Two ( 2 ) days. The date of Substantial Completion as of the date of this Change Order therefore is June 23, 2006 NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. Donadio & Associates, Architects, P.A. Chilberg Construction Co., Inc. Indian River County Board of County Commissioners ARCHITECT (Firm name) CO RACTOR (Fi name OWNER (Firm name) 609 17th Street, Vero Beach, FI 32960 90 6'h PI ce, er B fi, FI 32960 1840 25th Street, Vero Beach,F1329 ) AD R SS � ADDR ADDRESS B (Srgna ure) BY (Signnnur� tBignalu Anthony Donadio Steve Chilb6rg, Pre ent h A. Baird, County Administrator (Typed name (Typed nam (Typed name)) / DATE DATE 2 '0 u AIA Document G701Ta - 2001 . Copyright 79, 87, 2000 and 2001 by The American Institute of Architects. All rights reserved ARNING: This AIA® Document is protected by U. pyright L and International Treaties. Unauthorized reproduction or distribution of thl IAa Document, or 1 any portion of it, may result In ere civil an Aminal penalties, and will be prosecuted to the memu tent possible unde e I his document was produced by software :40:19 on 02/28/2006 under Order No. 1000192296_1 which a fres 8/8/2006. and i t re e. User Not e fi55092) ) / Revlewcda and Recommended for Approval W� ) -�_)////0j' Lvnn Williams. project Manaeer Thomas W. lVme. General S v e s rector U Jason Brown, Budget CHILBERG CONSTRUCTION COMPANY , INC . CHANGE ORDER WORKSHEET DATE : 20- Feb-06 PROJECT : 43rd Ave Sub-Complex DESCRIPTION : Orignal contract 382LF @ $53 . 69 per LF and 3 manholes 20 , 510 . 00 New Pipe Runs 1 , 370 LF @ $53 . 69 per LF and 3 manholes 73 , 555 . 30 tax 41413 . 00 Admininstrative 957 . 00 Total Change 58 ,415 . 30 CODE TASK VENDOR AMOUNT GEN'L CONDITION A 01025 General Liability Insurance C . C . C ./Zurich Insurance Services 268 . 71 B 01030 Builders Risk Insurance C . C . C ./Zurich Insurance Services175 . 25 C 01035 Worker's Compensation C . C . C ./FCCI 190 . 08 D 01620 Auto Expense Chilberg Construction Company E F LABOR A 01041 Project Management Chilberg Construction Company B 01043 Project Supervision Chilberg Construction Company A581415 . 00 C D SUBCONTRACTOR A 02375 Pipe runs & Manholes (add ' I ) Precision Paving B C D MATERIALS A B C D EQUIPMENT A B PREPARED BY: SUBTOTAL 59 , 709 . 03 NOTE. General Liability Insurance .0046 on Subs and .0497 on Labor Overhead Builders Risk Insurance .30 per $ 100.00 Profit/Builder's Fee % 71176 . 58 Workers Comp . 0476 Supero/.2880 Carp ./. 0059 Mgt. Bond Expense @. 1604 per 100 . % 95 . 77 Auto Expense is $ 3.73 per hour TOTAL 66 , 981 . 39 See attached. uli i - i cuuo ut : oo r3e lic 40u H1 / / FRECiS10N PAUZNG 10002 Precision Paving & Exlaavation, Inc . Mailing adder : Phone: 772-468.1313 - 8430 Hidden Pins Road Phone: 772.873-0$38 -- Lo=W @ 2800 Kings Flay. Fax: 772468-1071 precision Pavia PL Pince• Fl. 34943 Email: pre�pavQbdlsoNih.ne[ g Submitted To date Georgie Fisher January 13, 2006 Chilberg Construction 905 e place Chan `'Qtrler-l+i;C) Vero Beach, F132960 ;`OrlrginaContractAate August 22, 2005 Orlgmal '':Contract NA # 1213 Project:Name , 43 " avenue sub complex : County Comtuisioners Chanlge (Add or;.Delete tile=followin: rk woto :the ori ual contract Sewer Work: Added : New pipe Runs: 1 ,3 70 Linear Feet Old .pipe Runs : 382 Linear Feet Total added pipe Runs: 988 Linear Feet Work area Changed : The new pipe runs and manhole locations are located in more difficult areas to work in for various reasons. Proximity of location to Toad will require some added M. 07 (maintenance of traffic). Chan *e order amount $ 58,415.00 Revised Amount $78,925.00 Original Contract Amount $20,510.00 Payment to be made as followChange Order Amount $584415.00 s ❑ We agree to furnish labor and materials in Additional work to be preformed under the complete accordance with the above LI same in conditions has specified in the original specifications at the stated above contract price unless otherwise stipulated Signature: Precision Paving Representative Date : Signature By; Date : Note: Tbiis change order becomes part of the original contract when signed. Received lime Jan . l3 • 1 5 8 P M uli laic duo _V I ; a rAA 'r rz you YiII PRECISION PALLING 4 ' 0 003 Precision Paving & Excavation, Inc . Mailing address: Phonc: 772-068-1313 8430 Hidden Pines Road Phone: 772-873-0538 ; js Locffitd @ 2800 Kings Hvry. Fax: 772-468-1071 FL Picrcc, FL 34945 Email: prccP9V@be11sou1h_= Precision,Paying 3ammry 13 , 2#0S George: Fisher Chilbelg Construction Company Phone: (772) 978- 1707 Fax (772) 978- 1709 Rx: Request for Change Order Dear George: Our original bid was $20, 510.00 for approximately 382 linear feet ofpipe and 3 manholes. Approximately $53 .69 per foot including manholes. Our new cost with the work order change is $78,925 .00 for approximately 1 ,370 linear kiet of pipe @ $53 . 69 per foot ($73,925 .00) and 3 manholes. We estimate it will lake vs 5%o- 10%4 longer to install the Pipe in the new location 20' -30' from edge of the pavement. Maneuvering equipment in that space slows us down a bit, also we may need to do some maintenance oftraflic and the pipe and sewer manholes are deeper than the original depth. If we use the conserrative side of the 5%-10% additional time, say 6%o and administrative fees bring this cost to : $ 73, 555 .00 Total x 1 .06% Tax $ 77,968.00 + 957 . 00 Addtl_ Admin Fees $ 78,92S.9B We feel we are beirl;; conservative because with the new depth there is a chance we may need to do additional well pointing as well. Due to our desire to maintain a good solid working relationship with Cbiliberg Construction we are approximately $5,000.00 less than we probably should be, Sincerely, Sam Brink Precision Paving & Excarmion, Inc. Received Time Jan . i3 . 1 : 58PM