WABASSO BEACH PARK RESTORATION
This Work Order Number CT-3 is entered into as of this _th day of September 2008
pursuant to that certain Continuing Contract Agreement for Professional Services entered into as of
December 13 , 2005 ("Agreement") , by and between Indian River County , a political subdivision of the
State of Florida (" COUNTY") and Coastal Technology Corporation ( " Consultant") .
The COUNTY has selected the Consultant to perform the professional services set forth on
Attachment 1 , attached to this Work Order and made part hereof by this reference . The professional
services will be performed by the Consultant for the fee schedule set forth in Attachment 2 , attached
to this Work Order and made a part hereof by this reference . The Consultant will perform
the
professional services within the timeframe more particularly set forth in Attachment 3 , attached to this
Work Order and made a part hereof by this reference all in accordance with the terms and provisions
set forth in the Agreement . Pursuant to paragraph 1 . 4 of the Agreement , nothing contained in any
Work Order shall conflict with the terms of the Agreement and the terms of the Agreement shall be
deemed to be incorporated in each individual Work Order as if fully set forth herein .
IN WITNESS WHEREOF , the parties hereto have executed this Work Order as of the date first
written above .
CONSULTANT BOARD OF COUNTY COMMISSIONERS
Coastal Technology Cprporation OF INDIAN RIVER COUNTY
r,.
By : B _
Sa dra L . Bowden , Chairman
Title : president
Attest : J . K . Barton , Clerk of Goqrt
By NKkzzsa-
Deputy Clerk
k
it , CountyAdmini trator
as to form and legal sufficiency :
Fell ,
Senior Assistant County Attorney
1 of 6
ATTACHMENT 1 TO WORK ORDER CT- 3 — PROFESSIONAL SERVICES
WABASSO BEACH PARK RESTORATION
1 . INTRODUCTION
In September 2004 , Hurricanes Frances and Jeanne severely damaged Wabasso Beach Park ( Park) ;
the storms destroyed the boardwalk , restroom , pavilions and portions of the parking area and roadway
within the Park . Under prior authorization the CONSULTANT provided design and permitting services
to provide for restoration of the Park (Project) as related to paving , grading , boardwalk , water service ,
sewer, beach access stairs , ADA ramp and associated improvements . The work under this Work Order
provides for construction phase services in support of overall Construction Contract Administration and
day-to-day construction observations to be performed by the COUNTY. Construction is expected to
require about 210 calendar days .
Services are proposed under the Continuing Contract Agreement for Professional Services between
COUNTY and CONSULTANT, dated December 13 , 2005 . CONSULTANT shall sub-contract Task 1
water and sewer related services to Carter Associates , Inc . (CAI ) . The following describes the work to
be performed :
2 . SCOPE
TASK 1 — CONSTRUCTION PHASE SERVICES — WATER & SEWER
In general , CONSULTANT , through its ' subcontractor , Carter and Associates , will provide
construction phase services relative to the water & sewer improvements . CONSULTANT will :
Task 1a - Project Administration
A . Project Management . Regularly confer with the COUNTY and Contractor to monitor the progress
of construction .
B . Administrative Services . Provide services such as : word processing ; filing ; mailing ; reproduction ;
and deliveries to document and support Task 1 services .
Task 1 b — Basic Engineering Services
A . Construction Administration . Provide clarification via responses to Contractor' s RFI requests if
answers are not clearly identified in Contract Documents . Draft , review , comment and document up to
2 Contract Change Orders .
B . Shop Drawinq Review . Review and mark up water and sewer shop drawings for conformance to
permitted plans and specifications . Forward copies to IRCUD for review , comment and reply .
C . Final Certifications . Upon completion of engineering "As- Built' drawings (see Task le) and receipt
of required Contractor submittals , file completion certifications to : Florida DOT , Florida DEP water
and wastewater , and IRC Utility Department . File completion checklist with attachments to IRC
Utilities and assist Public Works to obtain IRCUD completion certificate .
Task 1c — Monthly Site Observations/Contractor Pay Application Review
2 of 6
Provide up to 6 monthly and 1 final engineering observations of completed water and sewer work to
confirm Contractor' s pay application quantities . Review and comment on 6 monthly and 1 final
Contractor' s payment requests .
Task 1 d - Site Observations
A . Routine Site Observations . Provide periodic construction observations sufficient to assure
conformance to permitted plans . Observe : gravity sewer and manhole installation and backfilling ;
directional bore gravity sewer : directional bore force main ; wet well installation and grouting ; pump
station mechanical equipment installations ; pump station drive ; roadway and easement restoration .
Observation time is based upon 3 hrs per daytimes 3 days per week times 8 weeks (total 72 hours ,
including travel time) . Should Contractor take more than 8 weeks to install the site water and sewer
systems , additional services will be required subject to COUNTY authorization beyond this Work
Order .
B . Water and Wastewater Completion Tests . Attend and witness water and force main pressure
tests , gravity sewer exfiltration test , and pump station start- up tests .
Task 1e - Engineering As -Builts
A . As- Built Drawings . From record documents and survey as-builts provided by the Contractor ,
revise the utility construction plans to indicate "as-built" utility conditions .
Task 2 — CONSTRUCTION PHASE SERVICES — SITE WORK & FDEP
In general , CONSULTANT will provide construction phase services to provide a basis for
CONSULTANT to :
o provide monthly reports and certify the construction to FDEP
o address design and /or permitting issues that may arise during construction relative to site work
and proposed improvements designed by the CONSULTANT .
CONSULTANT will :
(a) Schedule , prepare for and attend a pre-construction conference with FDEP , COUNTY and
the Contractor to address permit and construction requirements ,
( b) Confer with the COUNTY and Contractor to monitor the progress of construction ,
(c) Prepare up to 7 monthly project status reports and submit reports to FDEP ,
(d ) Perform up to 1 site visit every other week during construction to check construction for
compliance with the FDEP permit and Contract Documents ,
(e) Conduct a final site visit to check the construction for general compliance with the FDEP
permit ,
(f) Develop (with COUNTY and Contractor) , review and approve up to 2 change orders as
may become warranted ,
(g ) Review and comment on up to 6 monthly and 1 final Contractor' s payment requests .
( h) Provide a final certification of construction and submit to FDEP on behalf of COUNTY .
3of6
3 . DELIVERABLES
A . Final Water & Sewer Certification of Construction — "As- Built' drawings , certifications to :
Florida DOT , Florida DEP water and wastewater, and IRC Utility Department . Contractor
completion checklist .
B . FDEP Monthly Status Reports - prepare and submit to FDEP and COUNTY Monthly
Construction Project Progress Status Reports ,
C . Final FDEP Certification of Construction — provide final certification of construction in
accordance with FDEP Standard Permit Conditions ,
END ATTACHMENT 1
4of6
ATTACHMENT 2 to WORK ORDER NO . CT- 3
WABASSO BEACH PARK RESTORATION
1 . COMPENSATION
The COUNTY agrees to pay and the CONSULTANT agrees to accept , a not-to-exceed fee of
$ 34, 122 for services rendered according to Attachment 2 PROPOSAL of this WORK ORDER ,
2 . PARTIAL PAYMENTS
The COUNTY shall make monthly partial payments to the CONSULTANT for all authorized work
completed per the FEE SCHEDULE and pertaining directly to this project performed during the
previous calendar month . The CONSULTANT shall submit invoices monthly for services performed
and expenses incurred pursuant to this Agreement during the prior month .
The CONSULTANT shall submit duly certified invoices in duplicate to the Director of the Public Works
Department . For lump sum line items , the amount submitted shall be the prorated amount due for all
work performed to date under this phase , determined by applying the percentage of the work
completed as certified by the CONSULTANT , to the total due for this phase of the work . The amount
of the partial payment due the CONSULTANT for the work performed to date under these phases
shall be an amount calculated in accordance with the previous paragraph , less ten percent ( 10 % ) of
the invoice amount thus determined , which shall be withheld by the COUNTY as retainage , and less
previous payments . Per F . S . 218 . 74 (2 ) , the COUNTY will pay approved invoices on or before the
forty-fifth day after the COUNTY receives the CONSULTANT' s invoice .
Per F . S . 218 . 74 (2 ) , the ten percent ( 10 % ) retainage withheld shall be paid in full to the
CONSULTANT by the COUNTY , on or before the forty-fifth day after the date of final acceptance of
the Work by the Public Works Director,
Coastal CONSULTANT
Fee Summa y Tech ; CAI Total
s TO�II[ '^ �ti✓ E ', , '« «� .�. a�. mn-,. , R :e r � i3 a� r ,.i
. . .. ,, . . y.0 s`. X10 ,lll
� _ $ 4;963 $ 6, 50
aproject administration $ 140 $ 1 , 390 $ 1 , 530
b basic engineering services $419 ; $4 , 200 $4 , 619
c monthly site observations/contractor pay application review - 7 $ 336 ; $3 , 264 $3 , 600
d site observations - 3 per week $434 ; $4 , 464 $4 , 898
e engineering as-builts $ 168 $ 1 , 645 $ 1 , 813
TTR "I'JPIils ,* _ ; " ..,, _. �ar3 ' $'12 , , $0 . 17 , i62
a schedule and attend re-construction conference with FDEP staff $ 795 ; $ 795
b review COUNTY construction status reports $2 , 411 $2 , 411
c prepare Monthly Project Status reports and submit to FDEP - 7 $ 1 , 831 $ 17831
d 1 site visit every other week during construction - 15 $9 , 645 ; $9 , 645
e conduct final site visit $614 $614
develop , review and approve change orders - 2 $ 838 ; $ 838
review and approve general contractor payment applications - 7 $ 17174 $ 1 , 174
h prepare final construction certification & submit to FDEP $ 355 ; $ 355
Total Fees $ 19 , 159 ; $ 14 , 963 $ 34 , 122
5 of 6
ATTACHMENT 3 to WORK ORDER NO . CT= 3
WABASSO BEACH PARK RESTORATION
TIMEFRAME
CONSULTANT to complete Tasks 1 and 2 — Construction phase services within 210 days of start of
construction — concurrent with Contractor' s performance of Construction .