INTEROFFICE MEMORANDUM `S
TO : JOESEPH A. BAIRD, COUNTY ADMINISTRATOR
THROUGH: JIM W. DAVIS, P .E., PUBLIC WORKS DIRECTOR
FROM : JONATHAN C . GORHAM, PH . D , COASTAL RESOURCES MANAGER
SUBJECT: APPLIED TECHNOLOGY & MANAGEMENT
CONTRACT AMANDMENT # 12
DATE. MARCH 28, 2005
At the January 4, 2005 BCC meeting, the Board empowered the County
Administrator to sign Contracts and Change Orders pertaining to the
emergency beach restoration activities .
This attached Amendment # 12 to the Contract with Applied
Technology & Management Inc. Provides for construction phase
engineering services in support of the Sectors 3 &5 emergency beach
restoration project now underway. The Amendment adds $ 12,220 . 00 to
the Contract amount.
The Florida Department of Environmental Protection has agreed to pay
90% of the project costs (FDEP 2004 Hurricane Recovery Plan special
appropriated funds Contract No . H5IR1) for the Sectors 3& 5 project.
The County will share the remaining 10% of the project costs with
funding from the Beach Preservation Fund 128- 144- 572 .
If this proposed Amendment # 12 meets with your approval, please execute
both originals and return one original toernz
h the other original going to
the County Clerk's office. .s0 mssArlJ �
Please contact me with any questions at ext. 1568 .
F: \Public Works\JamesG\ FEMA DUNE REST'ORATION_2004-2005\memo Baird - Fischer Change Order 3.doc
INDIAN RIVER COUNTY
BEACH PRESERVATION PLAN
ENGINEERING DESIGN & PERMITTING
AMENDMENT NO. 12 TO THE PROFESSIONAL SERVICES AGREEMENT BETWEEN
APPLIED TECHNOLOGY AND MANAGEMENT, INC . , AND INDIAN RIVER COUNTY,
FLORIDA.
This is an amendment to the existing Professional Services Agreement (AGREEMENT)
dated April 27 , 1999 , between Applied Technology and Management, Inc . (CONSULTANT) and
Indian River County (COUNTY) . This amendment addresses changes in " Section III — Scope of
Services" and "Section V — Compensation" .
Amendment Description
This Amendment includes the following changes to " Section III — Scope of Services" :
The CONSULTANT shall complete the modified scope of services items in accordance with
tasks described in Exhibit "A"
This Amendment includes the following changes to " Section V — Compensation" :
Section V is being revised in response to Section III changes . The charges associated with the change
in project scope are in accordance with Exhibit "A" . The Section of the original AGREEMENT
entitled " Section V- Compensation" shall be revised to include compensation due to
CONSULTANT as outlined in Exhibit "A" .
This AGREEMENT is hereby amended as specifically set forth herein. All other sections of
the AGREEMENT shall remain in full force and effect, and are incorporated herein.
This Amendment No . 12 to the AGREEMENT regardless of where executed, shall be
governed by and construed by the laws of the State of Florida.
C :\DOCUME— I \ADMINI— I \L,OCALS— I \Temp\ATMAME- 1 . DOC
1
In witness whereof the parties have executed this Amendment this day of
2005 .
Applied Technology & Management, Inc . Indian River County, Florida
2770 NW 43rd Street, Suite B Board of County Commissioners
Gainesville, F132606 - 74/1 9 C�
By B
Michael Jenkins , Ph .D . , P . E . Joseph A. Baird
Coastal Engineering Team Leader County Administrator
W3 i NESS :
WI'iNESS :
.Corporate seal is acceptable in
place o' witnesses )
C ADOCUME-1 \ADMIN I-1 \LOCALS—I \Temp\ATMAM E- 1 . DOC
2
EXHIBIT " A"
SCOPE OF SERVICES AND PROJECT COSTS .
C:\DOCUME— I \ADMINI—I \LOCALS— I \Temp\ATMAME—I . DOC
3
ym
400 S. AUSTRALIAN AVE. , SUITE 855
WEST PALM BEACH, FL 33401 -5045
(561 ) 659-0041 FAX 659-3733
W W W.APPLIEDTM.COM
Scope of Work
March 14, 2005
Indian River County Preservation Projects
Hurricane Response Plan — Phase II
Sectors 3 & 5 Construction Phase Services
Introduction
To replace the dune sand lost from the Hurricanes Frances and Jeanne , a dune project was
designed and permitted as part of the Phase I efforts . The designed project will place
approximately 101 , 000 CY and 117 , 500 CY of material along the Sectors 3 and 5 , respectively ,
shorefronts . The typical fill placement density for this project ranges from 5 to 11 CY/ft. , and the
material would be placed solely landward of the mean high water line . A Coastal Construction
Control Line ( CCCL) Permit was acquired from the Florida DEP to construct the Sectors 3 & 5
Emergency Beach Restoration project .
Indian River County awarded a construction contract to Ranger Construction Industries , Inc.
(Contractor) . The Contractor will construct the project by truck- hauling sand from an upland
quarry (Stuart Mine ) , and will likely commence construction activities in March 2005 . Due to sea
turtle nesting constraints , the Contractor will place beach fill along the Sector 5 shorefront until
May 1St , 2005 and will remobilize and recommence construction activities on November 1St,
2005 . This Scope of Work will provide Indian River County with assistance in the construction -
phase administration and supervision . Due to potential of additional construction projects for
Sectors 1 & 2 and Sector 7 in the 2005/2006 dredging season , this Scope of Work is limited to
services through Spring 2005 mobilization — a separate Scope of Work will be developed prior
to the recommencement of this project on November 1 St
Applied Technology & Management, Inc. (ATM ) proposes the herein described Scope of Work
to assist Indian River County ( County) with professional coastal engineering services for the
Sectors 3 & 5 Hurricane Response Plan — Phase II .
Task 1 — Weekly Inspection and Meetings
During the construction phase of this project, ATM will provide construction services to assist
the County with site inspections and construction administration . ATM will provide weekly site
inspections and assistance with any issue that may arise from the Contractor. ATM will ensure
that the project is constructed in accordance with the issued CCCL permit and contract
documents . Under this task , ATM will perform the following :
1 ) Attend weekly meetings with the County and Contractor to provide assistance in
resolving any issues that the have arisen and provide guidance to the County and the
Environmental & Coastal Engineers, Scientists & Management Consultants
Scope of Work
Hurricane Response Plan — Phase II
Page 2 of 2
Contractor for the work planned the upcoming week . ATM will document observations
coincident with the site inspections and weekly meetings .
2 ) ATM will review interim submissions from the Contractor, including surveys , photos , and
correspondence .
3 ) The County will administer the Contractors payment requests , and ATM will provide the
County payment recommendations for the Contractor' s invoices .
4 ) Prepare and submit to the Florida DEP the permit- required monthly progress reports .
ATM effort will be commensurate with the hours and cost estimates provided within this Scope
of Services .
H :\jobs\04-990 IRC Hurricane Rspns - Phs 1 -Permit App\Scope and Budget\Sectors 3 and 5 Const draft 030205. doc
Environmental & Coastal Engineers, Scientists & Management COIZSnitants
Indian River County Beach Preservation Projects -
Hurricane Response Plan - Phase II
Sectors 3 5 Construction Phase Services
ATM Other
ATM Direct Costs
Project Staff ATM Drafting/ ATM ATM ATM Total (ODC's) & Total Task
Task Description and Breakdown Manager Engineer Technician AutoCad Clerical Surveyor Labor Equipment Budget
Weekly Inspection and
Task 1 Meetings
1 . 1 WeekIv Inspection 4 65 8 $89270 $490 $8 , 760
1 . 2 Payment Recommendations 2 8 4 $ 1 ,440 $60 $ 1500
1 . 3 DEP Submittals and Routine Corres on 2 12 4 $ 1 , 880 $80 $ 12960
Total Cost - Task 1 8 85 0 0 16 0 $ 11 , 590 $630 $ 12,220
Total Cost - All Tasks $ 1 , 120 $9 , 350 $0 $0 $ 1 , 120 $0 $ 11 ,590 $630 $ 122220